505E.2 Compliance Deadlines.

San Francisco Building Inspection Commission Codes · 2022 edition · updated 2026-08-28 · San Francisco

TABLE 5E-A

Compliance Deadlines (in years [1] )

Compliance Tier Submission of
Screening Form and
Optional Evaluation
Form
Submittal of Permit
Application with Plans
for Seismic Retrofit
Work
Completion of Work
And Issuance of CFC
I 1 2 4
II 1 3 5
III 1 4 6
IV 1 5 September 15, 2021
1   All time periods are in years measured from 90 days after the operative date of this Chapter.