1306A.1 Building additions.
San Francisco Building Inspection Commission Codes · 2022 edition · updated 2026-08-28 · San Francisco
For building additions where the sum of concurrent building permits by the same permit applicant would increase the floor area of the space in a building by more than ten percent, the permit applicant shall obtain a valid water conservation inspection and shall comply with the applicable water conservation measures required by this chapter as a condition for issuance of a Certificate of Final Completion and Occupancy by the Department upon completion of the addition.
1306A.1.1 Scope. This subsection shall apply to the entire building.