Division 9 — Fire Permit Procedures
§129.0907 Issuance of a Fire Permit and Closing of a Fire Permit Application
San Diego Zoning Code · 2026-06 edition · updated 2026-07-25 · San Diego
(a) A Fire Permit may be issued after all approvals have been obtained and the required fees have been paid.
(b) A Fire Permit shall not be issued until associated permits have been issued.
(c) If one year has elapsed since the date a Fire Permit application is deemed complete and the applicant has not requested that a Fire Permit be issued, the application file shall be closed. Plans and other data submitted for review may be returned to the applicant or destroyed by the Building Official. To reapply, the applicant shall submit a new Fire Permit application with required submittal materials and shall be subject to all applicable fees and regulations in effect on the date the new application is filed.
(d) The Fire Permit application file for City projects shall be closed after two years have elapsed since the date the Fire Permit application is deemed complete.
(e) The Building Official may extend a Fire Permit application one time, for a period not exceeding 180 calendar days, if the Building Official determines that circumstances beyond the control of the applicant prevented issuance of the Fire Permit.
(“Issuance of a Fire Permit” added 4-6-2016 by O–20624 N.S.; effective 5-6-2016.) (Retitled to “Issuance of a Fire Permit and Closing of a Fire Permit Application” and amended 4-9-2020 by O-21181 N.S.; effective 5-9-2020.)
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — San Diego Zoning Code
- Chapter 9
- Division 2 — House Numbers
- Division 3 — Advertising Displays Adjacent to Scenic Freeways,…
- Division 1 — General Provisions and Definitions
- Division 2 — Financing Facilities
- Division 3 — Bonds
- Division 1 — Housing Code
- Division 2 — Mobilehome Parks and Special Occupancy Parks
- Division 3 — San Diego Housing Commission
- Division 4 — Interim School Facilities Financing Ordinance
- Division 6 — Housing Impact Fees On Commercial Development
- Division 7 — Residential Tenant Protections
- Division 8 — Prohibition of Discrimination Based on a Tenant’s…
- Division 9 — Notice of Tenant’s Right to Operate a Daycare Home
- Division 10 — Affordable Housing Preservation
- Division 11 — Prohibition of Anti-Competitive Automated Rent P…
- Division 12 — Residential Tenant Utility Fees
- Division 1 — In General
- Division 2 — Responsibilities of City Council
- Division 3 — Administration of Program
- Division 5 — Designation of Residential Rehabilitation Areas a…
- Division 6 — Limitations on Amount of Loan
- Division 7 — Terms of Conventional RAP Loans
- Division 9 — Miscellaneous Provisions
- Division 19.7 — The Centre City Planned District
- Division 19.8 — The Centre City Planned District
- Division 2 — Land Development Authorities and Advisory Boards
- Division 2 — Fees and Deposits
- Division 3 — Notice
- Division 4 — Public Hearings
- Division 5 — Decision Process
- Division 1 — Definitions
- Division 2 — Rules for Calculation and Measurement
- Division 2 — Enforcement Authorities For the Land Development …
- Division 4 — Procedures For Abatement of Unsafe, Dangerous,
- Division 1 — Adoption And Amendment Procedures for Land Use Pl…
- Division 1 — Zoning and Rezoning Procedures
- Division 3 — Zoning Use Certificate Procedures
- Division 5 — Residential High Occupancy Permit
- Division 6 — Mobile Food Truck Permit
- Division 1 — General Subdivision Procedures
- Division 2 — Certificate of Compliance
- Division 4 — Tentative Maps (Added 12-9-1997 by O-18451 N.S.)
- Division 5 — Parcel Maps (Added 12-9-1997 by O-18451 N.S.; eff…
- Division 6 — Final Maps
- Division 7 — Merger of Parcels (Added 12-9-1997 by O-18451 N.S…
- Division 8 — Reversion to Acreage
- Division 9 — Public Right-of-Way Vacations
- Division 10 — Easement Vacations
- Division 3 — Conditional Use Permit Procedures
- Division 4 — Neighborhood Development Permit Procedures (Added…
- Division 5 — Site Development Permit Procedures
- Division 6 — Planned Development Permit Procedures (Added 12-9…
- Division 8 — Variance Procedures
- Division 1 — General Review Procedures for Previously Conformi…
- Division 2 — Review Procedures for Previously Conforming Signs
- Division 1 — General Procedures and Authorities for Implementa…
- Division 2 — Procedures for Determination of
- Division 3 — Procedures for Preparation and Review of Environm…
- Division 1 — General Construction Permit Authority and Procedu…
- Division 2 — Building Permit Procedures
- Division 3 — Electrical Permit Procedures (Added 12-9-1997 by …
- Division 4 — Plumbing/Mechanical Permit Procedures
- Division 6 — Grading Permit Procedures (Added 12-9-1997 by O-1…
- Division 7 — Public Right-of-Way Permits
-
▸ Division 9 — Fire Permit Procedures
Overview- §129.0901 Purpose of Fire Permit Procedures
- §129.0902 When a Fire Permit Is Required
- §129.0903 General Rules for Fire Permits
- §129.0904 Qualifications for Obtaining a Fire Permit
- §129.0905 How to Apply for a Fire Permit
- §129.0906 Decision Process for a Fire Permit
- §129.0907 Issuance of a Fire Permit and Closing of a Fire Perm…
- §129.0908 Fire Permit Expiration
- §129.0909 Required Inspections for a Fire Permit
- Chapter 13 — Zones
- Division 4 — Residential Base Zones
- Division 5 — Commercial Base Zones
- Division 6 — Industrial Base Zones
- Division 7 — Mixed-Use Base Zones
- Division 2 — Airport Approach Overlay Zone
- Division 3 — Airport Environs Overlay Zone
- Division 6 — Sensitive Coastal Overlay Zone
- Division 7 — Mobilehome Park Overlay Zone (Added 12-9-1997 by …
- Division 8 — Parking Impact Overlay Zone
- Division 9 — Residential Tandem Parking Overlay Zone
- Division 10 — Transit Area Overlay Zone
- Division 11 — Urban Village Overlay Zone
- Division 12 — Mission Trails Design District
- Division 13 — Clairemont Height Limit Overlay Zone
- Division 15 — Airport Land Use Compatibility Overlay Zone
- Division 16 — Community Enhancement Overlay Zone