SEC. 5.11 DEFINITIONS¶
Unless specifically defined below, words or phrases used in this ordinance shall be interpreted so as to give them the meaning they have in common usage and to give this ordinance its most reasonable application.
a. Area of Special Flood Hazard means the land in the floodplain within a community subject to a one percent or greater chance of flooding in any given year.
b. Base flood means a flood which has a one percent chance of being equalled or exceeded in any given year (also called the "100-year flood"). Base flood is the term used throughout this ordinance.
c. Building - see Structure
d. Development means any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials.
e. Flood or Flooding means:
a general and temporary condition of partial or complete inundation of normally dry land areas from: the overflow of inland or tidal waters; the unusual and rapid accumulation or runoff of surface waters from any source; or mudslides (i.e., mudflows) which are proximately caused by flooding as defined herein and are akin to a river of liquid & flowing mud on the surfaces of normally dry land areas, as when earth is carried by a current of water & deposited along the path of the current.
the collapse or subsidence of land along the shore of a lake or other body of water as a result of erosion or undermining caused by waves or currents of water exceeding anticipated cyclical levels or suddenly caused by an unusual and unforeseeable event which results in flooding as defined in this definition.
Disasters & Emergencies
f. Floodplain or Flood-prone Area means any land area susceptible to being inundated by water from any source - see Flooding.
g. Floodplain Administrator is the individual appointed to administer and enforce the floodplain management regulations, the Director of Public Works.
h. Floodplain management means the operation of an overall program of corrective and preventive measures for reducing flood damage and preserving and enhancing, where possible, natural resources in the floodplain, including but not limited to emergency preparedness plans, flood control works, floodplain management regulations, and open space plans.
i. Floodplain Management Regulations means this ordinance and other zoning ordinances, subdivision regulations, building codes, health regulations, special purpose ordinances (such as grading and erosion control) and other application of police power which control development in flood-prone areas. This term describes federal, state or local regulations in any combination thereof which provide standards for preventing and reducing flood loss and damage.
j. Governing body is the local governing unit, i.e. county or municipality, that is empowered to adopt and implement regulations to provide for the public health, safety and general welfare of its citizenry.
k. Historic structure means any structure that is
listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;
certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district;
individually listed on a state inventory of historic places in states with historic preservation programs which have been approved by the Secretary of Interior; or
individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either by an approved state program as determined by the Secretary of the Interior or directly by the Secretary of the Interior in states with approved programs.
l. Manufactured Home means a structure, transportable in one or more sections,
Disasters & Emergencies which is built on a permanent chassis and is designed for use with or without a permanent foundation when attached to the required utilities. The term "manufactured home" does not include a "recreational vehicle".
m. Manufactured Home Park or Subdivision" means a parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.
n. New Construction, for floodplain management purposes, means structures for which the "start of construction" commenced on or after the effective date of floodplain management regulations adopted by this community, and includes any subsequent improvements to such structures.
o. One-Hundred-Year Flood or "100-year flood" - see Base flood.
p. Recreational Vehicle means a vehicle which is
built on a single chassis;
400 square feet or less when measured at the largest horizontal projection;
designed to be self-propelled or permanently towable by a light-duty truck; and
designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
q. Start of Construction includes substantial improvement and other proposed new development and means the date the building permit was issued, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days from the date of the permit. The actual start means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufacture home on a foundation. Permanent construction does not include land preparation, such as clearing, grading, and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
r. Structure means a walled and roofed building that is principally above ground; this includes a gas or liquid storage tank or a manufactured home.
Disasters & Emergencies
s. Substantial damage means damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.
t.
Substantial Improvement means any reconstruction, rehabilitation, addition, or
other proposed new development of a structure, the cost of which equals or
exceeds 50 percent of the market value of the structure before the "start of
construction" of the improvement. This term includes structures which have
incurred "substantial damage", regardless of the actual repair work performed.
The term does not, however, include either
any project for improvement of a structure to correct existing violations or state or local health, sanitary, or safety code specifications which have been identified by the local code enforcement official and which are the minimum necessary to assure safe living conditions, or
any alteration of a "historic structure", provided that the alteration will not preclude the structure's continued designation as a "historic structure". (Ord. 665 N.S. 07/06)
SEC. 5.12 GENERAL PROVISIONS¶
(1)
Land to Which this Ordinance Applies. This ordinance shall apply to all areas
identified as flood-prone within the jurisdiction of City of Piedmont
(2) Basis for Establishing Flood-Prone Areas. The Floodplain Administrator shall obtain, review, and reasonably utilize any base flood data available from other Federal or state agencies or other source to identify flood-prone areas within the jurisdiction of City of Piedmont. This data will be on file at 120 Vista Avenue, Piedmont, CA 94611.
(3) Compliance. No structure or land shall hereafter be constructed, located, extended, converted, or altered without full compliance with the term of this ordinance and other applicable regulations. Violation of the requirements (including violations of conditions and safeguards established in connection with conditions) shall constitute a misdemeanor. Nothing herein shall prevent the City Council from taking such lawful action as is necessary to prevent or remedy any violation.
(4)
Abrogation and Greater Restrictions. This ordinance is not intended to repeal,
abrogate, or impair any existing easements, covenants, or deed restrictions.
However, where this ordinance and another ordinance, easement, covenant, or
deed restriction conflict or overlap, whichever imposes the more stringent
Disasters & Emergencies restrictions shall prevail.
(5) Interpretation. In the interpretation and application of this ordinance, all provisions shall be
a.
considered as minimum requirements;
b.
liberally construed in favor of the governing body; and
c.
deemed neither to limit nor repeal any other powers granted under state
statutes.
(6)
Warning and Disclaimer of Liability. The degree of flood protection required by
this ordinance is considered reasonable for regulatory purposes and is based on
scientific and engineering considerations. Larger floods can and will occur on
rare occasions. Flood heights may be increased by man-made or natural causes.
This ordinance does not imply that land outside the areas of special flood hazards
or uses permitted within such areas will be free from flooding or flood damages.
This ordinance shall not create liability on the part of City Council any officer or
employee thereof, the State of California, or the Federal Insurance
Administration, Federal Emergency Management Agency, for any flood damages
that result from reliance on this ordinance or any administrative decision lawfully
made hereunder.
(7)
Severability. This ordinance and the various parts thereof are hereby declared to
be severable. Should any section of this ordinance be declared by the courts to be
unconstitutional or invalid, such decision shall not affect the validity of the
ordinance as a whole, or any portion thereof other than the section so declared to
be unconstitutional or invalid. (Ord. 665 N.S. 07/06)
SEC. 5.13 ADMINISTRATION¶
(1) Establishment of Development Permit. A development permit shall be obtained for all proposed construction or other development in the community, including the placement of manufactured homes, so that it may be determined whether such construction or other development is within flood-prone areas.
(2) Designation of the Floodplain Administrator. The Director of Public Works is hereby appointed to administer, implement, and enforce this ordinance by granting or denying development permits in accord with its provisions.
(3)
Duties and Responsibilities of the Floodplain Administrator. The duties and
responsibilities of the Floodplain Administrator shall include, but not be limited to
the following.
Disasters & Emergencies
a.
Permit Review. Review all development permit applications to determine
that
permit requirements of this ordinance have been satisfied,
all other required state and federal permits have been obtained, and
the site is reasonably safe from flooding.
b.
Review and Use of Any Other Base Flood Data. The Floodplain
Administrator shall obtain, review, and reasonably utilize any base flood
data available from other Federal or state agency or other source.
SEC. 5.14 PROVISIONS FOR FLOOD HAZARD REDUCTION¶
(1)
Standards of Construction. If a proposed building site is in a flood-prone area, all
new construction and substantial improvements, including manufactured homes,
shall:
a.
Be designed (or modified) and adequately anchored to prevent flotation,
collapse or lateral movement of the structure resulting from hydrodynamic
and hydrostatic loads, including the effects of buoyancy.
b.
Be constructed:
with materials and utility equipment resistant to flood damage;
using methods and practices that minimize flood damage;
with electrical, heating, ventilation, plumbing and air conditioning equipment and other service facilities that are designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
Disasters & Emergencies (2) Standards for Subdivisions or Other Proposed New Development. If a subdivision proposal or other proposed new development, including manufactured home parks or subdivisions, is in a flood-prone area, any such proposals shall be reviewed to assure that:
a.
All such proposals are consistent with the need to minimize flood damage
within the floodprone area;
b.
All public utilities and facilities such as sewer, gas, electrical, and water
systems are located and constructed to minimize or eliminate flood
damage; and
c.
Adequate drainage is provided to reduce exposure to flood hazards.
(3) Standards for Utilities.
A.
All new and replacement water supply and sanitary sewage systems shall
be designed to minimize or eliminate:
infiltration of flood waters into the systems, and
discharge from the systems into flood waters.
B. On-site waste disposal systems shall be located to avoid impairment to them, or contamination from them during flooding. (Ord. 665 N.S. 07/06)
Rev. 2020-04-15 (Ordinance 748 N.S.)