Skip to content

Title 16 — BUILDING REGULATIONS

Part 9 — Local Modifications to

Palo Alto Municipal Code · 2026-09 edition · updated 2026-09-29 · Palo Alto

APPENDIX A5 - NONRESIDENTIAL VOLUNTARY MEASURES

Division A5.1 - PLANNING AND DESIGN

16.14.400 Section A5.106.5.3 Electric vehicle (EV) charging for new construction.

Section A5.106.5.3 - A5.106.5.3.4 of the California Green Building Standards Code are adopted as mandatory measures and amended to read:

A5.106.5.3 Electric vehicle (EV) charging for nonresidential structures. New non-residential structures shall comply with the following requirements for electric vehicle supply equipment (EVSE). All parking space calculations under this section shall be rounded up to the next full space. The requirements stated in this section are in addition to those contained in Section 5.106.5.3 of the California Green Building Standards Code.

A5.106.5.3.1 Nonresidential structures other than hotels. The following standards apply to newly constructed non-residential structures other

than hotels.

Comply with Section 5.106.5.3.1 EV capable spaces, Section 5.106.5.3.2 Electric vehicle charging stations and associated Table

A5.106.5.3.3, or Section A5.106.5.3.4 Electric vehicle charging stations (EVCS)—power allocation method and associated Table A5.106.5.3.4.

Refer to Section 5.106.5.3.2 for the permitted use of Level 2 or Direct Current Fast Charger (DCFC) to create EVCS. Refer to Section

5.106.3.2.1 for the allowed use of DCFC to comply with both EV capable spaces and Level 2 EVSE. Refer to Section 5.106.5.3.3 for the allowed use of Automatic Load Management System (ALMS).

Table A5.106.5.3.3 - Tier 2 EV Capable Spaces and EVCS

Total Number of Actual Number of Required EV Other than Office and Retail Number of Office and Retail Number of Required Parking Spaces Capable Spaces Required EVCS2,3 EVCS2,3

Total Number of Actual Number of Required EV Other than Office and Retail Number of Office and Retail Number of Required Parking Spaces Capable Spaces Required EVCS2,3 EVCS2,3

1-9 3 2 2 10-25 8 4 6 26-50 17 9 13 51-75 28 14 21 76-100 40 20 30 101-150 57 29 43 151-200 79 40 59 45% of actual parking 201 and over 50% of EV capable spaces1 75% of EV capable spaces1 spaces1

  1. Calculation for spaces shall be rounded up to the nearest whole number.
  2. Each EVCS shall reduce the number of required EV capable spaces by the same number.
  3. At least one Level 2 EVSE shall be provided.

Table A5.106.5.3.4 - Tier 2 EVCS - Power Allocation Method

Other than Office and Retail Total kVA Office and Retail Total kVA Required in Required in any Combination of EV Total Number of Actual Minimum Total kVA at 6.6. any Combination of EV Capable3,4, Parking Spaces kVA Capable3,4, Low Power Level 2, Level Low Power Level 2, Level 21,2, or 21,2, or DCFC DCFC

Other than Office and Retail Total kVA Office and Retail Total kVA Required in
Required in any Combination of EV Total Number of Actual Minimum Total kVA at 6.6. any Combination of EV Capable3,4,
Parking Spaces kVA Capable3,4, Low Power Level 2, Level Low Power Level 2, Level 21,2, or
21,2, or DCFC DCFC

1-9 19.8 19.8 19.8 10-25 52.8 52.8 52.8 26-50 112.2 112.2 112.2 51-75 184.4 184.4 184.4 76-100 264 264 264 101-150 376.2 376.2 376.2 151-200 521.4 521.4 521.4 45% of actual parking Total required kVA = P x .45 x 6.6 Total required kVA = P x .45 x 6.6 201 and over spaces x 6.6 Where P = Parking spaces in facility Where P = Parking spaces in facility

  1. Level 2 EVSE at 6.6 kVA minimum.
  2. At least one Level 2 EVSE shall be provided.
  3. Maximum allowed kVA to be utilized for EV capable spaces is 75%.
  4. If EV capable spaces are utilized, they shall meet the requirements of Section 5.106.5.3.1 EV capable spaces.
  5. For office and retail buildings the maximum allowed kVA to be utilized for EV capable spaces is 25%.

Location. The EVSE, receptacles, and/or raceway required by this section shall be placed in locations allowing convenient installation of and access to EVSE. Location of EVSE or receptacles shall be consistent with all city regulations.

(Ord. 5678 § 2 (part), 2025)

Division A5.4 - ENERGY EFFICIENCY

16.14.410 Section A5.203.1 Performance Approach for Newly Constructed Buildings.

Section A5.203.1 of Appendix A5 of the California Green Building Standards Code is not adopted as a Tier 1 and Tier 2 elective measure. Projects shall comply with Chapter 16.17 of the Palo Alto Municipal Code (California Energy Code).

(Ord. 5678 § 2 (part), 2025)

Division A5.4 - MATERIAL CONSERVATION AND RESOURCE EFFICIENCY

16.14.420 Section A5.405.5 Cement and Concrete.

Section A5.405.5 of Appendix A5 of the California Green Building Standards Code is adopted as a Mandatory measure for Tier 1 and Tier 2 projects and is amended to read:

A5.405.5 Cement and concrete. Use cement and concrete made with recycled products and complying with the following sections and requirements per PAMC Chapter 16.14.240.

(Ord. 5678 § 2 (part), 2025)

16.14.430 Section A5.408 Construction Waste Reduction, Disposal and Recycling.

Section A5.408 of Appendix A5 of the California Green Building Standards Code is adopted as a Mandatory measure for Tier 2 projects and is amended to read:

A5.408.3.1 Waste enhanced construction waste reduction. (80% construction waste reduction) as a mandatory requirement for all non- residential construction, including new construction, additions, and alterations, as long as the construction has a valuation of $25,000 or more. Non- residential projects with a lower valuation shall remain subject to California Green Building Standards Code Chapter 5 mandatory measures.

Exceptions:

  1. Residential stand-alone mechanical, electrical or plumbing permits.

  2. Commercial stand-alone mechanical, electrical or plumbing permits.

A5.408.3.1.1 - Deleted.

A5.408.3.1.2 Documentation. Documentation shall be provided to the enforcing agency which demonstrates compliance with all construction

and demolition waste reduction requirements.

(Ord. 5678 § 2 (part), 2025)

Chapter 16.15

ELECTRIC VEHICLE CHARGING STATIONS

16.15.010 Expedited permitting process for electric vehicle charging stations.

(a) Definitions.

(1) “Electric vehicle charging station” or “charging station” means any level of electric vehicle supply equipment station that is designed and

built in compliance with Article 625 of the California Electrical Code, as it reads on the effective date of this chapter, and delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle.

(2) “Specific, adverse impact” means a significant, quantifiable, direct, and unavoidable impact, based on objective, identified, and written

public health or safety standards, policies, or conditions as they existed on the date the application was deemed complete.

(3) “Electronic submittal” means the utilization of one or more of the following:

i. Electronic mail or email.

ii. The internet.

iii. Facsimile.

(b) Expedited permitting process. Consistent with Government Code Section 65850.7, the Chief Building Official shall implement an expedited, streamlined permitting process for electric vehicle charging stations, and adopt a checklist of all requirements with which electric vehicle charging stations shall comply with in order to be eligible for expedited review. The expedited, streamlined permitting process and checklist may refer to the recommendations contained in the most current version of the “Electric Vehicle Charging Station Permitting Guidebook” published by the Governor’s Office of Business and Economic Development. The city’s adopted checklist shall be published on the city’s website.

(c) Permit application processing.

(1) Prior to submitting an application for processing, the applicant shall verify that the installation of an electric vehicle charging station will not

have specific, adverse impact to public health and safety and building occupants. Verification by the applicant includes but is not limited to: electrical system capacity and loads; electrical system wiring, bonding and overcurrent protection; building infrastructure affected by charging station equipment and associated conduits; areas of charging station equipment and vehicle parking.

(2) A permit application that satisfies the information requirements in the city’s adopted checklist shall be deemed complete and be promptly

processed. Upon confirmation by the Chief Building Official or designee that the permit application and supporting documents meets the requirements of the city adopted checklist, and is consistent with all applicable laws and health and safety standards, the Chief Building Official or designee shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the city. If the Chief Building Official or designee determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.

(3) The Chief Building Official or designee shall not condition the approval for any electric vehicle charging station permit on the approval of

such a system by an association, as that term is defined by Civil Code Section 4080.

(4) Permit applications under this section may be submitted electronically, including electronic signatures on all forms, applications, and other

documentation.

(d) Technical review. It is the intent of this section to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the Chief Building Official’s authority to address higher priority life-safety situations. If the Chief Building Official or designee makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in this section, the city may require the applicant to apply for a use permit.

(Ord. 5661 § 2, 2025)

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Palo Alto Municipal Code
Palo Alto Municipal Code
  1. Article VIII — A. Board of Education
  2. Title 1 — GENERAL PROVISIONS
  3. Title 2 — ADMINISTRATIVE CODE
  4. Title 4 — BUSINESS LICENSES AND REGULATIONS
  5. Title 5 — HEALTH AND SANITATION
  6. Title 6 — ANIMALS
  7. Title 8 — TREES AND VEGETATION
  8. Title 9 — PUBLIC PEACE, MORALS AND SAFETY
  9. Title 10 — VEHICLES AND TRAFFIC
  10. Title 11 — ENVIRONMENTAL IMPACT PROCEDURE
  11. Title 12 — PUBLIC WORKS AND UTILITIES
  12. Title 13 — IMPROVEMENT PROCEDURE
  13. Title 15 — FIRE PREVENTION
  14. ▸Title 16 — BUILDING REGULATIONS
    Overview
    1. 16.04 California Building Code, California Code of Regulations…
    2. 16.05 California Mechanical Code, California Code of Regulatio…
    3. 16.08 California Plumbing Code, California Code of Regulations…
    4. 16.09 Sewer Use Ordinance
    5. 16.10 Private Sewage Disposal Systems
    6. 16.11 Stormwater Pollution Prevention
    7. 16.12 Recycled Water
    8. 16.13 Requirements for Food Facilities Related to Water Pollut…
    9. 16.14 California Green Building Standards Code, California Cod…
    10. 16.15 Electric Vehicle Charging Stations
    11. 16.17 California Energy Code, California Code of Regulations, …
    12. 16.19 California Historical Building Code, California Code of …
    13. 16.20 Signs
    14. 16.24 Fences
    15. 16.28 Excavations, Grading and Fills
    16. 16.32 Moving and Relocating Buildings
    17. 16.36 House Numbering
    18. 16.38 Certificate of Use and Occupancy for Community Housing
    19. 16.40 Unsafe Buildings
    20. 16.42 Seismic Hazards Identification Program
    21. 16.44 Fallout Shelters
    22. 16.45 Transportation Impact Fee for New Nonresidential Develop…
    23. 16.46 Approval of Projects with Impacts on Traffic in the San …
    24. 16.47 Reserved
    25. 16.48 Reserved
    26. 16.49 Historic Preservation
    27. 16.50 Reserved
    28. 16.52 Flood Hazard Regulations
    29. 16.56 Handicapped Access Regulations - Appeal
    30. 16.57 In-Lieu Parking Fee for New Nonresidential Development i…
    31. 16.58 Development Impact Fees
    32. 16.59 Citywide Transportation Impact Fee
    33. 16.60 Charleston Arastradero Corridor Pedestrian and Bicyclist…
    34. 16.61 Public Art for Private Developments
    35. 16.62 Expired Permits for Residential Construction and Demolit…
    36. 16.63 Small Residential Rooftop Solar Energy Systems
    37. 16.64 Development Fee and In-lieu Payment Administration
    38. 16.65 Citywide Affordable Housing Requirements
    39. 16.66 Hauled Liquid Waste
    40. Chapter 16.04 — CALIFORNIA BUILDING CODE, CALIFORNIA CODE OF
    41. Chapter 16.05 — CALIFORNIA MECHANICAL CODE, CALIFORNIA CODE OF
    42. Chapter 16.08 — CALIFORNIA PLUMBING CODE, CALIFORNIA CODE OF
    43. Chapter 16.09 — SEWER USE ORDINANCE
    44. Chapter 16.10 — PRIVATE SEWAGE DISPOSAL SYSTEMS
    45. Chapter 16.11 — STORMWATER POLLUTION PREVENTION
    46. Part 2 — General Provisions
    47. Part 3 — Development Projects
    48. Part 10 — Copper Controls
    49. Part 3 — Development Projects
    50. Part 4 — Required Best Management Practices for All Dischargers
    51. Part 5 — Illicit Discharge Detection and Elimination and Mobil…
    52. Part 6 — Pesticides Toxicity Control
    53. Part 7 — Trash Load Reductions
    54. Part 8 — Mercury Controls
    55. Part 9 — Polychlorinated Biphenyls (PCBs) Controls
    56. Part 10 — Copper Controls
    57. Chapter 16.12 — RECYCLED WATER
    58. Chapter 16.13 — REQUIREMENTS FOR FOOD FACILITIES RELATED TO WA…
    59. Part 6 — Rooftop Grease Containment System Requirements
    60. Part 11 — Food Facility Closure or Ownership Change
    61. Part 3 — Authority to Inspect and Enforce
    62. Part 4 — Prohibited Discharges, Devices, and Connections
    63. Part 5 — Grease Control Device Requirements
    64. Part 6 — Rooftop Grease Containment System Requirements
    65. Part 7 — Waste Oil Management Requirements
    66. Part 8 — Spill Response Requirements
    67. Part 9 — Best Management Practices for Existing Facilities
    68. Part 10 — Mobile Food Facilities
    69. Part 11 — Food Facility Closure or Ownership Change
    70. Chapter 16.14 — CALIFORNIA GREEN BUILDING STANDARDS CODE,
    71. Part 1 — General
    72. Chapter 4 — RESIDENTIAL
    73. Chapter 7 — INSTALLER AND SPECIAL
    74. Part 7 — Local Modifications to
    75. Chapter 5 — NONRESIDENTIAL
    76. Part 9 — Local Modifications to
    77. Part 1 — General
    78. Chapter 1 — ADMINISTRATION
    79. Chapter 2 — DEFINITIONS
    80. Chapter 3 — GREEN BUILDING
    81. Chapter 4 — RESIDENTIAL MANDATORY MEASURES
    82. Chapter 7 — INSTALLER AND SPECIAL INSPECTOR QUALIFICATIONS
    83. Part 7 — Local Modifications to
    84. Chapter 5 — NONRESIDENTIAL MANDATORY MEASURES
    85. Part 9 — Local Modifications to
    86. Chapter 16.16 — CALIFORNIA ELECTRICAL CODE, CALIFORNIA CODE OF
    87. Chapter 16.17 — CALIFORNIA ENERGY CODE, CALIFORNIA CODE OF
    88. Chapter 16.19 — CALIFORNIA HISTORICAL BUILDING CODE, CALIFORNI…
    89. Chapter 16.20 — SIGNS
    90. Chapter 16.20 — Table 1
    91. Chapter 16.20 — Table 2
    92. Chapter 16.20 — Table 2
    93. Chapter 16.20 — Table 3
    94. Chapter 16.24 — FENCES
    95. Chapter 16.28 — GRADING AND EROSION AND SEDIMENT CONTROL
    96. Chapter 16.32 — MOVING AND RELOCATING BUILDINGS
    97. Chapter 16.36 — HOUSE NUMBERING
    98. Chapter 16.38 — CERTIFICATE OF USE AND OCCUPANCY FOR COMMUNITY
    99. Chapter 16.40 — UNSAFE BUILDINGS
    100. Chapter 16.44 — FALLOUT SHELTERS
    101. Chapter 16.45 — TRANSPORTATION IMPACT FEE FOR NEW NONRESIDENTIAL
    102. Chapter 16.46 — APPROVAL OF PROJECTS WITH IMPACTS ON TRAFFIC I…
    103. Chapter 16.48 — RESERVED
    104. Chapter 16.49 — HISTORIC PRESERVATION
    105. Chapter 16.50 — RESERVED
    106. Chapter 16.52 — FLOOD HAZARD REGULATIONS
    107. Chapter 16.56 — HANDICAPPED ACCESS REGULATIONS - APPEAL
    108. Chapter 16.57 — IN-LIEU PARKING FEE FOR NEW NONRESIDENTIAL DEV…
    109. Chapter 16.58 — DEVELOPMENT IMPACT FEES
    110. Chapter 16.59 — CITYWIDE TRANSPORTATION IMPACT FEE
    111. Chapter 16.60 — CHARLESTON ARASTRADERO CORRIDOR PEDESTRIAN
    112. Chapter 16.61 — PUBLIC ART FOR PRIVATE DEVELOPMENTS
    113. Chapter 16.62 — EXPIRED PERMITS FOR RESIDENTIAL CONSTRUCTION AND
    114. Chapter 16.63 — SMALL RESIDENTIAL ROOFTOP SOLAR ENERGY SYSTEMS
    115. Chapter 16.64 — DEVELOPMENT FEE AND IN-LIEU PAYMENT ADMINISTRA…
    116. Chapter 16.66 — HAULED LIQUID WASTE
  15. Title 17 — HAZARDOUS MATERIALS STORAGE
  16. Title 18 — ZONING
  17. Title 19 — MASTER PLAN
  18. Article 7 — AUTHORITY FOR AND SCOPE OF MASTER OR GENERAL PLANS.
  19. Article 8 — PROCEDURE FOR ADOPTION OF MASTER OR GENERAL PLAN.
  20. Chapter 19.06 — SPECIFIC PLANS
  21. Chapter 19.10 — COORDINATED AREA PLANS
  22. Title 20 — PRECISE PLANS
  23. Title 21 — SUBDIVISIONS AND OTHER DIVISIONS OF LAND
  24. Title 22 — PARKS

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.