BE104.1 TESTING. ¶
Where radon-resistant construction is required, radon testing shall be as specified in Items 1 through 11:
Testing shall be performed after the dwelling passes its air tightness test.
Testing shall be performed after the radon control system and HVAC installations are complete. The HVAC system shall be operating during the test. Where the radon system has an installed fan, the dwelling shall be tested with the radon fan operating.
Testing shall be performed at the lowest occupied floor level, whether or not that space is finished. Spaces that are physically separated and served by different HVAC systems shall be tested separately.
Testing shall not be performed in a closet, hallway, stairway, laundry room, furnace room, bathroom or kitchen.
Testing shall be performed with a commercially available radon test kit or testing shall be performed by an approved third party with a continuous radon monitor. Testing with test kits shall include two tests, and the test results shall be averaged. Testing shall be in accordance with this section and the testing laboratory kit manufacturer’s instructions.
Testing shall be performed with the windows closed. Testing shall be performed with the exterior doors closed, except when being used for entrance or exit. Windows and doors shall be closed for not fewer than 12 hours prior to the testing.
Testing shall be performed by the builder, a registered design professional or an approved third party.
Testing shall be conducted over a period of not less than 48 hours or not less that the period specified by the testing device manufacturer, whichever is longer.
Written radon test results shall be provided by the test lab or testing party. The final written test report with results less than 4 picocuries per liter (pCi/L) shall be provided to the code official.
Where the radon test result is 4 pCi/L or greater, the fan for the radon vent pipe shall be installed as specified in Sections BE103.9 and BE103.12.
Where the radon test result is 4 pCi/L or greater, the system shall be modified and retested until the test result is less than 4 pCi/L.
Exception: Testing is not required where the occupied space is located above an unenclosed open space.
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX BE-12 2025 CALIFORNIA RESIDENTIAL CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
CALIFORNIA RESIDENTIAL CODE – MATRIX ADOPTION TABLE
APPENDIX BF – PATIO COVERS
(Matrix Adoption Tables are nonregulatory, intended only as an aid to the code user. See Chapter 1 for state agency authority and building applications.)
| Adopting agency | BSC | BSC- CG |
SFM | HCD | DSA | OSHPD | BSCC | DPH | AGR | DWR | CEC | CA | SL | SLC | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Adopting agency | BSC | BSC- CG |
SFM | 1 | 2 | 1/AC | AC | SS | SS/CC | 1 | 1R | 2 | 3 | 4 | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 5 |
| Adopt entire chapter | X | X | |||||||||||||||||||||
| Adopt entire chapter as amended (amended sections listed below) |
|||||||||||||||||||||||
| Adopt only those sections that are listed below |
|||||||||||||||||||||||
| Chapter / Section | |||||||||||||||||||||||
| 103.2 | X | ||||||||||||||||||||||
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX BF-2 2025 CALIFORNIA RESIDENTIAL CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — 2025 California Residential Code (Title 24, Part 2.5)
- Chapter 1 — ADMINISTRATION
- Chapter 2 — DEFINITIONS
- Chapter 3 — BUILDING PLANNING
- Chapter 4 — FOUNDATIONS
- Chapter 5 — FLOORS
- Chapter 6 — WALL CONSTRUCTION
- Chapter 7 — WALL COVERING
- Chapter 8 — ROOF-CEILING CONSTRUCTION
- Chapter 9 — ROOF ASSEMBLIES
- Chapter 10 — CHIMNEYS AND FIREPLACES
- Chapter 44 — REFERENCED STANDARDS
- Appendix AA — BOARD OF APPEALS
- Appendix AB — PERMIT FEES
- Appendix AC — RESERVED
- Appendix BA — RESERVED
- Appendix BB — TINY HOUSES
- Appendix BC — RESERVED
- Appendix BD — RESERVED
-
▸ Appendix BE — RADON CONTROL METHODS
- Appendix BF — PATIO COVERS
- Appendix BG — SOUND TRANSMISSION
- Appendix BH — AUTOMATIC VEHICULAR GATES
- Appendix BI — LIGHT STRAW-CLAY CONSTRUCTION
- Appendix BJ — STRAWBALE CONSTRUCTION
- Appendix BK — COB CONSTRUCTION (MONOLITHIC ADOBE)
- Appendix BL — HEMP-LIME (HEMPCRETE) CONSTRUCTION
- Appendix BM — 3D-PRINTED BUILDING CONSTRUCTION
- Appendix BN — EXTENDED PLATE WALL CONSTRUCTION
- Appendix BO — EXISTING BUILDINGS AND STRUCTURES
- Appendix CA — RESERVED
- Appendix CB — RESERVED
- Appendix CC — RESERVED
- Appendix CD — RESERVED
- Appendix CE — RESERVED
- Appendix CF — RESERVED
- Appendix CG — NONSEWERED SANITATION SYSTEMS
- Appendix CH — PRIVATE SEWAGE DISPOSAL
- Appendix CI — SWIMMING POOL SAFETY ACT
- Appendix CJ — EMERGENCY HOUSING
- Appendix CK — AREAS PROTECTED BY THE FACILITIES OF THE CENTRAL…