K107.1 General.

K107.1 General. Rooftop evacuation locations shall be permitted to include rooftop platforms and rooftop areas provided that they are no less than one (1) foot (0.30 meter) above the WSEL200. A minimum horizontal distance of three (3) feet (0.91 meter) shall be provided between the lower edge of the rooftop evacuation location access point and the evacuation location lower perimeter.

K107.2 Rooftop platforms required.

K107.2 Rooftop platforms required. A rooftop platform shall be provided if the roof covering materials are: 1. Clay tile, concrete tile, slate shingles, wood shingles or wood shakes, and the roof slope is three units vertical in 12 units hori- zontal (25 percent slope) or greater. on Jul 18, 2025 11:14 AM (CDT) THEREUNDER. APPENDIX K—GROUP R-3 AND GROUP R-3.1 OCCUPANCIES PROTECTED BY THE FACILITIES OF THE CENTRAL VALLEY FLOOD PROTECTION PLAN 2. Metal roof panels or metal roof shingles, and the roof slope is one unit vertical in 12 units horizontal (8.33 percent slope) or greater.

K107.3 Roof live loads.

K107.3 Roof live loads. Roof areas that are rooftop evacuation locations and roofs that support rooftop platforms that are evacuation locations shall be designed for the roof live load required for the occupancy as required in Table 1607.2.

K107.4 Evacuation routes to rooftop evacuation locations.

K107.4 Evacuation routes to rooftop evacuation locations. Evacuation routes to rooftop evacuation locations shall be permitted to be provided by a stairway, ramp, alternating tread device, fixed ladder or other means approved by the building official. Exception: In Group R-3.1 occupancies that are subject to the requirements of Chapter 11A or 11B, such requirements shall apply to the evacuation routes to rooftops.

K107.5 Perimeter protection.

K107.5 Perimeter protection. For Group R-3 and R-3.1 occupancies, the perimeter of rooftop evacuation locations shall be protected by: 1. Guards per Section 1013 if a rooftop platform is provided; or 2. A railing that is 12 inches (305 mm) in height if a sloped roof is provided.

K107.6 Utility/equipment buffer zone.

K107.6 Utility/equipment buffer zone. A separation of 48 inches shall be provided between a rooftop evacuation location and any mechanical equipment, photovoltaic system, utility service drop or other utility line. Electrical service lines shall not pass over evacua- tion locations.