J107.1 General. ¶
J107.1 General. Unless otherwise recommended in the geotechnical report, fills shall comply with the provisions of this section.
J107.2 Surface preparation. ¶
J107.2 Surface preparation. The ground surface shall be prepared to receive fill by removing vegetation, topsoil and other unsuitable materials, and scarifying the ground to provide a bond with the fill material.
J107.3 Benching. ¶
J107.3 Benching. Where existing grade is at a slope steeper than one unit vertical in five units horizontal (20-percent slope) and the depth of the fill exceeds 5 feet (1524 mm) benching shall be provided in accordance with Figure J107.3. A key shall be provided that is not less than 10 feet (3048 mm) in width and 2 feet (610 mm) in depth. on Jul 18, 2025 11:14 AM (CDT) THEREUNDER. APPENDIX J—GRADING FIGURE J107.3—BENCHING DETAILS For SI: 1 foot = 304.8 mm.
J107.4 Fill material. ¶
J107.4 Fill material. Fill material shall not include organic, frozen or other deleterious materials. Rock or similar irreducible material greater than 12 inches (305 mm) in any dimension shall not be included in fills.
J107.5 Compaction. ¶
J107.5 Compaction. All fill material shall be compacted to 90 percent of maximum density as determined by ASTM D1557, Modified Proctor, in lifts not exceeding 12 inches (305 mm) in depth.
J107.6 Maximum slope. ¶
J107.6 Maximum slope. The slope of fill surfaces shall be not steeper than is safe for the intended use. Fill slopes steeper than one unit vertical in two units horizontal (50-percent slope) shall be justified by a geotechnical report or engineering data.