Chapter 18A — SOILS AND FOUNDATIONS
Section 1805A — DAMPPROOFING AND WATERPROOFING
2025 California Building Code (Title 24, Part 2) · 2025 edition · updated 2026-07-29 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
1805 A .1 General. Walls or portions thereof that retain earth and enclose interior spaces and floors below grade shall be waterproofed and dampproofed in accordance with this section, with the exception of those spaces containing groups other than residential and institutional where such omission is not detrimental to the building or occupancy.
Ventilation for crawl spaces shall comply with Section 1202.4.
1805 A .1.1 Story above grade plane. Where a basement is considered a story above grade plane and the finished ground level adjacent to the basement wall is below the basement floor elevation for 25 percent or more of the perimeter, the floor and walls shall be dampproofed in accordance with Section 1805 A .2 and a foundation drain shall be installed in accordance with Section 1805 A .4.2. The foundation drain shall be installed around the portion of the perimeter where the basement floor is below ground level. The provisions of Sections 1803 A .5.4, 1805 A .3 and 1805 A .4.1 shall not apply in this case.
1805 A .1.2 Under-floor space. The finished ground level of an under-floor space such as a crawl space shall not be located below the bottom of the footings. Where there is evidence that the ground-water table rises to within 6 inches (152 mm) of the ground
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
SOILS AND FOUNDATIONS
level at the outside building perimeter, or that the surface water does not readily drain from the building site, the ground level of the under-floor space shall be as high as the outside finished ground level, unless an approved drainage system is provided. The provisions of Sections 1803 A .5.4, 1805 A .2, 1805 A .3 and 1805 A .4 shall not apply in this case.
1805 A .1.2.1 Flood hazard areas. For buildings and structures in flood hazard areas as established in Section 1612 A .3, the finished ground level of an under-floor space such as a crawl space shall be equal to or higher than the outside finished ground level on one side or more.
Exception: Under-floor spaces of Group R-3 buildings that meet the requirements of FEMA TB 11.
1805 A .1.3 Ground-water control. Where the ground-water table is lowered and maintained at an elevation not less than 6 inches (152 mm) below the bottom of the lowest floor, the floor and walls shall be dampproofed in accordance with Section 1805 A .2. The design of the system to lower the ground-water table shall be based on accepted principles of engineering that shall consider, but not necessarily be limited to, permeability of the soil, rate at which water enters the drainage system, rated capacity of pumps, head against which pumps are to operate and the rated capacity of the disposal area of the system.
1805 A .2 Dampproofing. Where hydrostatic pressure will not occur as determined by Section 1803 A .5.4, floors and walls shall be dampproofed in accordance with this section.
1805 A .2.1 Floors. Dampproofing materials for floors shall be installed between the floor and the base course required by Section 1805 A .4.1, except where a separate floor is provided above a concrete slab.
Where installed beneath the slab, dampproofing shall consist of not less than 6-mil (0.006 inch; 0.152 mm) polyethylene with joints lapped not less than 6 inches (152 mm), or other approved methods or materials. Where permitted to be installed on top of the slab, dampproofing shall consist of mopped-on bitumen, not less than 4-mil (0.004 inch; 0.102 mm) polyethylene, or other approved methods or materials. Joints in the membrane shall be lapped and sealed in accordance with the manufacturer’s installation instructions.
1805 A .2.2 Walls. Dampproofing materials for walls shall be installed on the exterior surface of the wall, and shall extend from the top of the footing to above ground level. Dampproofing shall consist of a bituminous material, 3 pounds per square yard (16 N/m [2] ) of acrylic modified cement, [1] / 8 inch (3.2 mm) coat of surface-bonding mortar complying with ASTM C887, any of the materials permitted for waterproofing by Section 1805.3.2 or other approved methods or materials.
1805 A .2.2.1 Surface preparation of walls. Prior to application of dampproofing materials on concrete walls, holes and recesses resulting from the removal of form ties shall be sealed with a bituminous material or other approved methods or materials. Unit masonry walls shall be parged on the exterior surface below ground level with not less than [3] / 8 inch (9.5 mm) of Portland cement mortar. The parging shall be coved at the footing.
Exception: Parging of unit masonry walls is not required where a material is approved for direct application to the masonry.
1805 A .3 Waterproofing. Where the ground-water investigation required by Section 1803 A .5.4 indicates that a hydrostatic pressure condition exists, and the design does not include a ground-water control system as described in Section 1805 A .1.3, walls and floors shall be waterproofed in accordance with this section.
1805 A .3.1 Floors. Floors required to be waterproofed shall be of concrete and designed and constructed to withstand the hydrostatic pressures to which the floors will be subjected.
Waterproofing shall be accomplished by placing a membrane of rubberized asphalt, butyl rubber, fully adhered/fully bonded HDPE or polyolefin composite membrane or not less than 6-mil [0.006 inch (0.152 mm)] polyvinyl chloride with joints lapped not less than 6 inches (152 mm) or other approved materials under the slab. Joints in the membrane shall be lapped and sealed in accordance with the manufacturer’s installation instructions.
1805 A .3.2 Walls. Walls required to be waterproofed shall be of concrete or masonry and shall be designed and constructed to withstand the hydrostatic pressures and other lateral loads to which the walls will be subjected.
Waterproofing shall be applied from the bottom of the wall to not less than 12 inches (305 mm) above the maximum elevation of the ground-water table. The remainder of the wall shall be dampproofed in accordance with Section 1805 A .2.2. Waterproofing shall consist of two-ply hot-mopped felts, not less than 6-mil (0.006 inch; 0.152 mm) polyvinyl chloride, 40-mil (0.040 inch; 1.02 mm) polymer-modified asphalt, 6-mil (0.006 inch; 0.152 mm) polyethylene or other approved methods or materials capable of bridging nonstructural cracks. Joints in the membrane shall be lapped and sealed in accordance with the manufacturer’s installation instructions.
1805 A .3.2.1 Surface preparation of walls. Prior to the application of waterproofing materials on concrete or masonry walls, the walls shall be prepared in accordance with Section 1805 A .2.2.1.
1805 A .3.3 Joints and penetrations. Joints in walls and floors, joints between the wall and floor and penetrations of the wall and floor shall be made watertight utilizing approved methods and materials.
1805 A .4 Subsoil drainage system. Where a hydrostatic pressure condition does not exist, dampproofing shall be provided and a base shall be installed under the floor and a drain installed around the foundation perimeter. A subsoil drainage system designed and constructed in accordance with Section 1805 A .1.3 shall be deemed adequate for lowering the ground-water table.
1805 A .4.1 Floor base course. Floors of basements, except as provided for in Section 1805 A .1.1, shall be placed over a floor base course not less than 4 inches (102 mm) in thickness that consists of gravel or crushed stone containing not more than 10 percent of material that passes through a No. 4 (4.75 mm) sieve.
Exception: Where a site is located in well-drained gravel or sand/gravel mixture soils, a floor base course is not required.
18A-8 2025 CALIFORNIA BUILDING CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
SOILS AND FOUNDATIONS
1805 A .4.2 Foundation drain. A drain shall be placed around the perimeter of a foundation that consists of gravel or crushed stone containing not more than 10-percent material that passes through a No. 4 (4.75 mm) sieve. The drain shall extend not less than 12 inches (305 mm) beyond the outside edge of the footing. The thickness shall be such that the bottom of the drain is not higher than the bottom of the base under the floor, and that the top of the drain is not less than 6 inches (152 mm) above the top of the footing. The top of the drain shall be covered with an approved filter membrane material. Where a drain tile or perforated pipe is used, the invert of the pipe or tile shall not be higher than the floor elevation. The top of joints or the top of perforations shall be protected with an approved filter membrane material. The pipe or tile shall be placed on not less than 2 inches (51 mm) of gravel or crushed stone complying with Section 1805.4.1, and shall be covered with not less than 6 inches (152 mm) of the same material.
is used, the invert of the pipe or tile shall not be higher than the floor elevation. The top of joints or the top of perforations shall be protected with an approved filter membrane material. The pipe or tile shall be placed on not less than 2 inches (51 mm) of gravel or crushed stone complying with Section 1805.4.1, and shall be covered with not less than 6 inches (152 mm) of the same material.
1805 A .4.3 Drainage discharge. The floor base and foundation perimeter drain shall discharge by gravity or mechanical means into an approved drainage system that complies with the California Plumbing Code .
Exception: Where a site is located in well-drained gravel or sand/gravel mixture soils, a dedicated drainage system is not required.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — 2025 California Building Code (Title 24, Part 2)
- Chapter 1 — ADMINISTRATION
- Chapter 2 — DEFINITIONS
- Chapter 3 — OCCUPANCY CLASSIFICATION AND USE
- Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED ON OCCUPANCY A…
- Chapter 5 — GENERAL BUILDING HEIGHTS AND AREAS
- Chapter 6 — TYPES OF CONSTRUCTION
- Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
- Chapter 7A — MATERIALS AND CONSTRUCTION METHODS FOR EXTERIOR W…
- Chapter 8 — INTERIOR FINISHES
- Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
- Chapter 10 — MEANS OF EGRESS
- Chapter 11 — RESERVED
- Chapter 11A — HOUSING ACCESSIBILITY
- Chapter 11B — ACCESSIBILITY TO PUBLIC BUILDINGS, PUBLIC ACCOMM…
- Chapter 12 — INTERIOR ENVIRONMENT
- Chapter 13 — ENERGY EFFICIENCY
- Chapter 14 — EXTERIOR WALLS
- Chapter 15 — ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
- Chapter 16 — STRUCTURAL DESIGN
- Chapter 16A — STRUCTURAL DESIGN
- Chapter 17 — SPECIAL INSPECTIONS AND TESTS
- Chapter 17A — SPECIAL INSPECTIONS AND TESTS
- Chapter 18 — SOILS AND FOUNDATIONS
-
▸ Chapter 18A — SOILS AND FOUNDATIONS
Overview- Section 1801A — GENERAL
- Section 1802A — DESIGN BASIS
- Section 1803A — GEOTECHNICAL INVESTIGATIONS
- Section 1804A — EXCAVATION, GRADING AND FILL
- Section 1805A — DAMPPROOFING AND WATERPROOFING
- Section 1806A — PRESUMPTIVE LOAD-BEARING VALUES OF SOILS
- Section 1807A — FOUNDATION WALLS, RETAINING WALLS AND EMBEDDED…
- Section 1808A — FOUNDATIONS
- Section 1809A — SHALLOW FOUNDATIONS
- Section 1810A — DEEP FOUNDATIONS
- Section 1811A — PRESTRESSED ROCK AND SOIL FOUNDATION ANCHORS
- Section 1812A — EARTH RETAINING SHORING
- Section 1813A — VIBRO STONE COLUMNS FOR GROUND IMPROVEMENT
- Chapter 19 — CONCRETE
- Chapter 19A — CONCRETE
- Chapter 20 — ALUMINUM
- Chapter 21 — MASONRY
- Chapter 21A — MASONRY
- Chapter 22 — STEEL
- Chapter 22A — STEEL
- Chapter 23 — WOOD
- Chapter 24 — GLASS AND GLAZING
- Chapter 25 — GYPSUM PANEL PRODUCTS AND PLASTER
- Chapter 26 — PLASTIC
- Chapter 27 — ELECTRICAL
- Chapter 28 — MECHANICAL SYSTEMS
- Chapter 29 — PLUMBING SYSTEMS
- Chapter 30 — ELEVATORS AND CONVEYING SYSTEMS
- Chapter 31 — SPECIAL CONSTRUCTION
- Chapter 31A — SYSTEMS FOR WINDOW CLEANING OR EXTERIOR BUILDING…
- Chapter 31B — PUBLIC POOLS
- Chapter 31C — RADIATION
- Chapter 31D — FOOD ESTABLISHMENTS
- Chapter 31F — MARINE OIL TERMINALS
- Chapter 32 — ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
- Chapter 33 — SAFEGUARDS DURING CONSTRUCTION
- Chapter 34 — RESERVED
- Chapter 35 — REFERENCED STANDARDS
- Appendix A — EMPLOYEE QUALIFICATIONS
- Appendix B — BOARD OF APPEALS
- Appendix C — GROUP U—AGRICULTURAL BUILDINGS
- Appendix D — FIRE DISTRICTS
- Appendix E — RESERVED
- Appendix F — RODENTPROOFING
- Appendix G — FLOOD-RESISTANT CONSTRUCTION
- Appendix H — SIGNS
- Appendix I — PATIO COVERS
- Appendix J — GRADING
- Appendix K — GROUP R-3 AND GROUP R-3.1 OCCUPANCIES PROTECTED B…
- Appendix L — EARTHQUAKE RECORDING INSTRUMENTATION
- Appendix M — TSUNAMI-GENERATED FLOOD HAZARDS
- Appendix N — REPLICABLE BUILDINGS
- Appendix O — PERFORMANCE-BASED APPLICATION
- Appendix P — SLEEPING LOFTS
- Appendix Q — EMERGENCY HOUSING