California ADU rules · Fresno County

Can I Build an ADU in Parlier?

Yes — you can build an ADU in Parlier. California's statewide ADU law requires every city, including Parlier, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Parlier follows the California statewide ADU standards; figures below are the state floor plus any local factors noted.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

CA state law

Conversion ADUs (≥1, up to 25% of units) + up to 8 detached

Conversions of non-livable space (at least 1, or up to 25% of existing units) plus up to 8 detached ADUs on a lot with existing multifamily — never exceeding the number of existing units. JADUs are single-family only.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

CA state law

1,200 sq ft

Statewide default cap for detached new-construction ADUs in the absence of a compliant local ADU ordinance. The unconditional by-right floor a city must always allow is 800 sq ft (see Guaranteed minimum size); a city with a compliant ordinance may set its own ceiling.

Max attached ADU size

CA state law

50% of the primary dwelling, but ≥850 sq ft (≥1,000 sq ft for 2+ bedrooms) is always allowed

Cal. Gov. Code § 66321 (size minimums & height)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

CA state law

16 ft

16 ft baseline; cities must allow 18 ft within ½ mi of a major transit stop or where the primary dwelling is two-story, and 20 ft on a lot with a multistory multifamily building.

Cal. Gov. Code § 66321 (size minimums & height)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

CA state law

None required

No statewide separation requirement between the ADU and the primary dwelling.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Parking

Parking required

CA state law

Up to 1 space

At most 1 space per ADU (or per bedroom, whichever is less) — and waived in the common cases below.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

CA state law

Not required

When a garage/carport is demolished or converted to build an ADU, replacement parking cannot be required.

Cal. Gov. Code § 66314 (local ordinance standards)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

CA state law

Only for a JADU

No owner-occupancy requirement for ADUs (the prior sunset was removed). A JADU may require owner-occupancy, principally where it shares sanitation with the main house.

Cal. Gov. Code § 66315 (owner-occupancy)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

CA state law

Building permit

Only a ministerial building permit — no conditional use permit or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Parlier has not adopted a state-compliant ADU ordinance. Its zoning code carries only a 1985-era 'second dwelling unit' section (§ 18.14.168) that conflicts with current law — it would require a conditional use permit, three off-street parking spaces, a 75%-of-primary size cap, and an existing occupied unit on the lot, and provides no junior-ADU pathway. All of those local provisions are preempted, so California state ADU law (Gov. Code §§ 66310–66342) controls: ministerial approval within 60 days, the 800 sq ft by-right floor, 4-ft side/rear setbacks, and the state parking exemptions. Confirm current local processing with Parlier Community Development.

Frequently asked questions

Can I build an ADU in Parlier?

Yes. California's statewide ADU law requires Parlier to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Parlier?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Parlier?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Parlier?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Parlier?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Parlier?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

Last updated Ord. 85-16 (1985); not amended for state ADU law. This is an AI-assisted summary of Parlier's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Parlier Planning before relying on it.

Will an ADU work on your Parlier lot?

Ask GoCodebook about your address and get the size, setback, parking and permit rules that actually apply to your parcel — with the exact citation.