CPC · California Plumbing Code

Blowdown, purging, initial pressure tests and leak testing for new or altered systems

For homeowners: when medical gas piping is installed or altered (e.g., in a clinic), the contractor must first blow the lines clear with clean nitrogen, pressure‑test each section at a higher safety pressure (1.5× operating pressure but at least 150 psi), remove particles by purging, leak‑test final connections with the system gas, and keep permanent test records — all required by the California Plumbing Code (§ 1324.3, § 1324.4, § 1324.5, § 1324.5.8, § 1324.5.9) .

Last reviewed: July 6, 2026

What the code requires — plain English

Piping for medical gas and vacuum systems must be blown clear with oil‑free, dry nitrogen NF before installing outlets or other components (§ 1324.4) and every section must be pressure tested at specified times and pressures (§ 1324.5, § 1324.5.1.1) . After final tie‑in the new joint(s) must be leak‑tested with the system gas and vacuum joints require ultrasonic or equivalent detection; outlets downstream of a brazed connection must be purged and particle removal performed as required (§ 1324.5.8, § 1324.5.9) .

The single most important rule: blow the new piping clean with oil‑free, dry nitrogen before installing outlets, test each section at 1.5× operating pressure (but never less than 150 psi), locate and repair leaks, then purge and verify gas concentration before patient‑use (§ 1324.3, § 1324.4, § 1324.5.1.1) .


Requirements in detail

Key defined terms (bolded on first mention)

  • Blowdown — blowing the distribution piping clear with gas prior to installing outlets or sensitive components (§ 1324.4) .
  • Test gasoil‑free, dry nitrogen NF required for blowdown and many tests (§ 1324.3) .
  • Final tie‑in test — leak testing of the joints connecting new work to existing system using the system gas at normal operating pressure (§ 1324.5.9) .
  • Heavy, intermittent purging — the particulate removal purging required after construction debris may be present (§ 1324.5.8) .

When tests/operations must be done

  • Blowdown: after distribution piping is installed but before station outlet/inlet rough‑ins or other components are installed (§ 1324.4) .
  • Initial pressure tests: for each piping section (1) after blowdown, (2) after station outlet/inlet rough‑ins, and (3) before installing components that would be damaged by test pressure (§ 1324.5) .
  • Source shutoff: the source shutoff valve must remain closed during the pressure tests specified in § 1324.5 (§ 1324.5.1) .
  • Cross‑connection check: confirm no cross‑connections; piping reduced to atmospheric pressure; test charging for this cross‑connection check to 50 psi with oil‑free, dry nitrogen NF (§ 1324.5.2, § 1324.5.2.1–.3) .
  • Particulate removal: perform heavy, intermittent purging to remove construction particulates (§ 1324.5.8) .
  • Final tie‑in leak test: use the gas of system designation at normal operating pressure and a leak detectant safe for oxygen and free of ammonia; vacuum joints require ultrasonic detection or equivalent (§ 1324.5.9 and subsections) .
  • Records: permanent records of the final tie‑in tests must be maintained per NFPA 99 references in § 1324.5.9.4 .

Decision‑relevant values and actions (summary table)

Decision / value Required action or value Code Reference
Test gas for blowdown and most tests Oil‑free, dry nitrogen NF § 1324.3
When to perform blowdown After distribution piping installation but before station outlet/inlet rough‑ins or other components § 1324.4
Timing for initial pressure tests (1) After blowdown (2) After outlet/inlet rough‑ins (3) Before installing pressure‑sensitive components § 1324.5
Required test pressure (pressure gases & vacuum) 1.5 × system operating pressure, but not less than 150 psi (1034 kPa); maintain while inspecting joints with safe leak detectant § 1324.5.1.1
Cross‑connection verification charge Charge system under test to 50 psi (345 kPa) with oil‑free, dry nitrogen NF § 1324.5.2.3
Particulate removal Heavy, intermittent purging of pipeline to remove construction deposits § 1324.5.8
Final tie‑in leak test (pressure gases) Leak‑test joints with gas of system designation at normal operating pressure; use oxygen‑safe, ammonia‑free detectant § 1324.5.9
Vacuum joint testing method Use ultrasonic leak detector or equivalent capable of detecting leaks in an active vacuum system § 1324.5.9.1

Exceptions & special cases

  • The code text we retrieved does not provide alternate test pressures or specific exceptions for very high‑pressure systems beyond the 1.5×/150‑psi rule; if your system operating pressure would make 1.5× exceed typical fitting ratings, consult the AHJ and NFPA 99 references cited in the sections (§ 1324.5.1.1) .
  • Cryogenic central supply testing and specialized cryogenic procedures are addressed elsewhere (see referenced NFPA/ANSI standards); the CPC text we have points to specialized requirements for cryogenic systems but the detailed method is not reproduced in the retrieved snippets — consult § 1324.5.7.3 and the standards cited there for those specifics .
  • The CPC requires testing and certification by a technically competent third party per § 1324.5.7; where in‑house personnel perform testing, they must meet the competency criteria in the code (§ 1324.5.7.2–.3) .

If you need a ruling about a very specific, unusual pressure or material condition, the code references (NFPA 99 and ASSE/IAPMO/ANSI standards cited in these sections) will be the next source; the retrieved CPC excerpts do not include the full NFPA test tables or cryogenic details.


Common mistakes

  • Assuming atmospheric blowdown alone is sufficient — the CPC requires blowdown with oil‑free, dry nitrogen NF prior to installing outlets (§ 1324.4) .
  • Testing at the system operating pressure only — the code requires 1.5× operating pressure, but not less than 150 psi for pressure tests (§ 1324.5.1.1) .
  • Using a leak check fluid that is not safe for oxygen or that contains ammonia — the final tie‑in must use a detectant safe with oxygen and free of ammonia (§ 1324.5.9) .
  • Forgetting to keep the source shutoff valve closed during the pressure test (§ 1324.5.1) .
  • Failing to perform heavy, intermittent purging to remove particulates after construction — leaving particulate can cause downstream device problems and fails the requirement in § 1324.5.8 .
  • Not documenting test results — permanent records for final tie‑in tests are required (§ 1324.5.9.4) .

Worked example — tie‑in of a new oxygen branch to an existing system

Scenario: You are connecting a new branch of oxygen piping to an existing Category‑1 medical oxygen system whose normal operating pressure is 50 psi.

Step 1 — Blowdown: After the new distribution piping is installed, blow the pipe clear with oil‑free, dry nitrogen NF before installing station outlets or other components, per § 1324.4 .

Step 2 — Initial pressure test: Compute required test pressure: 1.5 × operating pressure = 1.5 × 50 psi = 75 psi, but the code requires not less than 150 psi, so you must test at 150 psi gauge. Maintain that pressure while examining EVERY joint with an oxygen‑safe, ammonia‑free leak detectant (§ 1324.5.1.1) . Ensure the source shutoff valve is closed during this test (§ 1324.5.1) .

Step 3 — Cross‑connection test: When verifying no cross‑connections, reduce other systems to atmospheric and charge the system under test with oil‑free, dry nitrogen NF to 50 psi for that check, per § 1324.5.2.3 .

Step 4 — Particle purge and final tie‑in: After final brazed connection and successful leak test, perform heavy, intermittent purging downstream to remove particulates (per § 1324.5.8) and purge the outlet(s) immediately downstream of the tie‑in in accordance with § 1324.5.9.2; then perform final leak test with the system gas at normal operating pressure and keep records (§ 1324.5.8, § 1324.5.9) cite .

Step 5 — Operational verification: Before use for patient care, perform the operational pressure and gas concentration checks required by the following operational test sections (see § 1324.5.10 and § 1324.5.11) — these are referenced in the CPC and must be completed before putting the new branch into service .


Related provisions

  • § 1324.3 — Test gas specification: oil‑free, dry nitrogen NF .
  • § 1324.5.1.1 — Required test pressure (1.5× operating pressure; not less than 150 psi) .
  • § 1324.5.2 — Initial cross‑connection test procedures and charging to 50 psi for that test .
  • § 1324.5.7 — System verification testing competency and third‑party tester requirements .
  • § 1324.5.10 — Operational flow/pressure drop tests at outlets/inlets .
  • § 1324.5.11 — Medical gas concentration testing after purging (§ references gas‑specific concentration checks) .

Code references

Grounded in the retrieved California Plumbing Code — click a citation to read the verbatim passage:

  • CPC § 1324.4 High relevance — show source text

    1324.4 Initial Piping Blowdown. Piping in medical gas and vacuum distribution systems shall be blown clear by means of oil-free, dry nitrogen NF after installation of the distribution piping but before installation of station outlet/inlet rough-in assemblies and other system components (e.g., pressure/vacuum alarm devices, pressure/vacuum indicators, pressure relief valves, manifolds, source equipment). [NFPA 99:5.1.12.2.2]

    1324.5 Initial Pressure Tests – Medical Gas and Vac- uum Systems. Each section of the piping in medical gas and vacuum systems shall be pressure tested. Initial pressure tests shall be conducted as follows:

    (1) After blowdown of the distribution piping.

    (2) After installation of station outlet/inlet rough-in assemblies.

    (3) Prior to the installation of components of the distribution piping system that would be damaged by the test pressure (e.g., pressure/vacuum alarm devices, pressure/vacuum indicators, line pressure relief valves). [NFPA 99:5.1.12.2.3.1, 5.1.12.2.3.2]

    296 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    HEALTH CARE FACILITIES AND MEDICAL GAS AND MEDICAL VACUUM SYSTEMS

    1324.5.1 Shutoff Valve. The source shutoff valve shall

    remain closed during tests specified in Section 1324.5 through Section 1324.5.1.2. [NFPA 99:5.1.12.2.3.3]

    1324.5.1.1 Required Test Pressure. The test pressure for pressure gases and vacuum systems shall be 1.5 times the system operating pressure but not less than a gauge pressure of 150 psi (1034 kPa). The test pressure shall be maintained until each joint has been examined for leakage by means of a leak detectant that is safe for use with oxygen and does not contain ammonia. [NFPA 99:5.1.12.2.3.4, 5.1.12.2.3.5]

    1324.5.1.2 Leaks. Leaks, if any, shall be located, repaired (if permitted), replaced (if required), and retested. [NFPA 99:5.1.12.2.3.6]

    1324.5.2 Initial Cross-Connection Test. It shall be

    determined that no cross-connections exist between the

    various medical gas and vacuum piping systems. [NFPA 99:5.1.12.2.4]

    1324.5.2.1 Atmospheric Pressure. All piping systems shall be reduced to atmospheric pressure.

    [NFPA 99:5.1.12.2.4.1]

    1324.5.2.2 Sources of Test Gas. Sources of test

    gas shall be disconnected from all piping systems, except for the one system being tested. [NFPA 99:5.1.12.2.4.2]

    1324.5.2.3 System to Be Charged. The system under test shall be charged with oil-free, dry nitrogen NF to a gauge pressure of 50 psi (345 kPa).

    [NFPA 99:5.1.12.2.4.3]

  • CPC § 1324.0 High relevance — show source text

    1324.0 Performance Criteria and Testing Category 1 (Gases, Medical Surgical Vacuum). 1324.1 Where Required. Inspection and testing shall be performed on components, or portions thereof, of new, piped medical gas or vacuum systems, additions, renovations, temporary installations, or repaired systems in accordance with Section 1324.2 through Section 1324.5.11, and certified in accordance with Section 1306.0.

    1324.2 Breached Systems. All systems that are breached and components that are subject to additions, renovations, or replacement (e.g., new gas sources: bulk, manifolds, compressors, dryers, alarms) shall be inspected and tested. Systems shall be deemed breached at the point of pipeline intrusion by physical separation or by system component removal, replacement, or addition. Breached portions of the systems subject to inspection and testing shall be confined to only the specific altered zone and components in the immediate zone or area that is located upstream for vacuum systems and downstream for pressure gases at the point or area of intrusion. [NFPA 99:5.1.12.1.3 – 5.1.12.1.5]

    1324.2.1 Reports. The inspection and testing reports shall be submitted directly to the party that contracted for the testing, who shall submit the report through channels to the responsible facility authority and any others that are required. Reports shall contain detailed listings of all findings and results. [NFPA 99:5.1.12.1.6, 5.1.12.1.7] 1324.3 Test Gas. The test gas shall be oil-free, dry nitrogen NF. [NFPA 99:5.1.12.2.1.2]

    1324.4 Initial Piping Blowdown. Piping in medical gas and vacuum distribution systems shall be blown clear by means of oil-free, dry nitrogen NF after installation of the distribution piping but before installation of station outlet/inlet rough-in assemblies and other system components (e.g., pressure/vacuum alarm devices, pressure/vacuum indicators, pressure relief valves, manifolds, source equipment). [NFPA 99:5.1.12.2.2]

    1324.5 Initial Pressure Tests – Medical Gas and Vac- uum Systems. Each section of the piping in medical gas and vacuum systems shall be pressure tested. Initial pressure tests shall be conducted as follows:

    (1) After blowdown of the distribution piping.

    (2) After installation of station outlet/inlet rough-in assemblies.

    (3) Prior to the installation of components of the distribution piping system that would be damaged by the test pressure (e.g., pressure/vacuum alarm devices, pressure/vacuum indicators, line pressure relief valves). [NFPA 99:5.1.12.2.3.1, 5.1.12.2.3.2]

    296 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    HEALTH CARE FACILITIES AND MEDICAL GAS AND MEDICAL VACUUM SYSTEMS

    1324.5.1 Shutoff Valve. The source shutoff valve shall

    remain closed during tests specified in Section 1324.5 through Section 1324.5.1.2. [NFPA 99:5.1.12.2.3.3]

  • CPC § 1324.5.8 High relevance — show source text

    1324.5.8 Particulate Matter. In order to remove any traces of particulate matter deposited in the pipelines as a result of construction, a heavy, intermittent purging of the pipeline shall be done. [NFPA 99:5.1.12.4.6]

    1324.5.9 Final Tie-In Test. Each joint in the final connection between the new work and the existing system shall be leak-tested with the gas of system designation at the normal operating pressure by means of a leak detectant that is safe for use with oxygen and does not contain ammonia. [NFPA 99:5.1.12.4.9.2]

    1324.5.9.1 Vacuum Joints. Vacuum joints shall be tested using an ultrasonic leak detector or other means that will allow detection of leaks in an active

    vacuum system. [NFPA 99:5.1.12.4.9.3] 1324.5.9.2 Pressure Gases. For pressure gases, immediately after the final brazed connection is made and leak-tested, an outlet in the new piping and an outlet in the existing piping that are immediately downstream from the point or area of intrusion shall be purged in accordance with the applicable requirements of Section 1324.5.8. [NFPA 99:5.1.12.4.9.4]

    1324.5.9.3 Positive Pressure Gases. Before the new work is used for patient care, positive pressure gases shall be tested for operational pressure and gas concentration in accordance with Section 1324.5.10 and Section 1324.5.11. [NFPA 99:5.1.12.4.9.5]

    1324.5.9.4 Permanent Records. Permanent

    records of these tests shall be maintained in accordance with NFPA 99. [NFPA 99:5.1.12.4.9.6]

    298 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    HEALTH CARE FACILITIES AND MEDICAL GAS AND MEDICAL VACUUM SYSTEMS

    1324.5.10 Operational Flow Pressure Drop Test. Operational flow pressure drop tests shall be performed at each station outlet/inlet or terminal where the user

    makes connections and disconnections. [NFPA 99: 5.1.12.4.10]

    1324.5.10.1 Medical-Surgical Vacuum Inlets. Medical-surgical vacuum inlets shall draw 3 SCFM (85 Nl/min) without reducing the vacuum pressure below 12 inch (305 mm) gauge HgV at any adjacent station inlet. [NFPA 99:5.1.12.4.10.4]

    1324.5.10.2 Oxygen and Medical Air Outlets. Oxygen and medical air outlets serving Category 1 space shall allow a transient flow rate of 6 SCFM (170 SLPM) for 3 seconds. [NFPA 99:5.1.12.4.10.5]

    1324.5.11 Medical Gas Concentration Test. After

    purging each system with the gas of system designation, the following shall be performed:

    (1) Each pressure gas source and outlet shall be analyzed for concentration of gas, by volume.

    (2) Analysis shall be conducted with instruments designed to measure the specific gas dispensed.

  • CPC § 1324.5.7 High relevance — show source text

    1324.5.7 System Verification. Verification tests shall be performed only after all tests required in Section

    1324.3 through Section 1324.5.5.7, Installer Performed Tests, have been completed. [NFPA 99:5.1.12.4.1.1] 1324.5.7.1 Test Gas. The test gas shall be oil-free, dry nitrogen NF or the system gas where permitted.

    [NFPA 5.1.12.4.1.2]

    1324.5.7.2 Approved Tester. Testing shall be conducted by a party technically competent and experienced in the field of medical gas and vacuum pipeline testing and meeting the requirements of ASSE/IAPMO/ANSI 6030, except as required by Section 1324.5.7.3. [NFPA 99:5.1.12.4.1.3]

    Testing shall be performed by a party other than the installing contractor. [NFPA 99:5.1.12.4.1.5]

    Where systems have not been installed by inhouse personnel, testing shall be permitted by personnel of that organization who meet the requirements of Section 1324.5.7.2. [NFPA 99:5.1.12.4.1.6]

    1324.5.7.3 Cryogenic Fluid Testing. Testing of the cryogenic fluid central supply system shall be conducted by a party technically competent and experienced in the field of cryogenic fluid systems and meeting the requirements of ASSE/IAPMO/ANSI 6035, in accordance with the mandatory requirements in CGA M-1. [NFPA 99:5.1.12.4.1.4]

    1324.5.8 Particulate Matter. In order to remove any traces of particulate matter deposited in the pipelines as a result of construction, a heavy, intermittent purging of the pipeline shall be done. [NFPA 99:5.1.12.4.6]

    1324.5.9 Final Tie-In Test. Each joint in the final connection between the new work and the existing system shall be leak-tested with the gas of system designation at the normal operating pressure by means of a leak detectant that is safe for use with oxygen and does not contain ammonia. [NFPA 99:5.1.12.4.9.2]

    1324.5.9.1 Vacuum Joints. Vacuum joints shall be tested using an ultrasonic leak detector or other means that will allow detection of leaks in an active

    vacuum system. [NFPA 99:5.1.12.4.9.3] 1324.5.9.2 Pressure Gases. For pressure gases, immediately after the final brazed connection is made and leak-tested, an outlet in the new piping and an outlet in the existing piping that are immediately downstream from the point or area of intrusion shall be purged in accordance with the applicable requirements of Section 1324.5.8. [NFPA 99:5.1.12.4.9.4]

    1324.5.9.3 Positive Pressure Gases. Before the new work is used for patient care, positive pressure gases shall be tested for operational pressure and gas concentration in accordance with Section 1324.5.10 and Section 1324.5.11. [NFPA 99:5.1.12.4.9.5]

  • CPC § 318.0. High relevance — show source text

    These tests shall be made using air, CO 2, or nitrogen pressure and shall be made in the presence of the Authority Having Jurisdiction. Necessary apparatus for conducting tests shall be furnished by the permit holder. Test gauges used in conducting tests shall be in accordance with Section 318.0.

    1213.4 Detection of Leaks and Defects. The piping system shall withstand the test pressure specified without showing any evidence of leakage or other defects. Any reduction of test pressures as indicated by pressure gauges shall be deemed to indicate the presence of a leak unless such reduction can be readily attributed to some other cause. [NFPA 54:8.1.5.1]

    1213.4.1 Detecting Leaks. The leakage shall be located by means of an approved gas detector, a noncorrosive leak detection fluid, or other approved leak detection methods. [NFPA 54:8.1.5.2]

    1213.4.2 Repair or Replace. Where leakage or other defects are located, the affected portion of the piping system shall be repaired or replaced and retested. [NFPA 54:8.1.5.3]

    1213.5 Piping System Leak Test. Leak checks using fuel gas shall be permitted in piping systems that have been pressure-tested in accordance with Section 1213.0 through Section 1213.4.2. [NFPA 54:8.2.1]

    1213.5.1 Turning Gas On. During the process of turning gas on into a system of new gas piping, the entire system shall be inspected to determine that there are no open fittings or ends and that all valves at unused outlets are closed and plugged or capped. [NFPA 54:8.2.2]

    1213.5.2 Leak Check. Immediately after the gas is turned on into a new system or into a system that has been initially restored after an interruption of service, the piping system shall be checked for leakage. Where leak

    age is indicated, the gas supply shall be shut off until the necessary repairs have been made. [NFPA 54:8.2.3]

    1213.5.3 Placing Appliances and Equipment in Operation. Appliances and equipment shall not be placed in operation until after the piping system has been checked for leakage in accordance with Section 1213.5.2, the piping system is purged in accordance with Section 1213.6, and connections to the appliance are checked for leakage. [NFPA 54:8.2.4]

    1213.6 Purging Requirements. The purging of piping shall be in accordance with Section 1213.6.1 through Section 1213.6.3. [NFPA 54:8.3]

    1213.6.1 Piping Systems Required to be Purged Outdoors. The purging of piping systems shall be in accordance with Section 1213.6.1.1 through Section 1213.6.1.5 where the piping system meets either of the following:

    (1) The design operating gas pressure is greater than 2 psig (14 kPa).

    (2) The piping being purged contains one or more sections of pipe or tubing meeting the size and length criteria of Table 1213.6.1. [NFPA 54:8.3.1]

    TABLE 1213.6.1

    SIZE AND LENGTH OF PIPING

  • CPC § 11.0 Medium relevance — show source text

    11.0 - 1.11.11_|||X|||||||||||||||||||||| |1.13.0||||||||||||||||||||X||||| |Division II - Scope and
    Administration||||||||||||||||||||||||| |101.0||||||||||X|X|X||X|X|||||||||| |102.0||||||||||X|X|X||X|X|||||||||| |103.0||||||||||X|X|X||X|X|||||||||| |104.2 Items 1 & 2||||X|X|||||||||||||||||||| |104.3.1||||||||||X|X|X||X|X|||||||||| |104.4.3.1|X|||||||||||||||||||||||| |105.0||||||||||X|X|X||X|X||||||||||

    This state agency does not adopt sections identified with the following symbol: The Office of the State Fire Marshal’s adoption of this chapter or individual sections is applicable to structures regulated by other state agencies pursuant to Section 1.11.0.

    2 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    CHAPTER 1

    ADMINISTRATION

    DIVISION I

    CALIFORNIA ADMINISTRATION

    1.1.0 General.

    1.1.1 Title. These regulations shall be known as the Califor- nia Plumbing Code, may be cited as such and will be referred to herein as “this code.” The California Plumbing Code is Part 5 of thirteen parts of the official compilation and publi- cation of the adoption, amendment, and repeal of plumbing regulations to the California Code of Regulations, Title 24, also referred to as the California Building Standards Code. This part incorporates by adoption the 2024 Uniform Plumb- ing Code of the International Association of Plumbing and Mechanical Officials with necessary California amendments.

    1.1.2 Purpose. The purpose of this code is to establish the minimum requirements to safeguard the public health, safety and general welfare through structural strength, means of egress facilities, stability, access to persons with disabilities, sanitation, adequate lighting and ventilation, and energy con- servation; safety to life and property from fire and other haz- ards attributed to the built environment; and to provide safety to fire fighters and emergency responders during emergency operations.

    1.1.3 Scope. The provisions of this code shall apply to the construction, alteration, movement, enlargement, replace- ment, repair, equipment, use and occupancy, location, main- tenance, removal, and demolition of every building or structure or any appurtenances connected or attached to such buildings or structures throughout the State of California.

  • CPC § 4.1 Medium relevance — show source text
    • 100°F
      (16°C-38°C)|1 h|6 h|2 h|12 h|6 h|24 h| |40°F-60°F
      (4°C-16°C)|2 h|12 h|4 h|24 h|12 h|48 h| |10°F- 40°F
      (-12°C+4°C)|8 h|48 h|16 h|96 h|48 h|8 days| |*If gaps or loose fits are encountered in the system, double these cure times.|*If gaps or loose fits are encountered in the system, double these cure times.|*If gaps or loose fits are encountered in the system, double these cure times.|*If gaps or loose fits are encountered in the system, double these cure times.|*If gaps or loose fits are encountered in the system, double these cure times.|*If gaps or loose fits are encountered in the system, double these cure times.|*If gaps or loose fits are encountered in the system, double these cure times.|

    2025 CALIFORNIA PLUMBING CODE 467

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    IS 33

    FIGURE 1

    LOCATION OF THRUST BLOCKS (STANDARD AND METRIC COMBINED) A COMPARISON OF THRUST-BLOCK AREAS (See Section 4.1)

    468 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    IS 33

    FIGURE 2

    THRUST BLOCK BEARING AREA (See Section 5.2.2)

    2025 CALIFORNIA PLUMBING CODE 469

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    IS 33

    Uniform Plumbing Code References for Ductile Iron and PVC Pressure Building Supply and Exterior Cold-Water Piping

    The following sections of the 2024 Uniform Plumbing Code apply to ductile iron and PVC pressure building supply and exterior cold-water piping.

    Chapter 3 General Regulations

    309.0 Workmanship

    312.0 Protection of Piping, Materials, and Struc tures

    313.0 Hangers, Supports, and Anchors

    314.0 Trenching, Excavation, and Backfill

    Chapter 6 Water Supply and Distribution

    604.0 Materials (water piping)

    Table 604.1 Materials for Building Supply and Water Distribution Piping and Fittings

    605.4 Ductile Iron Pipe and Joints

    605.12 PVC Plastic Pipe and Joints

    605.16.2 Plastic Pipe to Other Materials

    609.0 Installation, Testing, Unions, and Location

    Abbreviations

    IAPMO International Association of Plumbing and Mechanical Officials

    UPC Uniform Plumbing Code published by IAPMO

    AWWA American Water Works Association

    CSA Canadian Standards Association

    Applicable Standards.

    ASME B16.4 Gray Iron Threaded Fittings Classes 125 and 250

    ASTM D1785 Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120

    ASTM D2241 Poly (Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDR Series)

  • CPC § 103 Medium relevance — show source text
    FLOW
    GPM
    FIXTURE UNITS Col3
    FLOW
    GPM
    FLUSH VALVE
    TANKS
    FLUSHOMETER
    VALVES
    1 0
    2 1
    3 3
    4 4
    5 6
    6 7
    7 8
    8 10
    9 12
    10 13
    11 15
    12 16
    13 18
    14 20
    15 21
    16 23
    17 24
    18 26
    19 28
    20 30
    21 32
    22 34 5
    23 36 6
    24 39 7
    25 42 8
    26 44 9
    27 46 10
    28 49 11
    29 51 12
    30 54 13
    31 56 14
    32 58 15
    33 60 16
    34 63 18
    35 66 20
    36 69 21
    37 74 23
    38 78 25
    39 83 26
    40 86 28
    41 90 30
    42 95 31
    FLOW
    GPM
    FIXTURE UNITS Col3
    FLOW
    GPM
    FLUSH VALVE
    TANKS
    FLUSHOMETER
    VALVES
    43 99 33
    44 103 35
    45 107 37
    46 111 39
    47 115 42
    48 119 44
    49 123 46
    50 127 48
    51 130 50
    52 135 52
    53 141 54
    54 146 57
    55 151 60
    56 155 63
    57 160 66
    58 165 69
    59 170 73
    60 175 76
    62 185 82
    64 195 88
    66 205 95
    68 215 102
    70 225 108
    72 236 116
    74 245 124
    76 254 132
    78 264 140
    80 275 148
    82 284 158
    84 294 168
    86 305 176
    88 315 186
    90 325 195
    92 337 205
    94 348 214
    96 359 223
    98 370 234
    100 380 245
    105 406 270
    110 431 295
    115 455 329
    120 479 365

    558 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    USEFUL TABLES

    AREAS AND CIRCUMFERENCES OF CIRCLES

  • CPC § 1323.13.3 Medium relevance — show source text

    2, 1323.13.3| |1326.4 - 1326.10|1326.5 - 1326.11| |1505.6 - 1505.14|1505.5 - 1505.13| |Figure 1505.10|Figure 1505.9| |1506.6 - 1506.13|1506.5 - 1506.12| |1603.3 - 1603.4|1603.4 - 1603.5| |Table 1603.4|Table 1603.5| |1603.5 - 1603.19|1603.6 - 1603.20| |1603.20|1503.2.4| |L 402.9 - L 402.11|L 402.8 - L 402.10| |L 404.9 - L 404.12|L 404.8 - L 404.11| |L 411.5, L 411.6|L 411.2, L411.3| |L 411.7|L 411.4| |L 411.9 - L 411.12|L 411.5 - L 411.8|

    xxii 2025 CALIFORNIA PLUMBING CODE

    ), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.

    RELATED PUBLICATIONS AND SERVICES

    The Documents Listed are Not by this Reference Adopted by The State of California.

    IAPMO provides a variety of other products which are useful for inspectors, building officials, architects, engineers,

    manufacturers, contractors, plumbers, and apprentices.

    IAPMO Headquarters Directory

    4755 East Philadelphia Street, Ontario, California 91761-2816

    Publication Order Desk Phone: 800-85-IAPMO

    Publication Toll Free Fax: 877-85-CODES

    E-mail: iapmo@iapmo.org

    Website: www.iapmo.org

    Free Code Question: 800-201-0335

    Uniform Plumbing Code – 2024 Edition:

    The Uniform Plumbing Code is the most widely adopted plumbing code in the world. The 2024 edition contains complete “turnkey” requirements for the installation and maintenance of plumbing systems, all in one easy to use book.

    Uniform Plumbing Code Illustrated Training Manual:

    The UPC Illustrated Training Manual is an excellent reference for anyone involved in the plumbing industry. It contains an extensive definitions section and several hundred comprehensive technical diagrams and illustrations. It serves as a textbook, and it also is useful as a valuable tool for explaining the intent and use of the Code.

    Uniform Plumbing Code Study Guide:

    This book is the perfect complement to the UPC Illustrated Training Manual. Alone, it constitutes a complete self-study course for learning the UPC. It has hundreds of questions, general practice exams, and plumbing math, pipe sizing exercises and fitting identification. A big help in getting you ready for a certification exam!

    Guide to Important Code Questions to the Uniform Plumbing Code:

    An excellent reference for learning and understanding plumbing code changes and identifies code changes between editions. It is a useful tool for preparing code change proposals.

    Uniform Mechanical Code – 2024 Edition:

    The Uniform Mechanical Code contains complete requirements for the installation and maintenance of heating, ventilating, cooking and refrigeration systems.

    Uniform Mechanical Code Illustrated Training Manual:

    Contains technical diagrams and illustrations that demonstrate the intent and use of the UMC. A great reference for everyone involved in Mechanical HVACR design and installation.

    Uniform Mechanical Code Study Guide:

  • CPC § 102.3 Medium relevance — show source text

    1

    CEBC—25: California Existing Building Code

    102.3, 1011.5.2, 1103.1, 1104.18, 1105.5.2

    CMC—25: California Mechanical Code

    201.3, 308.3, 605.1, 605.2.1.1, 605.2.1.2, 605.2.1.3, 605.2.1.4, 605.2.1.5, 605.3, 605.4, 605.4.2.3, 605.4.2.5, 605.5.2, 605.7, 606.1, 606.2, 608.1, 608.3, 608.4, 608.5, 608.8, 608.9.1, 608.10, 608.17, 610.1.1, 903.2.11.4, 904.14, 907.3.1, 909.1, 909.10.2, 909.13.1, 910.4.7, 915.6.1, 1006.2.2.3, 1011.16, 1020.6.1, 1207.4.7, 1207.6.1, 1207.6.1.2.2, 1207.11.8, 2104.2.1, 2105.3, 2301.1, 2301.6, 2309.3.1.2, 2311.3.1, 2311.4.3, 2311.8.2, 2311.8.8, 2311.8.10, 2404.9, 2404.9.2, 2504.5, 2703.2.2, 2703.10.4, 2703.14, 2803.2, 2803.3, 3001.1, 3003.1, 3004.2, 3108.12.1, 3108.12.2, 3703.5, 3804.1.1.7, 3904.1, 3905.3, Table 5003.1.1(1), 5003.8.4.2, 5003.8.5.2, 5003.8.6.2, 5004.3.1, 5303.7.6, 5303.16.9, 5305.5, 5306.2.2, 5306.2.3, 5307.4.4, 5504.2.1.3, 5504.2.2.3, 5505.4.1.1, 5701.3, 5703.6.1, 5704.2.8.9, 5705.3.7.5.1, 5706.2, 5706.4.4, 6003.1.3, 6003.2.3.2, 6004.2.2.7, 6005.3.1, 6005.3.2, 6103.2.1.7

    CPC—25: California Plumbing Code

  • California Plumbing Code Medium relevance — show source text


    2
    5
    10
    15
    20
    30|184
    175
    215
    265
    312
    360
    461|1168
    823
    806
    777
    750
    723
    670|647
    533
    521
    501
    481
    461
    426|229
    219
    269
    327
    379
    433
    541|1542
    1069
    1049
    1017
    985
    955
    895|852
    698
    684
    662
    638
    615
    574|312
    296
    366
    440
    507
    570
    704|1971
    1346
    1324
    1287
    1251
    1216
    1147|1056
    863
    846
    821
    794
    768
    720|454
    424
    524
    620
    702
    780
    937|2996
    1999
    1971
    1927
    1884
    1841
    1759|1545
    1308
    1283
    1243
    1205
    1166
    1101| |50|0
    2
    5
    10
    15
    20
    30|176
    168
    204
    253
    299
    345
    442|1292
    971
    953
    923
    894
    866
    809|704
    613
    602
    583
    562
    543
    502|220
    209
    257
    313
    363
    415
    521|1724
    1273
    1252
    1217
    1183
    1150
    1086|948
    811
    795
    765
    736
    708
    649|295
    280
    347
    418
    481
    544
    674|2223
    1615
    1591
    1551
    1512
    1473
    1399|1189
    1007
    991
    963
    934
    906
    848|428
    401
    496
    589
    668
    741
    892|3432
    2426
    2396
    2347
    2299
    2251
    2159|1818
    1509
    1490
    1455
    1421
    1387
    1318| |100|0
    2
    5

  • CPC § 101.2.2 Medium relevance — show source text

    CFC—25: California Fire Code

    101.2.2, 101.4.2, 301.3.1, 302.2, 307.1, 308.1, 802.2.1, 802.2.3, 803.2.3, 803.4.1.1, 803.4.1.2, 803.4.1.3, 803.4.1.4, 803.4.1.5, 803.4.1.6, Table 804.5.1.1(1), 904.1.5, 1011.6.1.1, 1303.1.2, 1305.2.8.1, 1305.2.14, 1305.2.14.1, 1401.2, 1501.1, 1501.5, 1502.1, 1502.1.1, 1502.2, 1502.3, 1504.1, 1507.1, 1507.2

    CMC—25: California Mechanical Code

    302.2, 702.7, 807.1, 902.1.1, 1008.1, 1305.2.7.1, 1305.2.8, 1305.2.8.1

    CPC—25: California Plumbing Code

    302.2, 408.1, 702.7, 1009.1, 1009.2, 1009.3, 1009.5, 1302.1.6, 1503.1

    16-4 2025 CALIFORNIA EXISTING BUILDING CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    REFERENCED STANDARDS

    CRC—25: California Residential Code

    101.2, 101.4.1, 104.3.1, 109.3.3, 109.3.10, 302.2, 307.1, 308.1, 401.3, 402.1, 405.2.6, 502.2, 502.3, 502.4, 503.2, 503.3, 503.11, 505.2, 505.3, 507.3, 701.3, 702.4, 702.5, 706.2, 708.1, 805.2, 806.4, 809.1, 906.2, 907.1, 1011.2.1, 1103.1, 1103.2, 1103.3, 1104.1, 1201.4, 1302.1.2, 1302.1.3, 1302.1.3, 1303.1.3, 1401.2, 1402.1, 1402.2, 1402.2.1, 1402.3, 1402.4, 1402.5, 1402.6

    ICC 300—2023: ICC Standard on Bleachers, Folding and Telescopic Seating and Grandstands

    301.1.1, 401.1.1, 1401.1.1

    ICC A117.1—2017: Accessible and Usable Buildings and Facilities

Frequently asked questions

Who must perform the tests?

Testing must be done by a party technically competent in medical gas and vacuum pipeline testing; the code prefers an independent tester meeting the competency standards referenced in § 1324.5.7.2–.3 .

What gas is used for blowdown and pressure testing?

Oil‑free, dry nitrogen NF is the test gas specified for blowdown and many verification tests (§ 1324.3) .

What test pressure do I use if my system operates at 100 psi?

Use 1.5 × 100 psi = 150 psi; because the rule is 1.5× operating pressure but not less than 150 psi, you would still test at 150 psi in this case (§ 1324.5.1.1) .

How must vacuum joints be tested?

Vacuum joints must be tested using an ultrasonic leak detector or other method capable of detecting leaks in an active vacuum system (§ 1324.5.9.1) .

Can I use a soap solution for leak detection on oxygen piping?

No — the code requires leak detectant that is safe for use with oxygen and does not contain ammonia for final tie‑in leak tests (§ 1324.5.9) .

Must final test records be kept?

Yes — permanent records of the final tie‑in tests are required to be maintained as stated in § 1324.5.9.4 .

More in California Plumbing Code

Ask about the CPC

Get cited, plain-English answers on the California Plumbing Code for your project — any code section, any scenario.

Start Free Trial

Related in the CPC