Skip to content

Rev. Proc. 2015-13, is waived. See section 5.02 or 5.03 of Rev. Proc. 2011-46, as applicable, for

SECTION 19. SPECIAL RULES FOR LONG-TERM CONTRACTS (§ 460)

Internal Revenue Bulletin 2022-7 · 2026-10-03 edition · updated 2026-10-04 · United States

.01 Small business taxpayer exceptions from requirement to account for certain long-term contracts under § 460 or to capitalize costs under § 263A for certain home construction contracts.

(1) Description of change . This change applies to a taxpayer that (a) wants to change its method of accounting for exempt long-term construction contracts described in § 460(e)(1)(B) from the percentage-of-completion method of accounting described in § 1.460-4(b) to an exempt contract

Bulletin No. 2022–7 679 February 14, 2022

method of accounting described in § 1.460-4(c); or (b) chooses to stop capitalizing costs under § 263A for home construction contracts described in § 460(e)(1)(A) and meets the requirements of § 460(e)(1)(B)(i) and (ii).

(2) Inapplicability . A taxpayer can use a method of accounting for its exempt long-term contracts that is different from the method used for contracts that are not exempt. Thus, a taxpayer must use the percentage-of-completion method of accounting for nonresidential long-term construction contracts that do not meet the requirements of § 460(e)(1)(B), proposed §1.460-3(b)(1)(ii), or §1.460-3(b)(1)(ii), as applicable, in the first taxable year it enters into such a contract, but must continue to use its exempt contract method of accounting for its existing exempt long-term construction contracts. Similarly, in the first taxable year that a taxpayer enters into a nonresidential long-term construction contract that meets the requirements of § 460(e)(1)(B), proposed §1.4603(b)(1)(ii), or §1.460-3(b)(1)(ii), as applicable, the taxpayer can use a permissible exempt contract method of accounting for such a contract. Rev. Rul. 92-28, 1992-1 C.B. 153. Accordingly, only a taxpayer who previously adopted the percentage-of-completion method of accounting for exempt long-term construction contracts and wants to change to another permissible exempt contract method of accounting is required to request consent to change under this section 19.01. Similarly, a taxpayer that enters into a home construction contract described in § 460(e)(1)(A) and that meets the requirements of § 460(e)(1)(B)(i) and (ii) requires consent to change its method of accounting to not capitalize costs under § 263A only if the taxpayer has previously applied § 263A to home construction contracts exempt from the capitalization requirement under § 460(e)(1).

(3) Manner of making change . This change is made on a cut-off basis and applies only to longterm construction contracts entered into on or after the first day of the year of change. Accordingly, a § 481(a) adjustment is neither permitted nor required.

(4) Certain eligibility rule temporarily inapplicable . The eligibility rule in section 5.01(1)(f) of Rev. Proc. 2015-13, 2015-5 I.R.B. 419, does not apply to this change for a taxpayer’s first, second, or third taxable year ending after December 31, 2017.

(5) Reduced filing requirement . A taxpayer is required to complete only the following information on Form 3115 (Rev. December 2018) to make this change:

(a) The identification section of page 1 (above Part I);

(b) The signature section at the bottom of page 1;

(c) Part I;

(d) Part II, all lines except line 16;

(e) Part IV, line 25; and

(f) Schedule D, Part I.

(6) Designated automatic accounting method change number . The designated automatic accounting method change number for a change under this section 19.01 is “236.”

February 14, 2022 680 Bulletin No. 2022–7

(7) Contact information . For further information regarding changes under this section, contact Innessa Glazman at (202) 317-7006 (not a toll-free number).

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Internal Revenue Bulletin 2022-7

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.