SECTION 3. METHODS FOR
Internal Revenue Bulletin 2013-20 · 2026-10-03 edition · updated 2026-10-04 · United States
ESTABLISHING BEGINNING OF CONSTRUCTION
This notice provides two methods that a taxpayer may use to establish that construction of a qualified facility has begun. A taxpayer may establish the beginning of construction by starting physical work of a significant nature as described in section 4. Alternatively, a taxpayer may establish the beginning of construction by meeting the safe harbor provided in section 5 (Safe Harbor). Although a taxpayer may satisfy both methods, a taxpayer need only satisfy one method to establish that construction of a facility has begun for the purpose of qualifying for the PTC or ITC.
2013–20 I.R.B. 1085 May 13, 2013
trols the turbines, and associated power conditioning equipment. The entire wind farm will be connected to the power grid through a single intertie, and power generated by the wind farm will be sold to a local utility through a single power purchase agreement. In 2013, for 10 of the 50 turbines, X excavates the site for the foundations of the wind turbines and pours concrete for the supporting pads. Thereafter, X completes the construction of all 50 turbines and related facilities pursuant to a continuous program of construction (as determined under section 4.06). For purposes of sections 45 and 48, the entire wind farm is a single project that will be treated as a single facility, and X has performed physical work of a significant nature that constitutes the beginning of construction of that facility in 2013.
.05 Property integral to the facility
- (1) In general . Only physical work of a significant nature on tangible personal property and other tangible property used as an integral part of the activity performed by the facility will be considered for purposes of determining whether a taxpayer has begun construction of a facility. This includes property integral to the production of electricity, but does not include property used for electrical transmission. Thus, physical work on a transmission tower located at the site is not physical work of a significant nature because the transmission is not an integral part of the activity performed by the facility. However, physical work on a custom-designed transformer that steps up the voltage of electricity produced at the facility to the voltage needed for transmission is physical work of a significant nature with respect to the facility because power conditioning equipment is an integral part of the activity performed by the facility.
(2) Roads . Roads that are integral to the facility are integral to the activity performed by the facility; these include onsite roads that are used for moving materials to be processed (for example, biomass) and roads for equipment to operate and maintain the qualified facility. Starting construction on these roads constitutes physical work of a significant nature with respect to the facility. Roads primarily for access to the site, or roads used primarily for employee or visitor vehicles are not integral to the activity performed by the facility; physical work of a significant nature
erly included in the depreciable basis of the facility. Preliminary activities include planning or designing, securing financing, exploring, researching, obtaining permits, licensing, conducting surveys, environmental and engineering studies, clearing a site, test drilling of a geothermal deposit, test drilling to determine soil condition, or excavation to change the contour of the land (as distinguished from excavation for footings and foundations). Removal of existing turbines and towers is preliminary work and, therefore, does not constitute physical work of a significant nature with respect to the facility.
(2) Inventory . Physical work of a significant nature does not include work (performed either by the taxpayer or by another person under a binding written contract) to produce property that is either in existing inventory or is normally held in inventory by a vendor.
.03 Construction by contract . For property that is manufactured, constructed, or produced for the taxpayer by another person under a binding written contract (as described in section 4.03(1)), the work performed under the contract is taken into account in determining when physical work of a significant nature begins, provided the contract is entered into prior to the work taking place.
(1) Binding written contract . A contract is binding only if it is enforceable under local law against the taxpayer or a predecessor and does not limit damages to a specified amount (for example, by use of a liquidated damages provision). For this purpose, a contractual provision that limits damages to an amount equal to at least five percent of the total contract price will not be treated as limiting damages to a specified amount. For additional guidance regarding the definition of a binding contract, see § 1.168(k)–1(b)(4)(ii)(A)–(D).
(2) Master contract . If a taxpayer enters into a binding written contract for a specific number of components to be manufactured, constructed, or produced for the taxpayer by another person under a binding written contract (a “master contract”), and then through a new binding written contract (a “project contract”) the taxpayer assigns its rights to certain components to an affiliated special purpose vehicle that will own the facility for which such property is to be used, work performed with respect to the master contract may be taken
into account in determining when physical work of a significant nature begins with respect to the facility.
.04 Facility - (1) In general . A facility (within the meaning of section 45(d)) generally includes all components of property that are functionally interdependent. Components of property are functionally interdependent if the placing in service of each of the components is dependent upon the placing in service of each of the other components in order to generate electricity. For example, on a wind farm for the production of electricity from wind energy, an electricity-generating wind turbine, its tower, and its supporting pad comprise a single facility. Each such facility can be separately operated and metered and can begin producing electricity separately. See Rev. Rul. 94–31, 1994–1 C.B. 16.
(2) Single project . Solely for purposes of determining whether construction of a facility has begun for purposes of sections 45 and 48, multiple facilities that are operated as part of a single project (along with any property, such as a computer control system, that serves some or all such facilities) will be treated as a single facility. Whether multiple facilities are operated as part of a single project will depend on the relevant facts and circumstances. Factors indicating that multiple facilities are operated as part of a single project include, but are not limited to:
(a) The facilities are owned by a single legal entity;
(b) The facilities are constructed on contiguous pieces of land;
(c) The facilities are described in a common power purchase agreement or agreements;
(d) The facilities have a common intertie;
(e) The facilities share a common substation;
(f) The facilities are described in one or more common environmental or other regulatory permits;
(g) The facilities were constructed pursuant to a single master construction contract; and
(h) The construction of the facilities was financed pursuant to the same loan agreement.
(3) Example . X is developing a wind farm that will consist of 50 turbines, their associated towers, their supporting pads, a computer system that monitors and con
May 13, 2013 1086 2013–20 I.R.B.
tion of the facility will be determined by the relevant facts and circumstances. Facts and circumstances indicating continuous efforts to advance towards completion of the facility may include, but are not limited to:
(a) paying or incurring additional amounts included in the total cost of the facility;
(b) entering into binding written contracts for components or future work on construction of the facility;
(c) obtaining necessary permits; and (d) performing physical work of a significant nature (as described in section 4.02). (2) Disruptions to continuous efforts . Certain disruptions in the taxpayer’s continuous efforts to advance towards completion of the facility that are beyond the taxpayer’s control will not be considered as indicating that a taxpayer has failed to make continuous efforts to advance towards completion of the facility. Examples of such disruptions include, but are not limited to:
(a) severe weather conditions; (b) natural disasters; (c) licensing and permitting delays; (d) delays at the written request of a state or federal agency regarding matters of safety, security, or similar concerns;
(e) labor stoppages; (f) inability to obtain specialized equipment of limited availability;
(g) the presence of endangered species; (h) financing delays of less than six months; and
(i) supply shortages. .03 Cost overruns - (1) Single project . If the total cost of a facility that is a single project comprised of multiple facilities (as described in section 4.04(2)) exceeds its anticipated total cost, so that the amount a taxpayer actually paid or incurred with respect to the facility before January 1, 2014, is less than five percent of the total cost of the facility at the time the facility is placed in service, the Safe Harbor is not fully satisfied. However, the Safe Harbor will be satisfied and the PTC or ITC may be claimed with respect to some, but not all, of the individual facilities (as described in section 4.04(1)) comprising the single project, as long as the total aggregate cost of those individual facilities is not more than twenty times greater than the amount the taxpayer paid or incurred
on these roads is not considered for purposes of determining whether a taxpayer has begun construction of a facility.
(3) Fencing . Generally, fencing is not an integral part of the facility because it is not integral to the activity performed by the facility.
(4) Buildings . Generally, buildings are not integral parts of the facility because they are not integral to the activity of the facility. However, the following structures are not treated as buildings for this purpose: (1) a structure that is essentially an item of machinery or equipment, or (2) a structure that houses property that is integral to the activity of the facility if the use of the structure is so closely related to the use of the housed property that the structure clearly can be expected to be replaced when the property it initially houses is replaced. See Treas. Regs. § 1.48–1(e)(1).
.06 Continuous construction - (1) In general . A continuous program of construction involves continuing physical work of a significant nature (as described in section 4.02). Whether a taxpayer maintains a continuous program of construction will be determined by the relevant facts and circumstances.
(2) Construction disruptions . Certain disruptions in the taxpayer’s construction of a facility that are beyond the taxpayer’s control will not be considered as indicating that a taxpayer has failed to maintain a continuous program of construction. Examples of such disruptions include, but are not limited to:
(a) severe weather conditions; (b) natural disasters; (c) licensing and permitting delays; (d) delays at the written request of a state or federal agency regarding matters of safety, security, or similar concerns;
(e) labor stoppages; (f) inability to obtain specialized equipment of limited availability;
(g) the presence of endangered species; (h) financing delays of less than six months; and
(i) supply shortages.