SECTION 4. SECTION 48A PHASE III
Internal Revenue Bulletin 2012-33 · 2026-10-03 edition · updated 2026-10-04 · United States
PROGRAM
.01 In General . The Service will consider a project under the § 48A Phase III program only if DOE provides a certification (“DOE certification”) and ranking (if any) for the project. Accordingly, a taxpayer must submit, for each project: (i) an application for certification by DOE that the project is technically and economically feasible (“application for DOE certification”), and (ii) an application for certification under § 48A(d)(4) by the Service (“application for § 48A certification”).
.02 Program Specifications . (1) The Service determines the amount of the § 48A Phase III credits allocated to a project at the time the Service accepts the application for § 48A certification for that project in accordance with this notice (see section 5 of this notice for the requirements applicable to the application for DOE certification and the application for § 48A certification).
(2) Section 48A Phase III credits in the amount of $658,500,000 are available for allocation in the 2012–2013 round. The credits will not be separated into pools based on the type of projects or the type of primary feedstock.
(3) The § 48A Phase III credit for a taxable year is an amount equal to 30 percent of the qualified investment (as defined in § 48A(b)) for that taxable year in a qualifying advanced coal project (as defined in § 48A(c)(1) and § 48A(e)). This rule applies to both facilities that use an IGCC (as defined in § 48A(c)(7)) and those that use other advanced coal-based generation technologies (as defined in § 48A(f)).
to those specified in § 48A(e)(3)(B) and (C), but does not adopt the feedstock rules of § 48A(e)(3)(A).
.11 Section 48A(d)(5) provides that the Secretary shall, upon making a certification under § 48A(d), publicly disclose the identity of the applicant and the amount of the credit certified with respect to such applicant.
.12 Section 48A(h) directs the Secretary to modify the terms of any competitive certification award to permit a change of coal project site if such change (i) is consistent with the objectives of § 48A, (ii) is requested by the recipient, and (iii) involves moving the project site to improve the potential to capture and sequester CO 2 emissions, reduce costs of transporting feedstock, and serve a broader customer base. This directive does not apply if the Secretary determines that the dollar amount of tax credits available to the taxpayer under § 48A would increase as a result of the modification or such modification would result in such project not being originally certified. In addition, the Secretary is required to consult with other relevant Federal agencies, including the Department of Energy, in considering any modification under § 48A(h).
.13 The at-risk rules in § 49 and the recapture and other special rules in § 50 apply to the qualifying advanced coal project credit.
Get a plain-English answer with a citation back to this text.
Ask AI about this code