a. In general . New CREB volume cap under § 54C will be allocated in accordance with this section for qualified projects for which Applications meeting the requirements of this notice have been filed with the IRS on or before the Application deadline set forth in this notice. For purposes of this section 6, all Related Projects, as defined in section 3(f)(iii), will be treated as a single project.

company” is a mutual or cooperative electric company described in §§ 501(c)(12) or 1381(a)(2)(C) of the Code. The Application must demonstrate that the entity is a public power provider, governmental body, or cooperative electric company within the meaning of § 54C(d)(2), (3), and (4), respectively.

(ii) Qualified project . Each Application must describe in reasonable detail the qualified renewable energy facility or facilities constituting the project to be financed with the proceeds of the New CREBs. The Application must demonstrate that each project will constitute a “qualified renewable energy facility” under § 54C(d)(1). The Application must indicate the expected date that the acquisition and construction of each project will commence and the expected date that each project will be placed in service.

The Application must contain a certification by an independent, licensed engineer that each project will meet the requirements for a “qualified facility” under § 45(d) (but without regard to § 45(d)(8) and (10) and to any placed in service date), and that the project will be technically viable and will produce electricity.

If the project is a qualified hydropower facility under § 45(d)(9) producing incremental hydropower production (as defined under § 45(c)(8)(B)), then the certification also must state that the project consists only of efficiency improvements or additions to capacity that produce additional production as described in § 45(c)(8)(B) based on a methodology that would meet Federal Energy Regulatory Commission (FERC) standards. If the project is a qualified hydropower facility under § 45(d)(9) for qualified hydropower production at a nonhydroelectric dam under § 45(c)(8)(C), then the certification also must state that: (i) the facility, when constructed, will meet FERC licensing requirements and other applicable environmental, licensing and regulatory requirements; and (ii) the facility will be operated so that the water surface elevation at any given location and time that would have occurred in the absence of the hydroelectric project is maintained, subject to any license requirements imposed under applicable law that change the water surface elevation for the purpose of improving environmental quality of the affected waterway.

(iii) Prior allocations and related projects . Each Application must describe the amount of CREB volume cap previously allocated to each project under § 54 of the Code described in the Application and to any “related projects.” For purposes of this notice and the Application, the term “related projects” means projects that are owned by the same entity, or a “related party” as defined in § 1.150–1(b), that are of the same type under § 45(d), located on the same site, and integrated, interconnected, or directly or indirectly dependent on each other, based on all the facts and circumstances (“Related Projects”). For purposes of the allocation methodology described in section 6 of this notice, a facility the construction of which causes an increase in capacity (measured in units of power) of a project for which an Applicant previously received an allocation under § 54 will not be treated as a Related Project with respect to such project.

(iv) Location of project . The Application must indicate the location of the project.

(v) Regulatory approvals . The Application must describe a plan to obtain all necessary Federal, state and local regulatory approvals for the project.

g. Plan of financing . The Application must contain a reasonably detailed description of the plan of financing for the project, including all reasonably expected sources and uses of financing and other funds, the status of such financing, the anticipated date of bond issuance, the sources of security and repayment for the bonds, the aggregate face amount of bonds expected to be issued for the project, and the issuer’s reasonably expected schedule for spending proceeds of New CREBs. If the owner intends to use the proceeds of New CREBs to reimburse amounts paid with respect to a qualified project, the Application must demonstrate that the requirements under § 54A(d)(2)(D) will be met.

h. Dollar amount of allocation re- quested . The Application must specify the dollar amount of the volume cap requested for the project.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Internal Revenue Bulletin 2009-17

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.