PART 886—SECTION 8 HOUSING ASSISTANCE PAYMENTS PROGRAM—SPECIAL ALLOCATIONS›Subpart A—Additional Assistance Program for Projects With HUD-Insured and HUD-Held Mortgages
§ 886.127 Lease requirements.
24 C.F.R. Parts 880, 881, 883, 886 — Section 8 Project-Based Programs (New Construction; Substantial Rehabilitation; State Housing Agencies; Loan Management/Property Disposition Set-Asides) · 2026 edition · updated 2026-07-29 · United States
(a) Term of lease. (1) The term of a lease, including a new lease or a lease amendment, executed by the owner and the family must be for at least one year, or the remaining term of the contract if the remaining term of the contract is less than one year.
(2) During the first year of the lease term, the owner may not terminate the tenancy for “other good cause” under 24 CFR 247.3(a)(3), unless the termination is based on family malfeasance or nonfeasance. For example, during the first year of the lease term, the owner may not terminate the tenancy for “other good cause” based on the failure by the family to accept the offer of a new lease.
(3) The lease may contain a provision permitting the family to terminate the lease on 30 days advance written notice to the owner. In the case of a lease term for more than one year, the lease must contain this provision.
(b) Required and prohibited provisions. The lease between the owner and the family must comply with HUD regulations and requirements, and must be in the form required by HUD. The lease may not contain any of the following types of prohibited provisions:
(1) Admission of guilt. Agreement by the family (i) to be sued, (ii) to admit guilt, or (iii) to a judgment in favor of the owner, in a court proceeding against the family in connection with the lease.
(2) Treatment of family property. Agreement by the family that the owner may take or hold family property, or may sell family property, without notice to the family and a court decision on the rights of the parties.
(3) Excusing owner from responsibility. Agreement by the family not to hold the owner or the owner's agents responsible for any action or failure to act, whether intentional or negligent.
(4) Waiver of notice. Agreement by the family that the owner does not need to give notice of a court proceeding against the family in connection with the lease, or does not need to give any notice required by HUD.
(5) Waiver of court proceeding for eviction. Agreement by the family that the owner may evict the family (i) without instituting a civil court proceeding in which the family has the opportunity to present a defense, or (ii) before a decision by the court on the rights of the parties.
(6) Waiver of jury trial. Agreement by the family to waive any right to a trial by jury.
(7) Waiver of appeal. Agreement by the family to waive the right to appeal, or to otherwise challenge in court, a court decision in connection with the lease.
(8) Family chargeable with legal costs regardless of outcome. Agreement by the family to pay lawyer's fees or other legal costs of the owner, even if the family wins in a court proceeding by the owner against the family. (However, the family may have to pay these fees and costs if the family loses.)
(c) Notification for nonpayment of rent. The lease must contain a provision or addendum that tenants will receive notification at least 30 days before a formal judicial eviction is filed.
[53 FR 3368, Feb. 5, 1988, as amended at 89 FR 101303, Dec. 13, 2024]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — 24 C.F.R. Parts 880, 881, 883, 886 — Section 8 Project-Based Programs (New Construction; Substantial Rehabilitation; State Housing Agencies; Loan Management/Property Disposition Set-Asides)
- 24 C.F.R. Parts 880, 881, 883, 886 — Section 8 Project-Based P…
- PART 880—SECTION 8 HOUSING ASSISTANCE PAYMENTS PROGRAM FOR NEW…
- PART 881—SECTION 8 HOUSING ASSISTANCE PAYMENTS PROGRAM FOR SUB…
- PART 883—SECTION 8 HOUSING ASSISTANCE PAYMENTS PROGRAM—STATE H…
-
▸ PART 886—SECTION 8 HOUSING ASSISTANCE PAYMENTS PROGRAM—SPECIAL…
Overview-
▸ Subpart A—Additional Assistance Program for Projects With HUD-…
Overview- § 886.101 Applicability.
- § 886.102 Definitions.
- § 886.103 Allocation of Section 8 contract authority.
- § 886.104 Invitations to participate.
- § 886.105 Content of application; Disclosure.
- § 886.106 Notices.
- § 886.107 Approval of applications.
- § 886.108 Maximum annual contract commitment.
- § 886.109 Housing assistance payments to owners.
- § 886.110 Contract rents.
- § 886.111 Term of contract.
- § 886.111a Notice upon contract expiration.
- § 886.112 Rent adjustments.
- § 886.113 Physical condition standard; physical inspection req…
- § 886.114 Equal opportunity requirements.
- § 886.115 [Reserved]
- § 886.116 Security and utility deposits.
- § 886.117 [Reserved]
- § 886.118 Amount of housing assistance payments in projects re…
- § 886.119 Responsibilities of the owner.
- § 886.120 Responsibility for contract administration.
- § 886.121 Marketing.
- § 886.122 [Reserved]
- § 886.123 Maintenance, operation, and inspections.
- § 886.124 Reexamination of family income and composition.
- § 886.125 Overcrowded and underoccupied units.
- § 886.126 Adjustment of utility allowances.
- § 886.127 Lease requirements.
- § 886.128 Termination of tenancy.
- § 886.129 Leasing to eligible families.
- § 886.130 Management and occupancy reviews.
- § 886.131 Audit.
- § 886.132 Tenant selection.
- § 886.138 Displacement, relocation, and acquisition.
- § 886.139 Emergency transfers for victims of domestic violence…
- § 886.140 Broadband infrastructure.
- Subpart B [Reserved]
- Subpart C—Section 8 Housing Assistance Program for the Disposi…
-