PART 58—ENVIRONMENTAL REVIEW PROCEDURES FOR ENTITIES ASSUMING HUD ENVIRONMENTAL RESPONSIBILITIESSubpart D—Environmental Review Process: Documentation, Range of Activities, Project Aggregation and Classification

§ 58.36 Environmental assessments.

24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-performed and responsible-entity NEPA procedures) · 2026 edition · updated 2026-07-29 · United States

If a project is not exempt or categorically excluded under §§ 58.34 and 58.35, the responsible entity must prepare an EA in accordance with subpart E of this part. If it is evident without preparing an EA that an EIS is required under § 58.37, the responsible entity should proceed directly to an EIS.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — 24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-performed and responsible-entity NEPA procedures)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.