10-1.810 Construction Inspection.
Walnut Creek Zoning Code · 2026-06 edition · ingested 2026-07-07 · Walnut Creek
General. All improvements are subject to inspection by the City Engineer or authorized personnel in accordance with the City's Standard Specifications.
Preconstruction Conference. Prior to commencing any construction, the developer shall arrange for a preconstruction conference with the Senior Engineering Inspector of the Community Development Department.
Final Inspection and Deficiency List. Upon completion of the subdivision improvements, the developer shall apply in writing to the Senior Engineering Inspector for final inspection. The Senior Engineering Inspector or authorized representative shall schedule a preliminary final inspection.
A deficiency list shall be compiled during the inspection, noting all corrections or any additional work required. If the number of items is excessive or the subdivision appears incomplete, the preliminary final inspection may be halted and rescheduling of a date as determined by the Senior Engineering Inspector or authorized representative.
When the preliminary final inspection has been completed, a copy of the deficiency list shall be transmitted to the subdivider for correction.
Upon having completed all corrections or additional work as outlined by the deficiency list, the developer shall state in writing that all corrections have been completed satisfactorily and request a final inspection. The Senior Engineering Inspector or authorized representative shall then make a final inspection.
Upon finding that all items on the deficiency list have been corrected and receipt of as-built improvement plans, the subdivision improvements shall be placed on the Council agenda for acceptance or accepted by the City
Engineer in the manner provided by this chapter.
The completion of corrections indicated by the deficiency list shall not relieve the developer from the responsibility of correcting any deficiency not shown on the list that may be subsequently discovered.