18.110.010 - Purpose of Chapter¶
This Chapter provides requirements for subdivision survey work, and the placement of subdivision monuments.
18.110.020 - Survey Procedure and Practice¶
The procedure and practice of all survey work done on any subdivision, whether for preparation of a Final Map or Parcel Map shall conform to the standard practices and principles of land surveying, the California Land Surveyor's Act, the Public Improvement and Engineering Standards, and the provisions of this Chapter. All related documents shall be executed by a Land Surveyor registered in the State of California.
A. Traverse. The traverse of the exterior boundaries of the subdivision computed from field measurements of the ground must close within a limit of error of one foot to 10,000 feet of perimeter before balancing the survey.
B. Field notes. When required by the Town Engineer, the engineer or surveyor making the survey shall prepare complete field notes, in a form satisfactory to the Town Engineer, showing references, ties, locations, elevations and other necessary data relating to monuments, set in compliance with these regulations, and shall submit the notes to the Town Engineer to be indexed and retained as a part of the permanent public record of his office.
C. Geodetic monuments. Whenever the Town Engineer has established a system of coordinates which is within a reasonable distance of the subdivision boundary, as determined by the Town Engineer, the field survey shall be tied into the system.
18.110.030 - Monuments¶
In surveying a subdivision, the engineer or surveyor shall set sufficient permanent monuments so that any part of the survey may be readily retraced. Survey monuments shall be set by the engineer or surveyor for all new subdivisions requiring a Parcel Map or Final Map, in compliance with the Public Improvement and Engineering Standards and this Section.
May 28, 2026
V-89
TRUCKEE MUNICIPAL CODE - TITLE 18, DEVELOPMENT CODE
18.110
Surveys and Monuments
A. Boundary monuments.
Boundary monuments shall be set on the exterior boundary of the subdivision at all corners, angle points, beginnings and ends of curves and at intermediate points approximately 1,000 feet apart. The locations of inaccessible points may be established by ties and shall be so noted on the Final Map or Parcel Map.
All exterior boundary monuments shall be set prior to recordation of the Final Map or Parcel Map or as certified on the Final Map.
B. Interior monuments. Whenever interior monuments are required, the monuments shall be set at:
All block and lot corners and angle points;
The beginnings and ends of curves;
Points of intersection with centerlines of other existing and proposed streets and alleys; and
The points of intersection with the exterior boundary lines.
Interior property line and centerline monuments and ties may be set after the Final Map or Parcel Map is recorded.
C. Monument type and positioning. All monuments set in the course of the survey shall be as specified by the Town Engineer and shall be set to the depth and in the manner prescribed by the Town Engineer.
D. Identification marks. All monuments shall be permanently and visibly marked or tagged with the registration or license number of the engineer or surveyor who signs the engineer's or surveyor's certificate and under whose supervision the survey is made.
E. Replacement of destroyed monuments. Any monument which is disturbed or destroyed before acceptance of all improvements by the Town shall be replaced by the subdivider.
F. Timing of monument installation . The exterior boundary of the subdivision shall be completely monumented or referenced before the Final Map or Parcel Map is submitted to the Town Engineer for filing. Interior monuments need not be set at the time the Final Map or Parcel Map is filed if the engineer or surveyor certifies on the map that the monuments will be set on or before a specified later date, and if the subdivider furnishes the Town a bond, instrument of credit, or cash deposit in a sufficient amount to guarantee payment of the cost of setting the monuments in compliance with Map Act Section 66496.
numents need not be set at the time the Final Map or Parcel Map is filed if the engineer or surveyor certifies on the map that the monuments will be set on or before a specified later date, and if the subdivider furnishes the Town a bond, instrument of credit, or cash deposit in a sufficient amount to guarantee payment of the cost of setting the monuments in compliance with Map Act Section 66496.
- G. Notice of completion. Within five days after all monuments have been set, the engineer or surveyor shall give written notice to the subdivider and the Town Engineer that the final monuments have been set. Verification of payment to the engineer or surveyor shall be filed as required by Article 9, Chapter 4 of the Map Act. The cost of setting monuments shall be included in the engineer's estimate for improvements in compliance with Section 18.108.040
May 28, 2026
V-90
TRUCKEE MUNICIPAL CODE - TITLE 18, DEVELOPMENT CODE
18.110
Surveys and Monuments
(Subdivision Improvement Agreements and Security). If requested, this amount of the bond may be released upon verification of the setting of the monuments by the Town Engineer.
18.110.040 - Survey Information on Parcel or Final Map¶
The following survey information shall be shown on each Final Map or Parcel Map for which a field survey was made in compliance with this Development Code.
A. Stakes, monuments (together with their precise position) or other evidence found on the ground, to determine the boundaries of the subdivision;
B. Corners of all adjoining properties identified by lot and block numbers, subdivision names, numbers and pages of record, or by section, township and range, or other proper designation;
C. All information and data necessary to locate and retrace any point or line without unreasonable difficulty;
D. The location and description of any required monuments to be set after recordation of the Final Map, and the statement that they are "to be set;"
E. Bearing and length of each lot line, block line and boundary line and each required bearing and distance;
F. Length, radius and angle of each curve and the bearing of each radial line to each lot corner on each curve;
G. The centerlines of any street or alley in or adjoining the subdivision which have been established by the Town Engineer, together with reference to a field book or map showing the centerline and the monuments which determine its position. If determined by ties, that fact shall be so stated;
H. Any other survey data or information as may be required to be shown by the Town Engineer or by the provisions of this Chapter.
May 28, 2026
V-91
TRUCKEE MUNICIPAL CODE - TITLE 18, DEVELOPMENT CODE
18.110
Surveys and Monuments
May 28, 2026
V-92
TRUCKEE MUNICIPAL CODE - TITLE 18, DEVELOPMENT CODE
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — Truckee Zoning Code
- Title 18 — Development Code
▸Title 18 — DEVELOPMENT CODE
Overview- Article I — Development Code Enactment and Applicability
- Article II — Zoning Districts and Allowable Land Uses
- Article III — Site Planning and General Development Standards
- Article IV — Land Use and Development Permit Procedures
- Article V — Subdivisions
- Article VI — Development Code Administration
- Article VII — Housing
- Article VIII — Development Code Definitions
- Article I
- Article II
- Article III
- Article IV
▸Article V
Overview- Chapter 18.90 — Subdivision Map Approval Requirements
- Chapter 18.92 — Subdivision Design and Improvements
- Chapter 18.94 — Residential Subdivision Design Guidelines
- Chapter 18.95 — Urban Lot Split and Two-Unit Projects (Senate …
▸Chapter 18.96 — TENTATIVE MAP FILING AND PROCESSING
Overview- Chapter 18.98 — Parcel Maps and Final Maps
- Chapter 18.100 — Common Interest Developments and Common Inter…
- Chapter 18.102 — Certificates of Compliance
- Chapter 18.104 — Reversions to Acreage
- Chapter 18.106 — Dedications, Exactions, Reservations, Easements
- Chapter 18.108 — Subdivision Improvement Plans and Agreements
- Chapter 18.110 — Surveys and Monuments
- Article VI
- Article VII
- Article VIII