Earlier editions: 2026-09
Title 19 — SHASTA COUNTY CARR FIRE, ZOGG FIRE, SALT FIRE, AND FAWN FIRE DISASTER RECOVERY
Shasta County Municipal Code Ch. 19.06 Extensions of Specified Land Use Approvals
Shasta County Municipal Code · 2026-10 edition · updated 2026-10-04 · Shasta County
Cite as: Shasta County Municipal Code Chapter 19.06 · Text as of 2026-10-04
19.06.010 - Tentative maps.¶
Notwithstanding any contrary provision of this code, any tentative map for parcels in the Carr Fire that was approved on or after July 23, 2016, and has not already been granted an extension of time is hereby extended by one year beyond its current expiration date.
Notwithstanding any contrary provision of this code, any tentative map for parcels in the Zogg Fire that was approved on or after September 27, 2018, and has not already been granted an extension of time is hereby extended by one year beyond its current expiration date.
Notwithstanding any contrary provision of this code, any tentative map for parcels in the Salt Fire that was approved on or after June 30, 2019, and has not already been granted an extension of time is hereby extended by one year beyond its current expiration date.
Notwithstanding any contrary provision of this code, any tentative map for parcels in the Fawn Fire that was approved on or after September 22, 2019, and has not already been granted an extension of time is hereby extended by one year beyond its current expiration date.
As used in this chapter, the term "tentative map" refers to tentative maps, tentative parcel maps, and vesting tentative maps.
(Ord. No. 2021-06, § II(Exh. A), 11-16-2021)
19.06.020 - Concurrent land use approvals.¶
Notwithstanding any contrary provisions of this code, for tentative maps extended pursuant to Section 19.06.010 above, any separate discretionary land use approval that was granted in conjunction with the tentative map approval is hereby extended consistent with the extended tentative map.
(Ord. No. 2021-06, § II(Exh. A), 11-16-2021)
19.06.030 - Lot line adjustments.¶
With respect to the Carr Fire only, notwithstanding any contrary provisions of this code, any lot line adjustment approved on or after July 23, 2016 and that has not already been granted an extension of time is hereby extended one year.
With respect to the Zogg Fire only, notwithstanding any contrary provisions of this code, any lot line adjustment approved on or after September 27, 2018 and that has not already been granted an extension of time is hereby extended one year.
With respect to the Salt Fire only, notwithstanding any contrary provisions of this code, any lot line adjustment approved on or after June 30, 2019 and that has not already been granted an extension of time is hereby extended one year.
With respect to the Fawn Fire only, notwithstanding any contrary provisions of this code, any lot line adjustment approved on or after September 22, 2019 and that has not already been granted an extension of time is hereby extended one year.
(Ord. No. 2021-06, § II(Exh. A), 11-16-2021)
19.06.040 - Other approvals.¶
With respect to the Carr Fire only, any use permit, zoning permit, variance or design review approval granted under this code that was approved on or after July 23, 2016 and that has not already been granted an extension of time is hereby extended for one year.
With respect to the Zogg Fire only, any use permit, zoning permit, variance or design review approval granted under this code that was approved on or after September 27, 2018 and that has not already been granted an extension of time is hereby extended for one year.
With respect to the Salt Fire only, any use permit, zoning permit, variance or design review approval granted under this code that was approved on or after June 30, 2019 and that has not already been granted an extension of time is hereby extended for one year.
With respect to the Fawn Fire only, any use permit, zoning permit, variance or design review approval granted under this code that was approved on or after September 22, 2019 and that has not already been granted an extension of time is hereby extended for one year.
(Ord. No. 2021-06, § II(Exh. A), 11-16-2021)