Santa Clara County Municipal Code Part 4 Report Acceptance; Permit Issuance
Santa Clara County Municipal Code · 2026-10 edition · updated 2026-10-04 · Santa Clara County
Cite as: Santa Clara County Municipal Code Part 4 · Text as of 2026-10-04
Sec. C12-317.1. - Generally.¶
The Land Development Coordinator will prepare a consolidated report and mail it to the applicant within 21 calendar days of the filing of the application subject to an extension of time established by mutual consent between the applicant and the Land Development Coordinator or within ten calendar days after receipt by the Land Development Coordinator of the reports by the referral agencies. If the applicant accepts the report and conditions, one copy of the accepted conditions shall be signed and returned together with the building plans for plan review. Once the building plans have been reviewed and approved by the Building Inspector and all other conditions complied with, the Central Permit Office shall issue the building permit.
(Ord. No. NS-1203.35, § 5, 3-13-78)