Skip to content

Chapter 12 — Land Development Reviews›Article 9 — Construction Permits

San Diego Municipal Code Div. 6 Grading Permit Procedures

San Diego Municipal Code · 2026-10 edition · updated 2026-10-18 · San Diego

Cite as: San Diego Municipal Code Division 6 · Text as of 2026-10-18

(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

§129.0601 Purpose of Grading Permit Procedures

The purpose of these procedures is to establish the process for review of Grading Permit applications for compliance with the regulations set forth in Chapter 14, Article 2, Division 1 and to protect persons, property and the environment. (Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Exceptions & meaning →

§129.0602 When a Grading Permit is Required

A Grading Permit is required for the following work:

(a) Any grading within open space easements or City-owned open space;

(b) Any grading required for the restoration of unauthorized grading;

(c) Any grading within the Special Flood Hazard Area;

(d) Any grading in accordance with a Grading Permit required as a condition of a
development permit to assure compliance with the development permit
conditions.

(e) Any grading that includes the following conditions:

(1) Excavation or fill that results in a slope with a gradient of 25 percent
or greater (4 horizontal feet to 1 vertical foot) and for which the depth
or height at any point is more than 5 feet measured vertically at the
face of the slope from the top of the slope to the bottom of the slope;

(2) Excavation or fill for which the depth or height at any point from the
lowest grade to the highest grade at any time during the proposed
grading is more than 5 feet measured vertically;

(3) Grading that creates manufactured slopes at a gradient exceeding that
specified in Section 142.0133;

(4) Grading for which the graded area is more than 1 acre;

Ch. Art. Div.
12 9 6 1

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2019)

(5) Grading that adversely affects the existing drainage pattern by altering
the drainage pattern, concentrating runoff, increasing the quantity of
runoff, or increasing the velocity of runoff to adjacent properties;

(6) Placing fill material that contains more than 5 percent, by volume, of
broken concrete, asphalt, masonry, or construction debris;

(7) Placing fill material that has any piece larger than 12 inches in any
direction; or

(8) Grading that includes blasting or other use of explosives.

(f) Any grading work on a property that contains a historical resource as
described in Section 143.0210.
(Amended 4-22-2002 by O-19051 N.S.; effective 10-8-2002.)

Exceptions & meaning →

§129.0603 Exemptions from Requirement for a Grading Permit

A Grading Permit is not required for the work listed below unless section 129.0602 requires otherwise.

(a) Excavation below finished grade for the basement or footing of a building, for
a retaining wall, or for any other structure authorized by a valid Building
Permit provided that the excavated material is disposed of at a legal disposal
site in a safe and sanitary manner. This paragraph shall not exempt any fill
made with material from the excavation that exceeds thresholds established in
Section 129.0602.

(b) The deposit of material in any disposal area operated or licensed by the City
where the operation and conduct thereof does not block or divert any natural
drainage way, affect the lateral support of, or unduly increase the stresses in
or pressures upon any adjacent or contiguous property.

(c) Gravel pits, mines, quarries, or the processing and stockpiling of soil, rock
and gravel, aggregate, or clay where these operations are conducted in
accordance with an approved Conditional Use Permit, and where the
operation does not block or divert any natural drainage way, affect the lateral
support of, or unduly increase the stresses in or pressures upon any adjacent or
contiguous property. This paragraph shall not exempt grading work required
by an approved restoration plan.

Ch. Art. Div. 12 9 6 2

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2019)

(d) Any operation in which grading is routinely conducted as an integral process
to the operation in accordance with an approved Conditional Use Permit,
where the operation does not block or divert any natural drainage way, affect
the lateral support of, or unduly increase the stresses in or pressures upon any
adjacent or contiguous property.

(e) Excavation or fill performed by a governmental agency or public utility, or the
contractor of either, in connection with the construction of roadways,
pipelines, or utility lines within their rights-of-way.

(f) Subsurface exploration activity which shall be restored to the pre-existing
grade.

(g) Agricultural grading in the agricultural zones.

(h) Excavation for individual cemetery graves, provided that the operation of the
cemetery is conducted in accordance with an approved conditional use permit.

(i) Drilling of wells.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Exceptions & meaning →

§129.0610 How to Apply for a Grading Permit

An application for a Grading Permit shall be submitted in accordance with Sections 112.0102 and 129.0105. The submittal requirements for Grading Permits including geotechnical reports are listed in the Land Development Manual. (Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Exceptions & meaning →

§129.0620 Qualifications to Prepare Plans and Perform Construction Work for Grading

The preparation of plans for, and the construction of, grading work regulated by this division shall be performed only by persons with the following qualifications:

(a) Grading plans required by this division shall be prepared by professionals as
licensed and allowed by the California Business and Professions Code;

(b) Geotechnical reports required for work authorized under this division shall be
prepared by professionals as licensed and allowed by the California Business
and Professions Code and as specified in Land Development Manual;

(c) Drainage reports required for work authorized under this division shall be
prepared by a civil engineer;

Ch. Art. Div.
12 9 6 3

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2019)

(d) Landscaping plans for revegetation or planting in public rights-of-way
required for work authorized under this division shall be prepared by a
landscape architect or other professional as licensed and authorized by the
California Business and Professions Code; and

(e) All grading and construction work required by this division shall be
performed by a contractor licensed by the State of California except that any
person owning property that is or will be that person’s primary residence may
perform grading on that property and any grading authorized by a Grading
Permit as a result of application by a public utility may be performed by the
public utility.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Exceptions & meaning →

§129.0630 Decision Process for Grading Permits

(a) A decision on an application for a Grading Permit shall be made in accordance with Process One.

(b) A Grading Permit shall be approved if the proposed work is consistent with
the Municipal Code, applicable development standards, any development
permits approved for that project, the terms of the California Regional Water
Quality Control Board, San Diego Region, Order No. 2001-01 dated February
21, 2000, any subsequent amendments, relating to the reduction of pollutant
discharges, and any other requirements imposed by the City Manager for the
purpose of ensuring that pollutant discharges are reduced to the maximum
extent practicable and water quality objectives are not violated.
(Amended 9-10-2001 by O-18976 N.S.; effective 10-10-2001 outside the Coastal
Overlay Zone; effective 11-16-2001 within the Coastal Overlay Zone.)

Exceptions & meaning →

§129.0641 Issuance of a Grading Permit

(a) An approved Grading Permit shall be issued after the prescribed fees have been paid, the required insurance has been guaranteed, and the prescribed bond has been posted.

(b) The applicant shall not begin any work, construction, or use on the property
that will be authorized by a Grading Permit until the required permit has been
issued.

(c) A Grading Permit shall not be issued for a development that requires a
development permit until the development permit has been issued.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Ch. Art. Div. 12 9 6 4

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2019)

Exceptions & meaning →

§129.0650 Expiration of a Grading Permit

(a) A Grading Permit shall expire by limitation and become void upon the later of:

(1) Twenty-four months after the Grading Permit issuance date;

(2) The expiration date of a subdivision improvement agreement
associated with the Grading Permit;

(3) The expiration date of a Building Permit associated with the Grading
Permit; or

(4) The expiration date approved by the City Manager at the time of
permit issuance and specified on the Grading Permit, where the
complexity or size of the project makes completion of the project
within 24 months unreasonable.

(b) If the grading or work authorized by a Grading Permit has not received final
inspection approval by the Grading Permit expiration date, all work shall stop
until a new Grading Permit is issued.

(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)
(Amended 8-4-2011 by O-20081 N.S.; effective 10-6-2011.)
(Amended 3-22-2018 by O-20917 N.S.; effective 4-21-2018.)

Exceptions & meaning →

§129.0651 Extension of Time for a Grading Permit

(a) A permittee may submit an application for an extension of time to the City before, but no earlier than 60 calendar days before, the expiration date of the Grading Permit. The City Manager may extend the Grading Permit for a period not exceeding 180 calendar days if the City Manager determines that circumstances beyond the control of the permittee prevented completion of the work. A Grading Permit shall not be extended more than once except as provided in Section 129.0651(d).

Ch. Art. Div.
12 9 6 5

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2019)

(b) If an application for an extension of time has been submitted before the
expiration date of the Grading Permit and in accordance with this section, the
existing permit shall automatically be extended until the City Manager has
made a decision on the application for an extension.

(c) If the Grading Permit has expired before an application is submitted for an
extension of time, an extension shall not be granted. To proceed with the
same development, a new application shall be required and the application is
treated as a new application.

(d) If an extension of time has been previously approved in accordance with
Section 129.0651(a), the City Manager may extend the expiration of the
Grading Permit one additional time if the City Manager finds the following:

(1) There has not been a significant change in the regulations applicable to
the site since the date of permit issuance;

(2) The additional extension is in the public interest; and

(3) Circumstances beyond the control of the applicant prevented the
authorized work from proceeding.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Exceptions & meaning →

§129.0652 Construction Change to a Grading Permit

(a) Proposed construction change to a Grading Permit must be approved before commencement of the construction change. A decision on a construction change shall be made in accordance with Section 129.0630.

(b) A proposed construction change to a Grading Permit that was approved in
conjunction with another permit or map may be approved if the proposed
change is in substantial conformance with the other approved permit or map.
If the proposed change is not in substantial conformance with the other
approved permit or map, the other permit or map must be amended before
consideration of the construction change.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Ch. Art. Div. 12 9 6 6

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2019)

Exceptions & meaning →

§129.0660 Inspection of Grading

All grading operations authorized by a Grading Permit shall be inspected by the City Engineer or the Building Official pursuant to Section 129.0104(a)(14). Professional inspection of grading operations shall be provided by the Engineer of Record as designated by the permit holder. (Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.) (Amended 7-31-2012 by O-20187 N.S.; effective 8-30-2012.)

Exceptions & meaning →

§129.0661 Designation of Engineer of Record

(a) The permittee shall retain and designate an Engineer of Record for each area of technical expertise needed to provide professional inspection services as required by the City Engineer and described in the Land Development Manual.

(b) If an Engineer of Record is changed during grading, the work shall be stopped
until the replacement Engineer has agreed in writing to accept responsibility
within the area of technical competence for approval upon completion of the
work. The permittee is responsible for notifying the City Engineer in writing
of any change before grading resumes.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)

Exceptions & meaning →

§129.0670 Completion of Grading

The permit holder shall notify the City Engineer, or the Building Official pursuant to Section 129.0104(a)(15), when the grading operation is ready for final inspection. Final approval shall not be given until all work, including installation of all drainage facilities and their protection devices, and all erosion control measures have been completed in accordance with the final approved grading plan and the As-Graded Reports have been submitted and approved by the City Engineer, or the Building Official pursuant to Section 129.0104(a)(15), in accordance with standards established by the City Engineer or Building Official. If the grading is for creating building pads, a Building Permit shall not be issued until the grading is completed by the permit holder and approved by the City. (Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.) (Amended 7-31-2012 by O-20187 N.S.; effective 8-30-2012.)

Ch. Art. Div.
12 9 6 7

San Diego Municipal Code Chapter 12: Land Development Reviews (2-2025)

Article 9: Construction Permits

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — San Diego Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.