16.48.010 - Purpose.

The purpose of this chapter is to provide for the payment of a development fee to be utilized for the development, which includes but is not limited to any and all environmental studies, analysis, reports and documents, and construction of a bridge crossing the Alessandro Arroyo at Overlook Parkway.

(Ord. 7074 §1, 2010; Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.020 - Definitions.

As used in this chapter the following terms shall have the following meanings:

Building permit for new development means a building permit issued pursuant to Chapter 16.08 of the Riverside Municipal Code for a structure or a portion of a structure which is not a replacement for a structure or a portion of a structure which existed on the same site on January 1, 1991.

Alessandro Heights area refers to the area of the City of Riverside generally located adjacent to the Alessandro Arroyo and as described by resolution of the City Council.

(Ord. 7748, § 52, 2025; Ord. 6393 §48, 1997; Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.030 - Establishment of fee.

A development fee for the construction of a bridge crossing the Alessandro Arroyo at Overlook Parkway is hereby established for and assessed against all new development in the Alessandro Heights area in the amount established by the City Council by resolution.

(Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.040 - Payment of fee.

The required development fee for the bridge crossing the Alessandro Arroyo at Overlook Parkway shall be paid prior to the issuance of a building permit for new development permit. No building permit for new development in the Alessandro Heights area shall be issued until such fee has been paid.

(Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.050 - Use of fee.

When the development fee for the bridge crossing the Alessandro Arroyo at Overlook Parkway has been collected, it shall be deposited in a separate capital facilities account or fund in a manner to avoid any commingling of the fees with other revenues and funds of the City, except to temporary investments. The fees may be expended solely for the purpose for which the fee was collected. An interest income earned by moneys in the capital facilities account or fund shall also

be deposited in that account or fund and shall be expended only for the purpose for which the fee was originally collected.

(Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.060 - Exemptions.

The following types of development shall not be required to pay the development fee for the bridge crossing the Alessandro Arroyo at Overlook Parkway:

A. Nonresidential development which replaces on the same lot previously existing residential or nonresidential development, not to exceed the size of the replaced development, within one year from the date of destruction or relocation of the previously existing development.

B. Residential development which replaces on the same lot previously existing nonresidential development, not to exceed the size of the replaced development, within one year from the date of destruction or relocation of the previously existing development.

C. Residential development which replaces on the same lot previously existing residential development, unit for unit, within one year from the date of destruction or relocation of the previously existing residential development.

D. Rehabilitation or remodeling of existing nonresidential development which does not add new square footage.

E. Rehabilitation or remodeling of or additions to existing residential development which does not add new dwelling units.

F. Development by local, State or federal governments for governmental use.

(Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.070 - Appeals.

Any person aggrieved by the application of fee pursuant to this chapter shall have the right to appeal to the Planning Commission. The appeal shall be taken not later than 30 days from the date the person is informed of the fee. Failure to appeal within the 30-day period shall be deemed a waiver of all rights of appeal under this chapter. The decision of the Planning Commission shall be transmitted to the City Council for ratification, modification or denial.

(Ord. 6462 §18, 1999; Ord. 5903 §1, 1991)

Exceptions & meaning →

16.48.080 - Annual report.

Within 60 days of the close of each fiscal year, the Public Works Director and the Chief Financial Officer/Treasurer shall make a report to the City Council which shall include the beginning and ending balance for the fiscal year, the fee, interest and other income, the amount of expenditure and the amount of any refunds made during the fiscal year. This report shall be made available to the public and shall be reviewed by the City Council at its next regularly scheduled public meeting not less than 15 days after the report is released.

(Ord. 7362 §8, 2017; Ord. 5903 §1, 1991)

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Riverside Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.