22.70.010 - Purpose of Chapter. ¶
This Chapter provides procedures for the implementation or vesting of the permits and entitlements required by this Development Code, including time limits and procedures for extensions of time. Time limits and extension criteria for Tentative Maps are found in Article VI (Subdivisions), beginning with Section 22.84.120 (Tentative Map Time Limits).
(Ord. No. 3577, 2012)
22.70.020 - Effective Date of Permits. ¶
A.
Final determinations adopted by resolution by the Director, Zoning Administrator, or Commission (e.g., Design Reviews, Floating Home Exceptions, Use Permits, Variances), shall become effective on the 9[th] business day following the date of application approval by the appropriate Review Authority, provided that no appeal of the Review Authority's action has been submitted, in compliance with Chapter 22.114 (Appeals).
B.
Final determinations adopted by resolution by the Board shall become effective immediately.
C.
Final determinations adopted by ordinance by the Board (e.g., Master Plans, Development Code, Zoning Map and Countywide Plan amendments), shall become effective on the 31st day following the date of approval by the Board.
(Ord. No. 3577, 2012; Ord. No. 3706, 2019)
22.70.030 - Deadline for Action. ¶
The Director, Zoning Administrator or Commission shall make an initial decision on a quasi-judicial discretionary permit within 60 days after the application is determined to be complete, or the appropriate time period in compliance with the CEQA time limit requirements, or the appropriate time limit otherwise established by any State or Federal Law, or the application shall be deemed approved, subject to the noticing requirements of Government Code Section 65956. A one-time extension for a period not to exceed an additional 90 days may be provided upon mutual agreement by the Director and the applicant (Government Code Section 65957).
Any permit application deemed approved in compliance with State law (Government Code Section 65956) shall be subject to all applicable provisions of this Development Code, which shall be satisfied by the applicant prior to the issuance of any construction permit or the establishment of a land use not requiring a construction permit.
Deadlines for action and results of inaction are modified for telecommunications projects by Federal law and in accordance with section 22.32.165 (Telecommunications Facilities).
(Ord. No. 3577, 2012; Ord. No. 3666, § II(exh. A), 2017; Ord. No. 3706, 2019)
22.70.040 - Performance Guarantees. ¶
A permit applicant may be required by conditions of approval, or by action of the review authority, to provide adequate security, in a form acceptable to the Director, to guarantee and/or monitor the faithful performance of and compliance with any/all conditions of approval imposed by the review authority on the permit.
(Ord. No. 3577, 2012)
22.70.050 - Time Limits and Extensions.
A.
Time limits, vesting. Unless conditions of approval establish a different time limit, any permit or entitlement not vested within three years of the date of approval shall expire and become void. The permit shall not be deemed vested until the permit holder has actually obtained a Building Permit or other construction permit and has substantially completed improvements in accordance with the approved permits, or has actually commenced the allowed use on the subject property, in compliance with the conditions of approval, or has recorded a Parcel or Final Map.
B.
Extensions of time. Upon request by the applicant, the Director may extend the time for an approved permit to be vested.
1.
Filing. The applicant shall file a written request for an extension of time with the Agency, at least ten days prior to the expiration of the permit, together with the filing fee required by the County Fee Ordinance.
2.
Review of extension request. The Director shall determine whether the permit holder has attempted to comply with the conditions of the permit. The burden of proof is on the permittee to establish, with substantial evidence, that the permit should not expire. The Director may instead refer the extension request to the Commission for review.
3.
Action on extension.
a.
If the Director determines that the permittee has proceeded in good faith and has exercised due diligence in complying with the conditions in a timely manner, the Director may extend the permit for a maximum period of three years following the original expiration date. If the approval was granted concurrently with a Tentative Map, the maximum amount of time extensions would be determined by Section 22.84.140 (Extensions of Time for Tentative Maps).
b.
When granting an extension, the Director may make minor modifications to the approved project if it is found that there has been a change in the factual circumstances surrounding the original approval.
4.
Hearing on extension. If the Director finds that significant policy questions are at issue, the Director may refer the application to the Commission for a public hearing in compliance with Chapter 22.118 (Notices, Public Hearings, and Administrative Actions).
5.
Coordination of expiration date among multiple permits. If a Building Permit, or other permit, is issued during the effective life of the entitlement or development application approval, the expiration date of the entitlement or development application approval shall be automatically extended to coincide with the expiration date of the Building Permit or permit.
(Ord. No. 3577, 2012)
22.70.060 - Changes to an Approved Project. ¶
Development or a new land use authorized in compliance with this Development Code shall be established only as approved by the review authority and subject to any conditions of approval, except where changes to the project are approved in compliance with this Section.
An applicant shall propose changes in writing, and shall also furnish appropriate supporting materials and an explanation of the reasons for the request. Changes may be requested either prior to or after construction or establishment and operation of the approved use.
A.
The Director may authorize changes to an approved site plan, architecture, or the nature of the approved use if the changes:
1.
Are consistent with all applicable provisions of this Development Code;
2.
Do not involve a feature of the project that was specifically addressed or was a basis for findings in a negative declaration or environmental impact report for the project;
3.
Do not involve a feature of the project that was specifically addressed or was a basis for conditions of approval for the project or that was a specific consideration by the Review Authority in the approval of the permit; and
4.
Do not result in a significant expansion of the use.
B.
Changes to the project involving features described in Subsections 22.70.060.A.2 and A.3 (Changes to an Approved Project), above, shall only be approved by the review authority through a new permit application processed in compliance with this Development Code.
(Ord. No. 3577, 2012)
ARTICLE V - COASTAL ZONES—DEVELOPMENT AND RESOURCE MANAGEMENT STANDARDS
IMPORTANT NOTE TO READER:
Article V was approved by the Marin County Board of Supervisors on June 24, 2003 and later updated on June 13, 2006, as part of this Development Code. However, the provisions of this Development Code shall not be used as the standard of review for property or development proposals located within the coastal zone until approved by the California Coastal Commission, except for those Development Code sections listed below: