1811.1 General.¶
The requirements of this section address the use of vertical rock and soil anchors in resisting seismic or wind overturning forces, resulting in tension on shallow foun- dations.
1811.2 Adoption.¶
Except for the modifications as set forth in Sections 1811.3 and 1811.4, all prestressed rock and soil foundation anchors shall comply with PTI Recommendations for Prestressed Rock and Soil Anchors.
1811.3 Geotechnical requirements¶
. The geotechnical report for the Prestressed Rock & Soil Foundation Anchors shall address the following:
1. Minimum diameter and minimum spacing for the anchors including consideration of group effects.
2. Maximum unbonded length and minimum bonded length of the tendon.
3. Maximum recommended anchor tension capacity based upon the soil or rock strength/grout bond and anchor depth/spacing.
4. Allowable bond stress at the ground/grout interface and applicable factor of safety for ultimate bond stress.
5. Anchor axial tension stiffness recommendations at the anticipated anchor axial tension displacements, when required for structural analysis.
6. Minimum grout pressure for installation and post-grout pressure.
7. Class I Corrosion Protection is required for all perma- nent anchors. A minimum of Class II Corrosion Protec- tion is required for temporary anchors in service less than or equal to 2 years.
8. Performance test shall be at a minimum of 1.6 times the design loads, but shall not exceed 80 percent of the specified minimum tensile strength of the tendons. There shall be a minimum of two preproduction test anchors. Preproduction test anchors shall be tested to ultimate load or a maximum of 0.80 times the specified minimum tensile strength of the tendon. A creep test is required for all prestressed anchors with greater than 10 kips of lock-off prestressing load.
9. Lock-off prestressing load requirements.
10. Acceptable drilling methods.
11. Geotechnical observation and monitoring require- ments.
1811.4 Structural Requirements¶
.
1. Tendons shall be thread-bar anchors conforming to ASTM A722.
2. The anchors shall be placed vertical.
3. Design loads shall be based upon the load combina- tions in Section 1605.3.1 and shall not exceed 60 per- cent of the specified minimum tensile strength of the tendons.
4. Ultimate load shall be based upon the lesser of the strength of the superstructure elements, the maximum
forces from a fully yielded structural system and forces from the load combinations with overstrength factor in accordance with ASCE 7, Section 12.4.3 and shall not exceed 80 percent of the specified minimum tensile strength of the tendons.
5. The anchor shall be designed to fail in grout bond to the soil or rock before pullout of the soil wedge by group effect.
6. Foundation design shall incorporate the effect of lock- off loads.
7. Design shall account for as-built locations of soil anchors considering all the acceptable construction tolerances.
8. Design shall account for both short- and long-term deformation.
9. Enforcement agency may require consideration of anchor deformation in evaluating deformation compat- ibility or building drift where it may be significant.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Building Code (Title 24, Part 2)
- Chapter 2 — DEFINITIONS AND ABBREVIATIONS
- Appendix G — FLOOD-RESISTANT
- Appendix L — EARTHQUAKE RECORDING
- Appendix M — TSUNAMI-GENERATED
- Chapter 1 — SCOPE AND ADMINISTRATION
- Chapter 3 — OCCUPANCY CLASSIFICATION AND USE
- Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED
- Chapter 5 — GENERAL BUILDING HEIGHTS AND AREAS
- Chapter 6 — TYPES OF CONSTRUCTION
- Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
- Chapter 7A — MATERIALS AND CONSTRUCTION
- Chapter 8 — INTERIOR FINISHES
- Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
- Chapter 10 — MEANS OF EGRESS
- Chapter 11A — HOUSING ACCESSIBILITY
- Chapter 11B — ACCESSIBILITY TO PUBLIC BUILDINGS, PUBLIC ACCOMM…
- Chapter 12 — INTERIOR ENVIRONMENT
- Chapter 14 — EXTERIOR WALLS
- Chapter 15 — ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
- Chapter 16 — STRUCTURAL DESIGN
- Chapter 16A — STRUCTURAL DESIGN
- Chapter 17 — SPECIAL INSPECTIONS AND TESTS
▸Chapter 18 — SOILS AND FOUNDATIONS
Overview- Section 1801
- Section 1802
- Section 1803
- Section 1804
- Section 1805
- Section 1806
- Section 1807
- Section 1808
- Section 1809
- Section 1810
- Section 1811
- Section 1812
- Section 1813
- Section 1803A
- Section 1801A
- Section 1802A
- Section 1804A
- Section 1805A
- Section 1806A
- Section 1807A
- Section 1808A
- Section 1809A
- Section 1810A
- Section 1811A
- Section 1812A
- Section 1813A
- Chapter 19 — CONCRETE
- Chapter 20 — ALUMINUM
- Chapter 21 — MASONRY
- Chapter 22 — STEEL
- Chapter 23 — WOOD
- Chapter 24 — GLASS AND GLAZING
- Chapter 25 — GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER
- Chapter 26 — PLASTIC
- Chapter 27 — ELECTRICAL
- Chapter 28 — MECHANICAL SYSTEMS
- Chapter 30 — ELEVATORS AND CONVEYING SYSTEMS
- Chapter 31 — SPECIAL CONSTRUCTION
- Chapter 31B — PUBLIC POOLS
- Chapter 31C — RADIATION
- Chapter 31D — FOOD ESTABLISHMENTS
- Chapter 31F — MARINE OIL TERMINALS
- Chapter 32 — ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
- Chapter 33 — SAFEGUARDS DURING CONSTRUCTION
- Chapter 35 — REFERENCED STANDARDS
- Appendix A — EMPLOYEE QUALIFICATIONS
- Appendix B — BOARD OF APPEALS
- Appendix C — GROUP U – AGRICULTURAL BUILDINGS
- Appendix D — FIRE DISTRICTS
- Appendix F — RODENTPROOFING
- Appendix H — SIGNS
- Appendix I — PATIO COVERS
- Appendix J — GRADING
- Appendix K — GROUP R-3 AND GROUP R-3.1 OCCUPANCIES
- Appendix N — REPLICABLE BUILDINGS
- Appendix O — EMERGENCY HOUSING