INSPECTIONS

[A] 110.1 General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain visible and able to be accessed for inspection purposes until approved. Approval as a result of an inspection shall not be construed to be an approval of a violation of the provisions of this code or of other ordinances of the jurisdiction. Inspections presuming to give authority to violate or cancel the provisions of this code or of other ordinances of the jurisdiction shall not be valid. It shall be the duty of the owner or the owner’s authorized agent to cause the work to remain visible and able to be accessed for inspection purposes. Neither the building official nor the jurisdiction shall be liable for expense entailed in the removal or replacement of any material required to allow inspection.

[A] 110.2 Preliminary inspection. Before issuing a permit, the building official is authorized to examine or cause to be examined buildings, structures and sites for which an application has been filed.

32 2019 CALIFORNIA BUILDING CODE

Copyright © 2019 ICC. ALL RIGHTS RESERVED. Accessed by Kevin Day (kevin.day@dgs.ca.gov), (California Building Standards Commission) Order Number #100735044 on Jul 24, 2019 03:54 PM (PDT) pursuant to License Agreement with ICC. No further reproduction or distribution authorized. Single user only, copying and networking prohibited. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.

100735044

[A] 110.3 Required inspections. The building official, upon notification, shall make the inspections set forth in Sections 110.3.1 through 110.3.11.

[A] 110.3.1 Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. For concrete foundations, any required forms shall be in place prior to inspection. Materials for the foundation shall be on the job, except where concrete is ready mixed in accordance with ASTM C94, the concrete need not be on the job.

[A] 110.3.2 Concrete slab and under-floor inspection. Concrete slab and under-floor inspections shall be made after in-slab or under-floor reinforcing steel and building service equipment, conduit, piping accessories and other ancillary equipment items are in place, but before any concrete is placed or floor sheathing installed, including the subfloor.

[A] 110.3.3 Lowest floor elevation. In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required in Section 1612.4 shall be submitted to the building official.

[A] 110.3.4 Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fireblocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved.

110.3.4.1 [HCD 1] Moisture content verification. Moisture content of framing members shall be verified in accordance with the California Green Building Stan- dards Code (CALGreen), Chapter 4, Division 4.5.

[A] 110.3.5 Lath, gypsum board and gypsum panel product inspection. Lath, gypsum board and gypsum panel product inspections shall be made after lathing, gypsum board and gypsum panel products, interior and exterior, are in place, but before any plastering is applied or gypsum board and gypsum panel product joints and fasteners are taped and finished.

Exception: Gypsum board and gypsum panel products that are not part of a fire-resistance-rated assembly or a shear assembly.

[A] 110.3.6 Weather-exposed balcony and walking sur- face waterproofing. Where balconies or other elevated walking surfaces are exposed to water from direct or blowing rain, snow or irrigation, and the structural framing is protected by an impervious moisture barrier, all elements of the impervious moisture barrier system shall not be concealed until inspected and approved.

Exception: Where special inspections are provided in accordance with Section 1705.1.1, Item 3.

[A] 110.3.7 Fire- and smoke-resistant penetrations. Protection of joints and penetrations in fire-resistancerated assemblies, smoke barriers and smoke partitions shall not be concealed from view until inspected and approved.

SCOPE AND ADMINISTRATION

[A] 110.3.8 Energy efficiency inspections. Inspections shall be made to determine compliance with Chapter 13 and shall include, but not be limited to, inspections for: envelope insulation R- and U- values, fenestration U- value, duct system R -value, and HVAC and water-heating equipment efficiency.

[A] 110.3.9 Other inspections. In addition to the inspections specified in Sections 110.3.1 through 110.3.8, the building official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this code and other laws that are enforced by the department of building safety.

[A] 110.3.10 Special inspections. For special inspections, see Chapter 17.

[A] 110.3.11 Final inspection. The final inspection shall be made after all work required by the building permit is completed.

[A] 110.3.11.1 Flood hazard documentation . If located in a flood hazard area, documentation of the elevation of the lowest floor as required in Section 1612.4 shall be submitted to the building official prior to the final inspection.

110.3.11.2 [HCD 1] Operation and maintenance man- ual. At the time of final inspection, a manual, compact disc, web-based reference or other media acceptable to the enforcing agency shall be placed in the building in accordance with the California Green Building Stan- dards Code (CALGreen), Chapter 4, Division 4.4.

[A] 110.4 Inspection agencies. The building official is authorized to accept reports of approved inspection agencies, provided that such agencies satisfy the requirements as to qualifications and reliability.

[A] 110.5 Inspection requests. It shall be the duty of the holder of the building permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspections of such work that are required by this code.

[A] 110.6 Approval required. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official. The building official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with this code. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the building official.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — California Building Code (Title 24, Part 2)
California Building Code (Title 24, Part 2)
  1. Chapter 2 — DEFINITIONS AND ABBREVIATIONS
  2. Appendix G — FLOOD-RESISTANT
  3. Appendix L — EARTHQUAKE RECORDING
  4. Appendix M — TSUNAMI-GENERATED
  5. Chapter 1 — SCOPE AND ADMINISTRATION
  6. Chapter 3 — OCCUPANCY CLASSIFICATION AND USE
  7. Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED
  8. Chapter 5 — GENERAL BUILDING HEIGHTS AND AREAS
  9. Chapter 6 — TYPES OF CONSTRUCTION
  10. Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
  11. Chapter 7A — MATERIALS AND CONSTRUCTION
  12. Chapter 8 — INTERIOR FINISHES
  13. Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
  14. Chapter 10 — MEANS OF EGRESS
  15. Chapter 11A — HOUSING ACCESSIBILITY
  16. Chapter 11B — ACCESSIBILITY TO PUBLIC BUILDINGS, PUBLIC ACCOMM…
  17. Chapter 12 — INTERIOR ENVIRONMENT
  18. Chapter 14 — EXTERIOR WALLS
  19. Chapter 15 — ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
  20. Chapter 16 — STRUCTURAL DESIGN
  21. Chapter 16A — STRUCTURAL DESIGN
  22. Chapter 17 — SPECIAL INSPECTIONS AND TESTS
  23. Chapter 18 — SOILS AND FOUNDATIONS
  24. Chapter 19 — CONCRETE
  25. Chapter 20 — ALUMINUM
  26. Chapter 21 — MASONRY
  27. Chapter 22 — STEEL
  28. Chapter 23 — WOOD
  29. Chapter 24 — GLASS AND GLAZING
  30. Chapter 25 — GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER
  31. Chapter 26 — PLASTIC
  32. Chapter 27 — ELECTRICAL
  33. Chapter 28 — MECHANICAL SYSTEMS
  34. Chapter 30 — ELEVATORS AND CONVEYING SYSTEMS
  35. Chapter 31 — SPECIAL CONSTRUCTION
  36. Chapter 31B — PUBLIC POOLS
  37. Chapter 31C — RADIATION
  38. Chapter 31D — FOOD ESTABLISHMENTS
  39. Chapter 31F — MARINE OIL TERMINALS
  40. Chapter 32 — ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
  41. Chapter 33 — SAFEGUARDS DURING CONSTRUCTION
  42. Chapter 35 — REFERENCED STANDARDS
  43. Appendix A — EMPLOYEE QUALIFICATIONS
  44. Appendix B — BOARD OF APPEALS
  45. Appendix C — GROUP U – AGRICULTURAL BUILDINGS
  46. Appendix D — FIRE DISTRICTS
  47. Appendix F — RODENTPROOFING
  48. Appendix H — SIGNS
  49. Appendix I — PATIO COVERS
  50. Appendix J — GRADING
  51. Appendix K — GROUP R-3 AND GROUP R-3.1 OCCUPANCIES
  52. Appendix N — REPLICABLE BUILDINGS
  53. Appendix O — EMERGENCY HOUSING

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.