1909A.1 General.

1909A.1 General. The text of ACI 318 shall be modified as indicated in Sections 1909A.1.1 through 1909A.1.16. 1909A.1.1 ACI 318, Section 4.12.2.2. Modify ACI 318, Section 4.12.2.2 by adding the following: Where prestressed concrete elements are restrained from movement, an analysis of the stresses in the prestressed elements and loads in the adjoining structural system induced by the above-described effects shall be made in accordance with PCI Design Handbook. 1909A.1.2 ACI 318, Section 4.12.2.3. Modify ACI 318, Section 4.12.2.3 by adding the following: For prestressed concrete members with…