Chapter 6 — SEISMIC EVALUATION PROCEDURES FOR HOSPITAL BUILDINGS
Article 10
California Administrative Code (Title 24, Part 1) · 2019 edition · updated 2026-09-10 · California
EVALUATION OF ELEMENTS THAT ARE NOT PART
OF THE LATERAL-FORCE-RESISTING SYSTEM
10.0 Introduction.¶
This article sets forth general requirements that apply to nonstructural elements related to lifesafety issues. Article 11 addresses evaluation of critical nonstructural systems needed for continued hospital function following an earthquake, and assignment of buildings to Nonstructural Performance Categories.
The evaluation statements discussed in this article (and listed in the appendix) deal with life-safety concerns. Some of the statements can be answered directly. For others, further investigation will be required in accordance with evaluation procedures indicated in other articles of these regulations using seismic forces indicated in Section 2.4.6 and the appropriate Cc seismic coefficient given in Table 2.4.3.1. Also, the
SEISMIC EVALUATION PROCEDURES FOR HOSPITAL BUILDINGS
materials used in the nonstructural element and its connections must be considered.
10.1 Nonstructural walls. The term “nonstructural walls”¶
refers to walls that are not part of the load-carrying system, but may become load bearing upon attachment and interaction with other elements. Evaluation must be made to determine if they are capable of resisting seismic forces required by Section 2.4.6 as well as the other requirements of these regulations.
10.1.1 Partitions.
10.1.1.1 Masonry partitions. There are no unbraced unreinforced masonry or hollow clay tile partitions in critical care areas, clinical laboratory service spaces, pharmaceutical service spaces, radiological service spaces, central and sterile supply areas, exit corridors, elevator shafts or stairwells.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Check for the presence of support angles at floor and roof, and for spaces at the sides and top of the wall to provide for interaction of the structural system.
10.1.1.2 Structural separations. At structural separations, partitions in exit corridors have seismic or control joints.
Check that seismic and/or control joints have been provided at structural separations. Conforming buildings that fail this check shall be placed in SPC 4.
10.1.1.3 Partition bracing. In exit corridors, the tops of partitions that extend only to the ceiling line have lateral bracing.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Partitions extending only to ceilings may overturn or buckle due to the lack of bracing.
10.1.2 Cladding and veneer. For conforming buildings, the evaluator may consider these conditions as mitigated, and no calculations are necessary. Exterior wall panels or cladding can fall if their connections to the building frames have insufficient strength and/or ductility.
10.1.2.1 Masonry veneer. Masonry veneer is connected to the back-up with corrosion-resistant ties spaced 24 inches on center maximum with at least one tie for every 2 2 /3 square feet.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Check for the presence of the required ties.
10.1.2.2 Cladding panels in moment frame buildings. For moment frame buildings of steel or concrete, panels are isolated from the structural frame to absorb predicted interstory drift without collapse.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Check the ability of the cladding panels and their connections to tolerate the story drift computed in Section 2.4.4 without an anchorage failure.
10.1.2.3 Cladding panel connections. Where bearing connections are required, there are at least two bearing connections for each cladding panel and there are at least four
2019 CALIFORNIA ADMINISTRATIVE CODE 125
Copyright © 2019 ICC. ALL RIGHTS RESERVED. Accessed by Kevin Day (kevin.day@dgs.ca.gov), (California Building Standards Commission) Order Number #100735044 on Jul 24, 2019 03:54 PM (PDT) pursuant to License Agreement with ICC. No further reproduction or distribution authorized. Single user only, copying and networking prohibited. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
100735044
SEISMIC EVALUATION PROCEDURES FOR HOSPITAL BUILDINGS
connections for each cladding panel capable of resisting outof-plane forces.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Verify that an adequate number of the appropriate connection types are present for each cladding panel.
10.1.2.4 Cladding panel condition. Cladding panel connections appear to be installed properly. No connection element is severely deteriorated or corroded. There is no cracking in the panel materials indicative of substantial structural distress. There is no substantial damage to exterior cladding due to water leakage. There is no substantial damage to exterior wall cladding due to temperature movements.
Substantial deterioration can lead to loss of cladding elements or panels. Exterior walls shall be checked for deterioration. Damage due to corrosion, rotting, freezing or erosion can be concealed within the wall. Probe into the wall space, if necessary, for signs of water leakage at vulnerable interior spaces (e.g., around windows and at floor areas). Check elements that tie cladding to the backup structure and that tie the back-up structure to floor and roof slabs. Check exterior walls for cracking due to thermal movements. Check the cladding systems with appropriate reductions in member capacities. Conforming buildings that fail this check shall be placed in SPC 4.
10.1.3 Metal stud back-up systems.
10.1.3.1 General. Additional steel studs frame window and door openings. Corrosion of veneer ties, tie screws, studs and stud tracks is minimal. Stud tracks are adequately fastened to the structural frame.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Verify that adequate framing has been provided around openings in the exterior walls. Check the cladding systems with appropriate reductions in member capacities. Check the adequacy of the connection to the structural frame using the forces specified in Section 2.4.6.
10.1.3.2 Masonry veneer with stud back-up. Masonry veneer more than 30 feet above the ground is supported by shelf angles or other elements at each floor level. Masonry veneer is adequately anchored to the back-up at locations of through-wall flashing. Masonry veneer is connected to the back-up with corrosion-resistant ties spaced 24 inches on center maximum and with at least one tie for every 2 2 /3 square feet.
stud back-up.** Masonry veneer more than 30 feet above the ground is supported by shelf angles or other elements at each floor level. Masonry veneer is adequately anchored to the back-up at locations of through-wall flashing. Masonry veneer is connected to the back-up with corrosion-resistant ties spaced 24 inches on center maximum and with at least one tie for every 2 2 /3 square feet.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Check that adequate supports and ties are provided.
10.1.4 Masonry veneer with concrete block back-up.
10.1.4.1 General. The concrete block back-up qualifies as reinforced masonry.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Verify that the concrete block back-up meets the requirements of Sections 5.3.2 and 5.3.3.
10.1.4.2 Masonry veneer support. Masonry veneer more than 30 feet above the ground is supported by shelf angles or other elements at each floor level. Masonry veneer is ade
quately anchored to the back-up at locations of through-wall flashing. Masonry veneer is connected to the back-up with corrosion-resistant ties spaced 24 inches on center maximum and with at least one tie for every 2 2 /3 square feet. The concrete block back-up is positively anchored to the structural frame at 4-foot maximum intervals along the floors and roofs.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Check that adequate supports and ties are provided.
10.1.5 Other veneer/panel systems.
10.1.5.1 Thin stone veneer panels. Stone anchorages are adequate for computed loads.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. There are no visible cracks or weak veins in the stone. Check the adequacy of the connection to the stone anchorage using the forces specified in Section 2.4.6.
10.1.5.2 Wood/aggregate panels. There is no visible deterioration of screws or wood at panel attachment points.
The deficiency is in the strength of the connections. Determine the cause and extent of distress and check the attachment of the panels with appropriate reductions in capacity. Conforming buildings that fail this check shall be placed in SPC 4.
10.1.6 Parapets, cornices, ornamentation and appendages. There are no laterally unsupported unreinforced masonry parapets or cornices above the highest anchorage level with height/ thickness ratios greater than 1.5. Concrete parapets with height/thickness ratios greater than 1.5 have vertical reinforcement. Cornices, parapets, signs and other appendages that extend above the highest anchorage level or cantilever from exterior wall faces and other exterior wall ornamentation are reinforced and well anchored to the structural system.
ve the highest anchorage level with height/ thickness ratios greater than 1.5. Concrete parapets with height/thickness ratios greater than 1.5 have vertical reinforcement. Cornices, parapets, signs and other appendages that extend above the highest anchorage level or cantilever from exterior wall faces and other exterior wall ornamentation are reinforced and well anchored to the structural system.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. If any of these items are of insufficient strength and/or are not securely attached to the structural elements, they may break off and fall, becoming significant life-safety hazards. Check the adequacy of these items using the forces specified in Section 2.4.6. The maximum height of an unbraced URM parapet shall be determined based on the height dimension measured above the lower of either the level of tension anchors or roof sheathing to the top of the wall parapet. The minimum height of a parapet above the wall anchor should be 12 inches.
Exception: If a reinforced concrete beam is provided at the top of the wall, the minimum height above the wall anchor may be 6 inches.
10.1.7 Means of egress. Canopies are anchored and braced to prevent collapse and blockage of building exits.
For conforming buildings, the evaluator may consider this condition as mitigated, and no calculations are necessary. Check canopies for the forces specified in Section 2.4.6.
126 2019 CALIFORNIA ADMINISTRATIVE CODE
Copyright © 2019 ICC. ALL RIGHTS RESERVED. Accessed by Kevin Day (kevin.day@dgs.ca.gov), (California Building Standards Commission) Order Number #100735044 on Jul 24, 2019 03:54 PM (PDT) pursuant to License Agreement with ICC. No further reproduction or distribution authorized. Single user only, copying and networking prohibited. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
100735044
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Administrative Code (Title 24, Part 1)
- Chapter 1 — ADMINISTRATIVE REGULATIONS OF THE
- Chapter 2 — ADMINISTRATIVE REGULATIONS FOR THE DEPARTMENT
- Chapter 3 — ADMINISTRATIVE REGULATIONS
- Chapter 4 — ADMINISTRATIVE REGULATIONS FOR THE DIVISION
- Chapter 5 — ACCESS TO PUBLIC BUILDINGS BY PERSONS WITH DISABIL…
▸Chapter 6 — SEISMIC EVALUATION PROCEDURES FOR HOSPITAL BUILDINGS
Overview- Article 1
- Article 11 — , Table 11.1 or shall no longer provide acute
- Article 2
- Article 1 — , Section 1.2, may be placed into SPC 4
- Article 3
- Article 4
- Article 5
- Article 6
- Article 7
- Article 8
- Article 9
- Article 10
- Article 11
- Article 11 — and Table 11.1. The language for the permanent
- Article 1 — , Article 2, Article 4, Article 6, Article 11, Table
- Article 1 — , Article 2, Article 4, Article 6, Article 11 and …
- Chapter 7 — SAFETY STANDARDS FOR HEALTH FACILITIES
- Chapter 8 — ADMINISTRATIVE REGULATIONS FOR THE CALIFORNIA
- Chapter 9 — ADMINISTRATIVE REGULATIONS FOR THE OCCUPATIONAL
- Chapter 10 — ADMINISTRATIVE REGULATIONS FOR THE
- Chapter 11 — ADMINISTRATIVE REGULATIONS FOR THE
- Chapter 12 — ADMINISTRATIVE REGULATIONS
- Chapter 13 — ADMINISTRATIVE REGULATIONS FOR THE BOARD
- Chapter 14 — ADMINISTRATIVE REGULATIONS
- Chapter 15 — DEPARTMENT OF CONSUMER AFFAIRS
- Chapter 16 — CALIFORNIA STATE LIBRARY