§ 9-4.701 SPECIFICATIONS.¶
All construction materials, methods, tests, and workmanship shall comply with city specifications for the construction of improvements and construction details and with the applicable provisions of the “Standard Specifications” of the Department of Trans-portation of the state current at the time of the filing of the final map of the subdivision.
('66 Code, § 9-4.701) (Ord. 275-C-S, passed 3-11-75) Penalty, see § 9-4.903
§ 9-4.702 INSPECTIONS.¶
(A) All work done in constructing improvements and all materials furnished shall be subject to the inspection of the Engineering Division.
(B) The Engineering Division shall have access to the work at all times during its construction and shall be furnished with every reasonable facility forascertaining that the materials used and the workmanship are in accordance with the requirements and intentions of this chapter.
(C) If any of the work on improvements is done by the subdivider prior to the approval of the improvement plans or prior to the inspections of the improvements as required by the City Engineer, such work may be rejected and shall be deemed to have been done at the risk and peril of the subdivider.
('66 Code, § 9-4.702) (Ord. 275-C-S, passed 3-11-75) Penalty, see § 9-4.903
§ 9-4.703 COMPLETION.¶
The subdivider shall prosecute the work to completion without undue delay, except for inclement weather or other reasonable causes. Delays in the completion of the work beyond the period stated in the subdivision agreement, unless an extension thereof is approved by the Council and the surety company, may result in the forfeiture of the cash deposit and/or security, or a portion thereof, for the completion of the work.
('66 Code, § 9-4.703) (Ord. 275-C-S, passed 3-11-75) Penalty, see § 9-4.903
§ 9-4.704 ACCEPTANCE.¶
(A) When all the improvement work required by the improvement plans, or a complete unit thereof, is completed to the satisfaction of the City Engineer, he shall issue a certificate to the Council stating that such portion of the work has been satisfactorily completed and shall recommend the acceptance by the Council of the completed portion of the work.
(B) Upon the satisfactory completion of all the work required to meet the requirements of this chapter and its acceptance by the Council. The Council shall file a notice of completion as to the required improvements in the office of the County Recorder.
(C) Any unexpended cash deposits not required for the completion of the work shall be refunded.
('66 Code, § 9-4.704) (Ord. 275-C-S, passed 3-11-75)