Overview

Wasco uses a two-tier system for design oversight: a citywide design review step called “Site Plan and Design Review,” and district-specific design rules in certain combining/overlay districts. Citywide, most projects with exterior work must clear § 17.52.060 before any building, grading, or occupancy approvals issue . In the Historic Downtown (H-D) combining district, a separate, focused “Downtown Design Review” applies with its own submittals, findings, timelines, and limited exemptions under § 17.24.040 .

In plain English: if you’re proposing new construction or any exterior changes in Wasco, expect to complete Site Plan and Design Review citywide, and if you’re in the Historic Downtown overlay, expect a specialized Downtown Design Review on top of that (§ 17.52.060; § 17.24.040).

How Site Plan and Design Review Works (citywide)

  • Trigger. Required for any project tied to a building or planning permit that involves construction, exterior building alteration, site or landscaping design, or other actions affecting the functional or aesthetic qualities of land or structures. No building/grading permits, business licenses, or certificates of occupancy issue until review is complete (§ 17.52.060(B)) .
  • Submittal/Completeness. The Director determines what application items are needed; a pre-application meeting is encouraged (§ 17.52.060(C)). Completeness is checked per the Permit Streamlining Act timelines (§ 17.50.050) .
  • Review standard. Staff checks consistency with this zoning code’s development standards, adopted design guidelines, and relevant policies (§ 17.52.060(D)) .
  • Required findings. Approval requires all four: allowed in the zone; complies with standards/guidelines; in keeping with neighborhood/project character; and not detrimental to orderly growth or public health and safety (§ 17.52.060(E)) .
  • Decision-maker. The Planning Director is the final review authority for Site Plan and Design Review (Table 5‑1; § 17.50.030), with appeal rights shown there (§ 17.50.030) .
  • Conditions/Enforcement. Conditions may be imposed to ensure compliance (§ 17.52.060(F)); permits can be revoked/modified (§ 17.52.110) .
  • Related chapters that commonly apply during review:
    • Wasco Development Standards — citywide site planning rules (e.g., fences/walls, equipment screening) in Chapter 17.30 frequently shape design review outcomes (§§ 17.30.020–.030) .
    • Wasco Landscaping and Screening — water-efficient landscaping thresholds and plan requirements in Chapter 17.34 can be triggered by design review (§§ 17.34.010–.030) .
    • Wasco Signage — many signs need a sign permit; signs are also reviewed against district design standards (§ 17.50.020; Chapter 17.38 reference) .
    • Wasco Parking — parking placement/landscaping is often conditioned through design review; Downtown has additional placement rules (§ 17.24.040, Downtown parking/access) .

District-by-District: Where Design Review Adds Requirements

Historic Downtown (H-D) Combining District — § 17.24.040

  • Purpose and geography. Protects and revitalizes the Downtown core; boundaries are codified; the H-D overlay combines with the C-D (Central District) base zone and is mapped as C-D‑H‑D (§ 17.24.040(A)(1)–(3)) .
  • What projects need Downtown Design Review. Any rehabilitation, renovation, alteration, reconstruction, painting, enlargement, or demolition of an existing building; or any new building, parking lot, or other structure triggers a design review application to the Planning Department (§ 17.24.040(B)(2)) .
  • Typical permitted uses. Uses follow the C-D base zone with specified exceptions (e.g., ABC-licensed uses may need a CUP; sit-down restaurants serving alcohol incidental to food are exempt from that CUP) (§ 17.24.040(B)(1)) .
  • Key dimensional/design standards that matter in review:
    • Storefront transparency, awnings, and façade rules; certain bright/fluorescent colors prohibited (§ 17.24.040, design standards) .
    • Fences/walls must be at least 50% transparent along streets; materials are limited (e.g., wrought iron, stone, brick; no painting of certain materials) (§ 17.24.040, fence/wall screening) .
    • Landscaping must screen parking and comply with § 17.34.030, unless modified by Downtown guidelines (§ 17.24.040, landscaping) .
    • Parking location: prioritize rear; no new lots between the street and storefront; limited access to 7th Street without a CUP (§ 17.24.040, Parking Location and Access) .
  • Process. The Planning Director reviews for consistency with Downtown regulations and the Historic Downtown Policy and Design Plan and may approve, condition, or deny; the decision is final unless appealed under Chapter 17.72 (§ 17.24.040(H)(1)–(4)) .
  • Timelines and enforcement. Approvals lapse if not acted upon within one year unless extended; non‑conforming to approved plans can trigger permit suspension and Planning Commission action (§ 17.24.040(H)(5)–(6)) .
  • Exemptions. Minor improvements (e.g., repairing awnings; replacing windows/doors/roofs; painting if colors are consistent with guidelines and approved; alterations to single-family dwellings) are exempt from Downtown Design Review (§ 17.24.040(H)(8)) .
  • Demolition. Downtown demolitions require Planning Department approval through the site plan review process; a separate demolition permit is also required (§ 17.24.040(I)) .
  • Prohibited uses. Adult-oriented businesses, smoke shops, internet cafés, and new vehicle-oriented uses (drive‑throughs, service bays) are prohibited (§ 17.24.040(C)) .

Precise Development Plan (P-D) Combining District — § 17.24.050

  • Purpose. Applies where unique conditions require tailored standards and superior design quality (§ 17.24.050(A)) .
  • Uses and standards. Uses follow the base zone, but development standards and lot sizes can deviate; density transfers within the P‑D area are allowed as long as the overall general plan density is met (§ 17.24.050(B)–(C)) .
  • Process. A P‑D permit with a public hearing before the Planning Commission is required; findings are recorded; minor plan modifications can be approved administratively (§ 17.24.050(D)) .
  • Where it applies. Mapped as an overlay (e.g., R‑1‑P‑D‑01) to specific projects/areas (§ 17.24.050(B)) .

Cluster (C-L) Combining District — § 17.24.060

  • Purpose. Promotes imaginative, well‑designed development to preserve open space, support housing, preserve agriculture, and share amenities (§ 17.24.060(A)) .
  • Uses/standards. Uses follow the base zone; development standards generally follow the base zone; overall density cannot exceed the general plan category (§ 17.24.060(B)–(C)) .
  • Design quality. Projects must be superior to base-zone outcomes in at least two ways (e.g., more open space/landscaping, better connectivity, superior site/building design, reduced impacts) (§ 17.24.060(C)(1)) .
  • Process. A C‑L site plan review permit is required and processed under § 17.52.060 by the Planning Director; minor modifications and time limits are codified (§ 17.24.060(D)) .

Geological Hazard (G-H) Combining District — § 17.24.070

  • Purpose. Limits risk from surface faulting, ground shaking/failure, etc. (§ 17.24.070(A)) .
  • Uses/standards. Uses follow the base zone, but development must comply with an approved G‑H site plan review permit; mitigation and setbacks include at least 50 ft from active fault traces or 100 ft from inferred traces (§ 17.24.070(B), (C)(1)) .
  • Process. A G‑H site plan review permit must be approved by the Planning Director, City Engineer, and Planning Commission; application content includes geologic studies (§ 17.24.070(D)) .

Airport Approach (A-A) Combining District — § 17.24.030

  • Purpose. Minimizes aviation hazards in airport compatibility zones consistent with the Kern County ALUCP (§ 17.24.030(A)) .
  • Uses/standards. Uses follow the base zone, adjusted for ALUCP constraints; height and density limits align with ALUCP; most other standards default to the base zone (§ 17.24.030(B)–(C)) .
  • Design review. No special A‑A–specific design review procedure is codified beyond the standard citywide process in § 17.52.060 (Not found in retrieved materials for any additional A‑A design step).

Decision-Relevant Design Review Pathways

Context What triggers it Decision-maker Key standards/limits Code Reference
Citywide Site Plan and Design Review Any building/planning permit involving construction, exterior changes, site or landscaping design Planning Director (final); appeal per Table 5‑1 Must meet 4 findings; conditions may be imposed § 17.52.060; § 17.50.030 Table 5‑1
Historic Downtown (H-D) Design Review Any new building, exterior alteration, painting, enlargement, parking lot, or demolition in H-D Planning Director (final; appeal per Ch. 17.72) Downtown design standards/guidelines; 1‑year expiration; limited exemptions for “minor improvements” § 17.24.040(H); § 17.24.040(I)
Cluster (C-L) Overlay Development within a C‑L district Planning Director Must be “superior” in at least two enumerated ways; standards generally follow base zone § 17.24.060(C)–(D)
Precise Development (P-D) Overlay Development within a P‑D district Planning Commission (hearing) May deviate from base standards if overall GP density met; superior design intent § 17.24.050(A)–(D)
Geological Hazard (G-H) Overlay Any use or development in G‑H Planning Director, City Engineer, Planning Commission Fault setbacks (50/100 ft) and mitigation per geologic report § 17.24.070(B)–(D)
Specific Plan (S-P) Overlay Development within S‑P City Council (legislative) Standards set by adopted specific plan; superior design factors listed § 17.52.070(C)

Practical Notes for Applicants

  • Coordinate early. The Director can elevate review to a higher authority where unusual circumstances exist (Table 5‑1 context; § 17.50.020(B)) .
  • Expect cross‑checks. Review commonly pulls in development standards (e.g., screening, fences/walls), landscaping, and signage chapters.
  • Downtown specifics. Projects in H‑D face added storefront, awning, fencing, landscaping, and parking‑placement rules, plus a distinct review process and one‑year approval window (§ 17.24.040(H)) .
  • CEQA. Environmental review may be required after completeness is established (§ 17.50.060) .
  • Nonconforming situations. Alterations can trigger review and conditions; see Wasco Nonconforming Uses for status implications (Not found in retrieved materials for a direct cross‑cite).

Checklist

  • Confirm your property’s base zoning and any combining/overlay districts in the Wasco Zoning map; if in H‑D, prepare for Downtown Design Review (§ 17.24.040(B)(2)) .
  • Prepare a complete Site Plan and Design Review application with all items the Director requires; consider a pre‑application meeting (§ 17.52.060(C)) .
  • Demonstrate compliance with applicable development standards and adopted design guidelines; address neighborhood character in your narrative (§ 17.52.060(D)–(E)) .
  • If Downtown: include required submittals (scaled site plan, elevations, material/color samples, landscaping, signs/lighting) (§ 17.24.040(B)(2)) .
  • Address landscaping thresholds and provide plans when triggered (§ 17.34.010–.030) .
  • If applicable, secure any variances or exceptions needed to meet design goals (appeals/exceptions referenced in § 17.24.040(H)(7) and § 17.50.020) .
  • Anticipate CEQA and special studies, if needed (§ 17.50.060) .
  • Do not conflate design review with the California Building Standards Code; building-code compliance is separate and follows after design approvals.

Risks & Ambiguities

Issue Why it matters What to verify
Are you inside the H‑D overlay? Triggers Downtown Design Review, unique standards, and a one‑year approval window Confirm overlay mapping and boundaries (§ 17.24.040(A), Figure 2‑1)
“Minor improvements” exemption scope (H‑D) Certain small projects may skip Downtown Design Review Whether your specific work fits the listed exemptions (§ 17.24.040(H)(8)); when in doubt, ask Planning
Who decides and who hears appeals? Determines schedule and risk Site Plan and Design Review is a Director decision; confirm appeal path in Table 5‑1 and references in H‑D (§ 17.50.030; § 17.24.040(H)(4))
Overlay-specific permits Some overlays layer in extra site plan permits (e.g., C‑L, G‑H) Whether your site sits in C‑L or G‑H and which additional findings or studies apply (§ 17.24.060(D); § 17.24.070(D))
Downtown demolition Adds approvals and timing Downtown demolitions require Planning approval via site plan review and separate demo permits (§ 17.24.040(I))
CEQA timeline impacts Can extend processing Whether your project is exempt, ND/MND, or EIR (§ 17.50.060)

Plain-English Summary

If you change what the public sees on your property in Wasco, you almost always need citywide Site Plan and Design Review before permits. In the Historic Downtown, you’ll also go through a Downtown-specific design review with extra storefront, awning, fencing, landscaping, and parking-placement rules. Most other overlays rely on the same citywide review, but some (like Cluster or Geologic Hazard) add special findings or studies. When in doubt, check your zoning, overlays, and talk to Planning early.

Source References

  • § 17.52.060 Site Plan and Design Review — triggers, findings, conditions, processing
  • § 17.50.030 (Table 5‑1) Planning Permit Review Authority — Director decision/appeal structure for Site Plan and Design Review
  • § 17.24.040 Historic Downtown (H‑D) Combining District — purpose, boundaries, design review, standards, exemptions, demolition, appeals, expiration, enforcement
  • § 17.24.050 Precise Development Plan (P‑D) Combining District — purpose, deviations, process
  • § 17.24.060 Cluster (C‑L) Combining District — superior‑design criteria; site plan review permit; Director decision
  • § 17.24.070 Geological Hazard (G‑H) Combining District — site plan review permit; fault setbacks; studies; review bodies
  • § 17.24.030 Airport Approach (A‑A) Combining District — purpose; standards per ALUCP and base zone
  • § 17.50.050 Initial Application Completeness Review; § 17.50.060 Environmental Review (CEQA) — process timing and studies

Sources

Retrieved passages

  • Wasco Zoning Code (Title 17) High relevance
  • Wasco Zoning Code (Title 17) High relevance
  • Wasco Zoning Code (§ 3) High relevance
  • Wasco Zoning Code (Section 17.34.030) High relevance
  • Wasco Zoning Code (section identifies) Medium relevance
  • Wasco Zoning Code (Title 17) Medium relevance
  • Wasco Zoning Code (title is) Medium relevance
  • Wasco Zoning Code (Title 17) Medium relevance
  • Wasco Zoning Code (Title 17) High relevance
  • Wasco Zoning Code (chapter may) High relevance
  • Wasco Zoning Code (Chapter 17.72.) Medium relevance
  • Wasco Zoning Code (section shall) Medium relevance

Cited sections

  • § 17.52.060 Site Plan and Design Review — triggers, findings, conditions, processing (§ 17.52.060)
  • § 17.50.030 (Table 5‑1) Planning Permit Review Authority — Director decision/appeal structure for Site Plan and Design Review (§ 17.50.030)
  • § 17.24.040 Historic Downtown (H‑D) Combining District — purpose, boundaries, design review, standards, exemptions, demolition, appeals, expiration, enforcement (§ 17.24.040)
  • § 17.24.050 Precise Development Plan (P‑D) Combining District — purpose, deviations, process (§ 17.24.050)
  • § 17.24.060 Cluster (C‑L) Combining District — superior‑design criteria; site plan review permit; Director decision (§ 17.24.060)
  • § 17.24.070 Geological Hazard (G‑H) Combining District — site plan review permit; fault setbacks; studies; review bodies (§ 17.24.070)
  • § 17.24.030 Airport Approach (A‑A) Combining District — purpose; standards per ALUCP and base zone (§ 17.24.030)
  • § 17.50.050 Initial Application Completeness Review; § 17.50.060 Environmental Review (CEQA) — process timing and studies (§ 17.50.050)
  • Wasco_ZoningCode.md

Frequently asked questions

Do I need design review in Wasco for a simple exterior facelift?

Yes—citywide Site Plan and Design Review applies to any project involving construction, exterior building alteration, or site/landscaping design. Permits won’t be issued until you clear it (§ 17.52.060(B)) .

How is Downtown Wasco different for design review?

Within the Historic Downtown (H‑D), Downtown Design Review is required for new construction, exterior alterations, painting, enlargements, parking lots, and demolitions, with specific storefront/awning/fencing/landscaping/parking standards and a one‑year approval window (§ 17.24.040(B), (H)–(I)) .

Who decides my Site Plan and Design Review and can I appeal?

The Planning Director makes the final decision for Site Plan and Design Review; appeals follow Table 5‑1 and applicable appeal chapters. Downtown decisions are final unless appealed under Chapter 17.72 (§ 17.50.030; § 17.24.040(H)(4)) .

What findings must be met to get design review approval?

Four findings: the use is allowed in the zone; the project meets development standards and any adopted design guidelines; it fits neighborhood/project character; and it’s not detrimental to orderly growth or public health/safety (§ 17.52.060(E)) .

Are any small projects in Downtown exempt from design review?

Yes. Minor improvements like awning repair, window/door/roof replacement, certain painting (with approved colors), and alterations to single‑family dwellings are exempt (§ 17.24.040(H)(8)) .

Can Downtown approvals expire?

Yes. A Downtown design review approval becomes void after one year unless a building permit issues and work begins, or an extension is granted (§ 17.24.040(H)(5)) .

What if my property is in a Cluster (C‑L) overlay?

You’ll need a C‑L site plan review permit, and your project must be superior to base‑zone development in at least two enumerated ways (e.g., more open space, better connectivity). The Planning Director is the review authority (§ 17.24.060(C)–(D)) .

Are there special design setbacks for geologic hazards?

Yes. In the G‑H overlay, structures for human occupancy must be set back at least 50 ft from active fault traces, or 100 ft if the trace is inferred/uncertain, and mitigation measures from a geologic report must be followed (§ 17.24.070(C)(1)) .

Does the Airport Approach overlay change design review?

It imposes height/density constraints consistent with the ALUCP, but no separate A‑A design review process is codified beyond the standard citywide review (§ 17.24.030) .

Will landscaping plans be required as part of design review?

Often, yes. Landscaping thresholds and plan requirements in Chapter 17.34 apply to many projects subject to design review (§ 17.34.010–.030) .

More in Wasco code

Ask about any Wasco property

Get a cited, plain-English answer on Wasco zoning, setbacks, FAR, ADUs and permits — for any address.

Start Free Trial

More Wasco zoning topics