Yes — you can build an ADU in Santa Fe Springs. California's statewide ADU law requires every city, including Santa Fe Springs, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Santa Fe Springs's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

Local rule

1 ADU (attached or detached) + 1 JADU (within existing/proposed residence)

Clarifies JADU must be within the walls of the existing or proposed residence.

SFS MC § 155.644(D)(2)(a)

Units on a multifamily lot

Local rule

conversions (>=1 or 25% of units) + up to 2 detached

City limits detached ADUs on multifamily lots to 2 per lot, less than state default of 8.

SFS MC § 155.644(D)(2)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,200 sq ft

1,200 sq ft for >1 bedroom; 850 sq ft for studio/1-bedroom. This is a local cap.

SFS MC § 155.644(D)(5)(a)-(b)

Max attached ADU size

Local rule

850 sq ft (1 bedroom or less); 1,200 sq ft (more than 1 bedroom)

Attached ADUs capped at same size as detached.

SFS MC § 155.644(D)(5)(a)-(b)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

CA state law

16 ft

16 ft baseline; cities must allow 18 ft within ½ mi of a major transit stop or where the primary dwelling is two-story, and 20 ft on a lot with a multistory multifamily building.

Cal. Gov. Code § 66321 (size minimums & height)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

CA state law

None required

No statewide separation requirement between the ADU and the primary dwelling.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Parking

Parking required

Local rule

Up to 1 space

Not more than 1 space per ADU; exemptions per state law.

SFS MC § 155.644(D)(11)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

Local rule

Not required

No replacement parking required for garage/carport conversion.

SFS MC § 155.644(D)(12)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

Local rule

60 days

Application deemed approved if not acted on in 60 days.

SFS MC § 155.644(C)(1), (F)(1)

Owner-occupancy

Local rule

Only for a JADU

No owner-occupancy for ADUs; JADUs require owner-occupancy.

SFS MC § 155.644(F)(1); Gov. Code § 66315

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

CA state law

Building permit

Only a ministerial building permit — no conditional use permit or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Santa Fe Springs-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Historic District

No parking required for ADUs in historic districts.

Fire Code Compliance

ADUs must comply with all building, safety, fire, and health codes; sprinklers not required unless for primary dwelling.

Santa Fe Springs limits detached ADUs on multifamily lots to 2 per lot and caps both attached and detached ADUs at 1,200 sq ft (850 sq ft for studios/1-bedrooms). Attached ADUs may be up to 25 ft tall, exceeding the state default for detached units.

Frequently asked questions

Can I build an ADU in Santa Fe Springs?

Yes. California's statewide ADU law requires Santa Fe Springs to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Santa Fe Springs?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Santa Fe Springs?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Santa Fe Springs?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Santa Fe Springs?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Santa Fe Springs?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Santa Fe Springs Municipal Code § 155.644
  • SFS MC § 155.644(D)(2)(a)
  • SFS MC § 155.644(D)(2)
  • SFS MC § 155.644(D)(5)(a)-(b)
  • SFS MC § 155.644(D)(11)
  • SFS MC § 155.644(D)(12)
  • SFS MC § 155.644(C)(1), (F)(1)
  • SFS MC § 155.644(F)(1); Gov. Code § 66315
  • SFS MC § 155.644(D)(12)(b)
  • SFS MC § 155.644(D)(9)
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66333 (junior ADUs)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated 2026-06-25. This is an AI-assisted summary of Santa Fe Springs's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Santa Fe Springs Planning before relying on it.