California ADU rules · Los Angeles County

Can I Build an ADU in Rosemead?

Yes — you can build an ADU in Rosemead. California's statewide ADU law requires every city, including Rosemead, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Rosemead's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

Local rule

1 attached OR 1 detached + 1 JADU

Allows either 1 attached ADU, or 1 detached ADU plus 1 JADU on a single-family lot.

Rosemead Zoning Code §17.30.190.C.3

Units on a multifamily lot

Local rule

up to 2 detached + conversions (>=1 or 25% of units)

Limits detached ADUs on multifamily lots to 2; allows at least 1 attached ADU or up to 25% of units as conversions.

Rosemead Zoning Code §17.30.190.C.4–5

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,200 sq ft

1,200 sq ft max for detached ADU with more than one bedroom; if both a JADU and detached ADU are built, detached ADU is limited to 800 sq ft.

Rosemead Zoning Code Table 17.30.190.1

Max attached ADU size

Local rule

50% of primary; if primary <1,600 sq ft, then 800 sq ft allowed

Attached ADU limited to 50% of primary residence; 800 sq ft minimum if primary residence is less than 1,600 sq ft.

Rosemead Zoning Code Table 17.30.190.1

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

Local rule

17 ft

One-story detached ADU: 17 ft; two-story: 30 ft; if primary residence is less than 16 ft, ADU max height is 16 ft.

Rosemead Zoning Code Table 17.30.190.1

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

Local rule

10 ft

10 ft minimum separation required between detached ADU and primary dwelling, unless not feasible (then state minimums apply).

Rosemead Zoning Code Table 17.30.190.1

Parking

Parking required

Local rule

Up to 1 space

One parking space per bedroom or per ADU, whichever is less; tandem parking allowed.

Rosemead Zoning Code Table 17.30.190.1

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

CA state law

Not required

When a garage/carport is demolished or converted to build an ADU, replacement parking cannot be required.

Cal. Gov. Code § 66314 (local ordinance standards)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

Local rule

Not required

No owner-occupancy required for ADUs permitted between Jan 1, 2020 and Jan 1, 2025.

Rosemead Zoning Code §17.30.190.C.10; State Gov. Code §66317

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

Local rule

Building permit, Administrative site plan/design review

Both building permit and administrative site plan/design review required.

Rosemead Zoning Code §17.30.190.C.1

Rosemead-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Historic Districts

No ADU parking required in historic districts; conversions may have additional review.

Rosemead limits detached ADUs on multifamily lots to two and requires a 10-foot separation from the primary dwelling for detached ADUs. Owner-occupancy is not required for ADUs permitted through 2024.

Frequently asked questions

Can I build an ADU in Rosemead?

Yes. California's statewide ADU law requires Rosemead to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Rosemead?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Rosemead?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Rosemead?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Rosemead?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Rosemead?

Owner-occupancy: not required. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Rosemead Zoning Code §17.30.190; Table 17.30.190.1; Ord. No. 931, § 5(Exh. A), 10-22-13
  • Rosemead Zoning Code §17.30.190.C.3
  • Rosemead Zoning Code §17.30.190.C.4–5
  • Rosemead Zoning Code Table 17.30.190.1
  • Rosemead Zoning Code §17.30.190.C.10; State Gov. Code §66317
  • Rosemead Zoning Code §17.30.190.C.1
  • Rosemead Zoning Code Table 17.30.190.1; §17.30.190.C.12
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66333 (junior ADUs)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66314 (local ordinance standards)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated 2026-06-25. This is an AI-assisted summary of Rosemead's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Rosemead Planning before relying on it.

Will an ADU work on your Rosemead lot?

Ask GoCodebook about your address and get the size, setback, parking and permit rules that actually apply to your parcel — with the exact citation.

Check my parcel free

Related