Can I Build an ADU in Garden Grove?

Yes — you can build an ADU in Garden Grove. California's statewide ADU law requires every city, including Garden Grove, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Garden Grove's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

CA state law

Conversion ADUs (≥1, up to 25% of units) + up to 8 detached

Conversions of non-livable space (at least 1, or up to 25% of existing units) plus up to 8 detached ADUs on a lot with existing multifamily — never exceeding the number of existing units. JADUs are single-family only.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,200 sq ft

Detached ADU capped at 850 sq ft for a studio/1-bedroom and 1,200 sq ft for 2+ bedrooms. The 800 sq ft state ADU is allowed by right regardless.

Max attached ADU size

Local rule

850 sq ft (studio/1-bedroom) or 1,200 sq ft (2+ bedrooms), or 50% of the primary dwelling, whichever is less — but at least 800 sq ft where the primary dwelling is under 1,600 sq ft

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

CA state law

16 ft

16 ft baseline; cities must allow 18 ft within ½ mi of a major transit stop or where the primary dwelling is two-story, and 20 ft on a lot with a multistory multifamily building.

Cal. Gov. Code § 66321 (size minimums & height)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

Local rule

6 ft

Garden Grove requires 6 ft of separation between a detached ADU and the primary dwelling (state law sets none); this does not apply to conversion ADUs.

Parking

Parking required

CA state law

Up to 1 space

At most 1 space per ADU (or per bedroom, whichever is less) — and waived in the common cases below.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

CA state law

Not required

When a garage/carport is demolished or converted to build an ADU, replacement parking cannot be required.

Cal. Gov. Code § 66314 (local ordinance standards)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

Local rule

30 days

Standard ADU/JADU applications get a 60-day decision; a detached ADU built from a City pre-approved plan gets an accelerated 30-day decision.

Owner-occupancy

CA state law

Only for a JADU

No owner-occupancy requirement for ADUs (the prior sunset was removed). A JADU may require owner-occupancy, principally where it shares sanitation with the main house.

Cal. Gov. Code § 66315 (owner-occupancy)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

CA state law

Building permit

Only a ministerial building permit — no conditional use permit or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Garden Grove-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Pre-approved ADU plan program

Garden Grove offers City pre-approved detached-ADU plans; using one cuts the decision deadline to 30 days (vs the standard 60).

Garden Grove's 2025 ordinance sizes detached ADUs by bedroom count (850 sq ft for studio/1-bedroom, up to 1,200 sq ft for 2+ bedrooms), requires 6 ft of separation from the main house, and rewards its pre-approved detached-ADU plans with a 30-day decision instead of the usual 60. There are no coastal, fire, or hillside ADU overlays in the city.

Frequently asked questions

Can I build an ADU in Garden Grove?

Yes. California's statewide ADU law requires Garden Grove to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Garden Grove?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Garden Grove?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Garden Grove?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Garden Grove?

A complete application must be acted on within 30 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Garden Grove?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

Last updated 2026-06-25. This is an AI-assisted summary of Garden Grove's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Garden Grove Planning before relying on it.