Rev. Proc. 2018-58, section 15, 2018–50

Internal Revenue Bulletin 2020-30 · 2026-10-03 edition · updated 2026-10-04 · United States

IRB at 1015.

Thus, in addition to other postponements (including other postponements for purposes of § 42 listed in Rev. Proc. 2018-58), Notice 2020-23 postponed until July 15, 2020, the time to perform the following time-sensitive actions for purposes of § 42 that are due to be performed on or after April 1, 2020, and before July 15, 2020:

  • The 10-percent test under § 42(h)(1) (E)(ii);

  • The 24-month minimum rehabilitation expenditure period under § 42(e); and

  • The income recertification requirement under § 1.42-5(c)(1)(iii).

IV. SCOPE OF THE RELIEF GRANTED IN THIS NOTICE

Sections V.A though E and VI.A through D of this notice apply to low-income housing projects under § 42, to qualified residential rental projects under § 142(d), and to Agencies, Issuers, Owners, and Operators that have responsibilities with respect to those projects. ­Section V.F of this notice applies to bonds for qualified residential rental projects that would be qualified bonds (as defined in § 141(e)) if the requirements of § 147(d) (2) were satisfied. The persons described in this section IV have been determined by the Secretary to be persons affected by the COVID-19 emergency for the purposes of the relief described in section V of this notice. In addition, the recipients of relief described in section VI of this

notice have been determined by the Secretary to be sufficiently affected by the COVID–19 pandemic to merit the relief that is provided here under the authority of § 1.42–13(a).

V. GRANT OF RELIEF PURSUANT TO SECTION 7508A

A. THE 10-PERCENT TEST FOR CARRYOVER ALLOCATIONS

For purposes of § 42(h)(1)(E)(ii), if the last day for an Owner of a building with a carryover allocation to meet the 10-percent test is on or after April 1, 2020, and before December 31, 2020, the last day for the Owner to meet the 10-percent test is postponed to December 31, 2020.

B. THE § 42(e) 24-MONTH MINIMUM REHABILITATION EXPENDITURE PERIOD

For purposes of § 42(e)(3)(A)(ii), if the 24-month minimum rehabilitation expenditure period for a building originally ends on or after April 1, 2020, and before December 31, 2020, the last day for the Owner to incur the minimum rehabilitation expenditures with respect to the building is postponed to December 31, 2020.

C. REASONABLE PERIOD FOR RESTORATION OR REPLACEMENT IN THE EVENT OF CASUALTY LOSS

For purposes of § 42(j)(4)(E), if a low-income building has suffered a ca

sualty loss and the reasonable period to restore by reconstruction or replacement ends on or after April 1, 2020, and before December 31, 2020, the last day for the Owner of the building to restore the loss by reconstruction or replacement is postponed to December 31, 2020.

D. REASONABLE RESTORATION PERIOD IN THE EVENT OF PRIOR MAJOR DISASTER

For purposes of section 8.02 of Rev. Proc. 2014-49, if a low-income building, due to a prior Major Disaster, has suffered a casualty loss that would have reduced its qualified basis and if the reasonable restoration period determined by the Agency for the building ends on or after April 1, 2020, and before December 31, 2020, the last day for the Owner of the building to complete the repair and restoration is postponed to December 31, 2020.

E. THE 12-MONTH TRANSITION PERIOD TO MEET SET-ASIDES FOR QUALIFIED RESIDENTIAL RENTAL PROJECTS

For purposes of section 5.02 of Rev. Proc. 2004-39, the last day of a 12-month transition period for a qualified residential rental project that ends on or after April 1, 2020, and before December 31, 2020, is postponed to December 31, 2020.

Bulletin No. 2020–30 153 July 20, 2020

F. THE § 147(d) 2-YEAR REHABILITATION EXPENDITURE PERIOD FOR BONDS USED TO PROVIDE QUALIFIED RESIDENTIAL RENTAL PROJECTS

If a bond is used to provide a qualified residential rental project and if the § 147(d) 2-year rehabilitation expenditure period for the bond ends on or after April 1, 2020, and before December 31, 2020, the last day of that period is postponed to December 31, 2020.

VI. GRANT OF RELIEF PURSUANT TO § 1.42-13(a)

A. INCOME RECERTIFICATIONS

An Owner of a low-income building is not required to perform income recertifications under § 1.42-5(c)(1)(iii) in the period beginning on April 1, 2020, and ending on December 31, 2020. The Owner must resume the income recertifications as due under § 1.42-5(c)(1)(iii) after December 31, 2020.

B. COMPLIANCE-MONITORING

For purposes of § 1.42-5, an Agency is not required to conduct compliance-monitoring inspections or reviews in the period beginning on April 1, 2020, and ending on December 31, 2020. The Agency must re

sume compliance-monitoring inspections or reviews as due under § 1.42-5 after December 31, 2020.

C. COMMON AREAS AND AMENITIES

If an amenity or common area in a low-income building or project is temporarily unavailable or closed during some or all of the period from April 1, 2020 to December 31, 2020, in response to the COVID-19 pandemic, and not because of other noncompliance for § 42 purposes, this temporary closure does not result in a reduction of the eligible basis of the building.

D. EMERGENCY HOUSING FOR MEDICAL PERSONNEL AND OTHER ESSENTIAL WORKERS

If individuals who are medical personnel or other essential workers (as defined by State or local governments) provide services during the COVID-19 pandemic, then, for purposes of providing emergency housing from April 1, 2020, to December 31, 2020, under Rev. Proc. 2014-49 or under Rev. Proc. 2014-50, Agencies, Issuers, Owners, and Operators of low-income housing projects may treat these individuals as if they were Displaced Individuals (defined under section 5.02 of Rev. Proc. 2014-49 or Section 4.04 of Rev. Proc.

2014-50, as applicable). That is, Agencies, Issuers, Owners, and Operators may provide emergency housing for these individuals pursuant to the provisions of the applicable revenue procedure. See sections 12, 13, and 14 of Rev. Proc. 2014-49 and sections 5, 6, and 7 of Rev. Proc. 2014-50.

VII. EFFECTIVE DATE

This notice is effective as of July 1, 2020.

VIII. EFFECT ON OTHER DOCUMENTS

Notice 2020-23, Rev. Proc. 2004-39, Rev. Proc. 2014-49, and Rev. Proc. 201450 are amplified.

IX. DRAFTING INFORMATION

The principal authors of this notice are Dillon Taylor and Michael J. Torruella Costa, Office of the Associate Chief Counsel (Passthroughs and Special Industries), and Timothy L. Jones and David White, Office of the Associate Chief Counsel (Financial Institutions and Products). For further information regarding this notice, contact Dillon Taylor or Michael J. Torruella Costa at (202) 317-4137 (not a tollfree number); contact Timothy L. Jones or David White at (202) 317-6980 (not a toll-free number).

July 20, 2020 154 Bulletin No. 2020–30

Get a plain-English answer with a citation back to this text.

Ask AI about this code