SECTION 5. APPLICATIONS FOR

Internal Revenue Bulletin 2007-26 · 2026-10-03 edition · updated 2026-10-04 · United States

CERTIFICATIONS

.01 In General . An application for § 48A certification and a separate application for DOE certification must be submitted for each qualifying advanced coal project. If an application for DOE certification does not include all of the information required by section 5.02 of this

notice and meet the requirements in sections 7.01 and 7.02 of this notice, the DOE may decline to accept the application. If an application for § 48A certification does not include all of the information listed in section 5.03(1) of this notice and meet the requirements in sections 7.01 and 7.02 of this notice, the application will not be accepted by the Service.

.02 Information Required in the Appli- cation for DOE Certification . An application for DOE certification must include all of the information requested in Appendix B to this notice and all of the following:

(1) The name, address, and taxpayer identification number of the taxpayer. If the taxpayer is a member of an affiliated group filing consolidated returns, also provide the name, address, and taxpayer identification number of the common parent of the group.

(2) The name and telephone number of a contact person.

(3) The name and address (or other unique identifying designation) of the qualifying advanced coal project.

(4) A statement specifying whether the project is an IGCC project or a qualifying advanced coal project that uses another advanced coal-based technology.

(5) In the case of an IGCC project, a statement specifying the type of coal (bituminous coal, subbituminous coal, or lignite) that will be the primary feedstock. An application for DOE certification with respect to an IGCC project will not be considered unless one of these types of coal is the primary feedstock. For purposes of § 48A(e)(3)(A), a type of coal is the primary feedstock only if at all times more than 50 percent of the cumulative total fuel input (coal and any other fuel input) used in normal plant operations (as defined in section 3.03(2) of this notice) of the project will consist of that type of coal.

(6) The estimated total cost of the project and the estimated total qualified investment in the eligible property that will be part of the project.

(7) The amount of the qualifying advanced coal project credit requested for the project. The amount requested must not exceed the maximum amount provided in section 4.02(2) of this notice.

(8) If the taxpayer is or will be requesting an amount of the qualifying gasification project credit under § 48B for the same project, a statement specifying the amount

June 25, 2007 1460 2007–26 I.R.B.

certification only if (A) the taxpayer has received all federal and state environmental authorizations or reviews necessary to commence construction of the project, and (B) the taxpayer, except in the case of a retrofit or repower of an existing generation unit, has purchased or entered into a binding contract for the purchase of the main steam turbine or turbines for the project, except that this contract may be contingent upon receipt of a certification under § 48A(d)(2). Section 48A(d)(2)(E) provides that a taxpayer that receives a certification has 5 years from the date of issuance of the certification to place the project in service and that the certification is void if the project is not placed in service by the end of that five-year period.

.02 Requirements for Certification . Within 2 years from the date that the Service accepts the taxpayer’s application for § 48A certification under section 4.02(10) of this notice, the taxpayer must submit to the Service documentation establishing that the requirements of § 48A(e)(2) are satisfied. See also sections 7.01 and 7.02 of this notice for other requirements that must be satisfied. The taxpayer should mark the package “SECTION 48A CERTIFICATION REQUIREMENTS” and send it to the appropriate address listed in section 5.04 of this notice or listed in later guidance published in the Internal Revenue Bulletin.

.03 Service’s Action on Certification . After receiving the material in section 6.02 of this notice, the Service will decide whether or not to certify the project and will notify the taxpayer, by letter, of that decision. If the Service certifies the project, the date of this letter is the date of issuance of the certification.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Internal Revenue Bulletin 2007-26

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.