SECTION 5. APPLICATIONS FOR

Internal Revenue Bulletin 2006-11 · 2026-10-03 edition · updated 2026-10-04 · United States

CERTIFICATIONS

.01 In General . An application for § 48B certification and a separate application for DOE certification must be submitted for each qualifying gasification project. If an application for DOE certification does not include all of the information required by section 5.02 of this notice and meet the requirements in sections 6.01 and 6.02 of this notice, the DOE may decline to accept the application. If an application for § 48B certification does not include all of the information listed in section 5.03 of this notice and meet the requirements in sections 6.01 and 6.02 of this notice, the application will not be accepted by the Service.

.02 Information Required in the Appli- cation for DOE Certification . An application for DOE certification must include all of the information requested in Appendix B to this notice and all of the following:

(1) The name, address, and taxpayer identification number of the taxpayer;

(2) The name and telephone number of a contact person;

(3) The name and address (or other unique identifying designation) of the qualifying gasification project;

(4) A statement specifying the projected placed-in-service date of the qualifying gasification project;

(5) The estimated total cost of the project and the estimated total qualified

March 13, 2006 611 2006–11 I.R.B.

the construction of progress expenditure property (as defined in former § 46(d)(2)).

.02 In the case of self-constructed property (as defined in former § 46(d)(5)(A)), former § 46(d)(3)(A) defined qualified progress expenditures to mean the amount that is properly chargeable (during the taxable year) to capital account with respect to that property. With respect to a qualifying gasification project that is self-constructed property, amounts paid or incurred are chargeable to capital account at the time and to the extent they are properly includible in computing basis under the taxpayer’s method of accounting (for example, after applying the requirements of § 461, including the economic performance requirement of § 461(h)).

.03 To claim the qualifying gasification project credit on the qualified progress expenditures paid or incurred by a taxpayer during the taxable year for construction of a qualifying gasification project, the taxpayer must make an election under the rules set forth in § 1.46–5(o) of the Income Tax Regulations. The taxpayer may not make the qualified progress expenditures election for a qualifying gasification project until the taxpayer has received an acceptance letter for the project under section 4.02(9) of this notice.

.04 If a taxpayer makes the qualified progress expenditures election pursuant to section 8.03 of this notice, rules similar to the recapture rules in § 50(a)(2)(A)-(D) apply. In addition to the cessation events listed in § 50(a)(2)(A), examples of other events that will cause the project to cease being a qualifying gasification project are:

(1) Failure to place the project in service within 7 years from the date of the acceptance letter under section 4.02(9) of this notice; or

(2) In the case of a project that was entitled to priority for carbon capture capability, failure to provide that priority benefit on the date the project is placed in service.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Internal Revenue Bulletin 2006-11

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.