.01 Section 103(a) provides that, except as provided in § 103(b), gross income does not include interest on any state or local bond. Section 103(b)(1) provides that § 103(a) shall not apply to any private activity bond that is not a qualified
Renewable Electricity Production Credit, Publication of Inflation Adjustment Factor and Reference Prices for Calendar Year 2003
Notice 2003–29
This notice publishes the inflation adjustment factor and reference prices for calendar year 2003 for the renewable electricity production credit under § 45(a) of the Internal Revenue Code. The 2003 inflation adjustment factor and reference prices are used in determining the availability of the credit. The 2003 inflation adjustment factor and reference prices apply to calendar year 2003 sales of kilowatt-hours of electricity produced in the United States or a possession thereof from qualified energy resources.
BACKGROUND
Section 45(a) provides that the renewable electricity production credit for any tax year is an amount equal to the product of 1.5 cents multiplied by the kilowatt-hours of specified electricity produced by the taxpayer and sold to an unrelated person during the tax year. This electricity must be produced from qualified energy resources and at a qualified facility during the 10year period beginning on the date the facility was originally placed in service.
Section 45(b)(1) provides that the amount of the credit determined under § 45(a) is reduced by an amount that bears the same ratio to the amount of the credit as (A) the amount by which the reference price for the calendar year in which the sale occurs exceeds 8 cents bears to (B) 3 cents. Under § 45(b)(2), the 1.5 cents in § 45(a) and the 8 cents in § 45(b)(1) are each adjusted by multiplying the amount by the inflation adjustment factor for the calendar year in which the sale occurs.
Section 45(c)(1) defines qualified energy resources as wind, closed-loop biomass, and poultry waste. Section 45(c)(3) defines a qualified facility as any facility owned by the taxpayer that originally is placed in service after December 31, 1993 (in the case of a facility using wind to produce electricity), December 31, 1992 (in the case of a facility using closed-loop biomass to produce electricity), or Decem
ber 31, 1999 (in the case of a facility using poultry waste to produce electricity), and before January 1, 2004. See § 45(d)(7) for rules relating to the inapplicability of the credit to electricity sold to utilities under certain contracts.
Section 45(d)(2)(A) requires the Secretary to determine and publish in the Federal Register each calendar year the inflation adjustment factor and the reference prices for the calendar year. The inflation adjustment factor and the reference prices for the 2003 calendar year were published in the Federal Register on April 17, 2003, (68 Fed. Reg. 19073).
Section 45(d)(2)(B) defines the inflation adjustment factor for a calendar year as the fraction the numerator of which is the GDP implicit price deflator for the preceding calendar year and the denominator of which is the GDP implicit price deflator for the calendar year 1992. The term “GDP implicit price deflator” means the most recent revision of the implicit price deflator for the gross domestic product as computed and published by the Department of Commerce before March 15 of the calendar year.
Section 45(d)(2)(C) provides that the reference price is the Secretary’s determination of the annual average contract price per kilowatt hour of electricity generated from the same qualified energy resource and sold in the previous year in the United States. Only contracts entered into after December 31, 1989, are taken into account.
INFLATION ADJUSTMENT FACTOR AND REFERENCE PRICES
The inflation adjustment factor for calendar year 2003 is 1.2048. The reference prices for calendar year 2003 are 4.85 cents per kilowatt-hour for facilities producing electricity from wind energy resources and 0 cents per kilowatt-hour for facilities producing electricity from closed-loop biomass and poultry waste energy resources.
PHASE-OUT CALCULATION
Because the 2003 reference prices for electricity produced from wind, closedloop biomass, and poultry waste energy resources do not exceed 8 cents per kilowatt hour multiplied by the inflation adjustment factor, the phaseout of the credit pro
2003–20 I.R.B. 917 May 19, 2003
.02 When computing the housing cost/ income ratio under § 143(f)(5), issuers of qualified mortgage bonds and mortgage credit certificates must use the area median gross income figures released by HUD on February 20, 2003. See § 2.06 of this revenue procedure.