SECTION 3. APPROVAL FOR

Internal Revenue Bulletin 2000-42 · 2026-10-03 edition · updated 2026-10-04 · United States

SPECIFIED CHANGES

Subject to the applicability restrictions of section 6 and to the individual conditions under each method below, approval is granted for a change to one of the following funding methods. The development of the normal cost is described for each of the funding methods provided in subsections .01, through .09. For funding methods that directly calculate an accrued liability, within the meaning of Rev. Rul. 81–13, 1981–1 C.B. 229, the development of the accrued liability is also described.

.01 Approval 1. Approval is granted for a change in funding method to the unit credit funding method described below.

(1) This approval does not apply if the plan is a cash balance plan. For this purpose, a cash balance plan is a defined benefit plan that defines any portion of an employee’s benefits by reference to the employee’s hypothetical account, where such hypothetical account is determined by reference to hypothetical allocations and hypothetical earnings that are designed to mimic the actual allocations of contributions and earnings to an employee’s account that would occur under a defined contribution plan.

(2) Under this method, the normal cost is the sum of the individual normal costs for all active participants. An individual normal cost is the sum of the normal costs for the various benefits valued using the method. The normal cost for each benefit is the present value of the portion of the projected benefit at each expected separation date that is allocated to the current plan year as set forth in paragraphs (5) and (6) below. For purposes of this approval, separation date includes any date of benefit commencement, if earlier.

(3) The accrued liability under the method is the sum of the individual accrued liabilities for each participant. An individual’s accrued liability is the sum of the accrued liabilities for the various benefits valued using the method. The accrued liability for each benefit is the present value of the portion of the projected benefit at each expected separation date that is allocated to prior plan years as set forth in paragraphs (4), (5), and (6) below.

(4) For a participant other than an active participant, or for a beneficiary, the projected benefit is the accrued retirement benefit, or other plan benefit, under the

terms of the plan and the projected benefit is allocated to prior plan years.

(5) For an active participant, when valuing all benefits other than ancillary benefits that are not directly related to the accrued retirement benefit, the projected benefit related to a particular separation date is the benefit determined for the participant under the plan’s benefit formula(s) calculated using the projected compensation and the projection, under respective assumptions, of any other components that would be used in the calculation of the benefit on the expected separation date. The projected benefit at each expected separation date is allocated to the years of credited service as follows.

(a) The portion of the projected benefit allocated to the current plan year is determined as

(i) the benefit that would be determined for the participant under the plan’s benefit formula(s) calculated using the projected compensation, if applicable, and the projection, under respective assumptions, of any other components that would be used in the calculation of the benefit on the expected separation date, except taking into account only credited service through the end of the current plan year, minus

(ii) the benefit that would be determined for the participant under the plan’s benefit formula(s) calculated using the projected compensation, if applicable, and the projection, under respective assumptions, of any other components that would be used in the calculation of the benefit on the expected separation date, except taking into account only credited service through the beginning of the current plan year.

(b) The portion of the projected benefit allocated to prior plan years is the benefit determined for the participant under the plan’s benefit formulas calculated using the projected compensation, if applicable, and the projection, under respective assumptions, of any other components that would be used in the calculation of the benefit on the expected separation date, except taking into account only credited service through the beginning of the current plan year (i.e., the amount in subparagraph (a)(ii) above).

(c) Notwithstanding that the alloca

2000–42 I.R.B. 359 October 16, 2000

tions in subparagraphs (a) and (b) only take into account credited service as of the beginning and end of the plan year, if a participant is expected to satisfy an eligibility requirement for a particular benefit that is being valued (e.g., subsidized early retirement benefit) as of an expected separation date, the amounts in subparagraphs (a) and (b), and in paragraph (6) below, must be determined as if the employee has satisfied the eligibility requirement.

(d) The portion of the projected benefit allocated to prior plan years may not be less than the participant’s actual accrued benefit as of the beginning of the current plan year. In addition, the benefit determined as of the end of the current plan year in subparagraph (a)(i) above may not be less than the participant’s estimated accrued benefit as of the end of the current plan year.

(6) For active participants, when valuing ancillary benefits that are not directly related to the accrued retirement benefit, the projected benefit related to a particular

separation date is the benefit determined for the participant under the plan’s benefit formula(s) calculated using the projected compensation and the projection, under respective assumptions, of any other components that would be used in the calculation of the benefit on the expected separation date. The portion of the projected benefit allocated to the current plan year is the projected benefit at the expected separation date divided by the number of years of service the participant will have at such date. The portion of such projected benefit allocated to prior years of service is the projected benefit multiplied by a fraction, the numerator of which is the number of years of service at the beginning of the plan year, and the denominator of which is the number of years of service the participant will have at the expected separation date.

(7) The unfunded liability equals the total accrued liability less the actuarial value of plan assets. All present values are determined as of the valuation date.

(8) The following examples illustrate the application of the method.

(a) Example 1. The retirement benefit under the terms of a plan is equal to 1.3% of high 1-year compensation per year of service, but not less than the top-heavy minimum of 2% of high 5-year average compensation for each year the plan is top-heavy (not exceeding 20%), as required under § 416(c). Compensation under the plan is limited to $100,000. The plan has been top-heavy only for the last 7 years. Employee E has 10 years of service at the beginning of the current plan year. E’s compensation for that year is $30,000. The compensation is assumed to increase at the rate of 5% compounded yearly. The particular benefit being valued is the early retirement benefit anticipated to commence at the expected separation date 7 years in the future (i.e., after completion of 17 years of service). At this separation date, the employee will be eligible for early retirement, and will have projected compensation of $40,202, and projected high 5-year average compensation of $36,552. The allocated benefits determined for Employee E at the beginning and end of the plan year, and on the separation date, are shown in the table below.

Determined As of the

Allocated Benefit Beginning of Determined Under Plan Plan Year End of Plan Year Separation Date

(1) 1.3% Benefit Formula $5,226 1 $5,749 1 $8,885 3

(2) Top-Heavy Formula $5,117 2 $5,848 2 $7,310 3

(3) Allocated Benefit (greater of (1) and (2)) $5,226 $5,848 $8,885

FOOTNOTES

1$5,226 = $40,202 x 1.3% x 10; $5,749 = $40,202 x 1.3% x 11 2$5,117 = $36,552 x 2.0% x 7; $5,848 = $36,552 x 2.0% x 8 3$8,885 = $40,202 x 1.3% x 17; $7,310 = $36,552 x 2.0% x 10

The benefit allocated to the current year is $622 ($5,848- $5,226), and the benefit allocated to prior years is $5,226. In this case, the projected benefit at the separation date is based on the 1.3% benefit formula, and the current year’s benefit allocation of the projected benefit results in an amount which is based on the 1.3% benefit formula at the beginning of the year and on the top-heavy formula at the end of the year.

(b) Example 2: Plan B is an accumulation plan within the meaning of § 1.401(a)(4)–12. The benefit formula under Plan B for each plan year is 1% of compensation for such year. The sum of the amounts for each of the years constitutes an employee’s benefit. The accrued benefit at any date under Plan B is the benefit payable at normal retirement age for the years of service to date. Employee F has 3 years of service at the beginning of the year. The benefit being valued

is the normal retirement benefit payable at the normal retirement date (the date Employee F reaches normal retirement age). At normal retirement age, Employee F will have 20 years of service. Compensation is assumed to increase at a rate of 5% per year. Employee F’s compensation was $28,665, $27,170, and $26,000 for the prior year, the second prior year, and the third prior year, respectively. For valuation purposes, Employee F’s compensation for the current year is assumed to be $30,098. During the preceding plan year, Plan B was amended effective on the first day of the current plan year to provide that with respect to all prior plan years, the normal retirement benefit is updated to the greater of the benefit actually accumulated as of the beginning of the current plan year or 1% of the preceding year’s compensation multiplied by the number of years of service prior to the beginning of the current plan year.

The benefit determined for Employee F, taking into account only credited service through the beginning of the current plan year under the plan’s benefit formula is $860 (the greater of (a) $818 ((1% x $26,000) + (1% x $27,170) + (1% x $28,665)), or (b) $860 (1% x $28,665 x 3)). Taking the amendment into account, the projected benefit payable at normal retirement age is $8,637 ($860 + (1% x $30,098 x 25.84), where 25.84 is the accumulation of $1 payable at the end of the year for 17 years determined at 5% interest). For purposes of allocating the projected benefit, changes in compensation assumed for later plan years are not taken into account in accordance with the plan’s benefit formula. The benefit allocated to the current plan year is $301 ((860 + (1% x $30,098)) - 860).

.02 Approval 2. Approval is granted for a change in funding method to the

October 16, 2000 360 2000–42 I.R.B.

level percent of compensation aggregate funding method described below.

(1) This approval applies only to plans which provide for compensation-related benefits.

(2) Under this method, the normal cost is calculated in the aggregate as the normal cost accrual rate multiplied by the total compensation of all active participants.

(a) The normal cost accrual rate is (i) the total present value of future benefits of all participants and beneficiaries less adjusted assets, divided by

(ii) the total, for all active participants, of the present value of the compensation expected to be paid to each participant for each year of the participant’s anticipated future service, determined as of the participant’s attained age.

(b) For this purpose, the adjusted assets are equal to

(i) the actuarial value of the assets, plus

(ii) the sum of the outstanding balances of the amortization bases established on account of funding waivers under § 412(b)(2)(C), switchback to the regular funding standard under § 412(b)(2)(D), use of the shortfall method under § 1.412(c)(1)–2, and the transition under § 1.412(c)(3)–2(d), minus

(iii) the credit balance (or plus the funding deficiency), if any, in the funding standard account.

.03 Approval 3. Approval is granted for a change in funding method to the level dollar aggregate funding method described below.

(1) Under this method, the normal cost is calculated in the aggregate as the normal cost per active participant multiplied by the number of active participants.

(a) The normal cost per active participant is

(i) the total present value of future benefits of all participants and beneficiaries, less adjusted assets, divided by

(ii) the total, for all active participants, of the present value of an annuity of $1 per year for every year of a participant’s anticipated future service, determined as of the participant’s attained age.

(b) For this purpose, the adjusted assets are equal to

(i) the actuarial value of the assets, plus

(ii) the sum of the outstanding bal

ances of the amortization bases established on account of funding waivers under § 412(b)(2)(C), switchback to the regular funding standard under § 412(b)(2)(D), use of the shortfall method under § 1.412(c)(1)–2 of the regulations, and the transition under § 1.412(c)(3)–2(d), minus

(iii) the credit balance (or plus the funding deficiency), if any, in the funding standard account.

.04 Approval 4. Approval is granted for a change in funding method to the level percent of compensation individual aggregate funding method described below.

(1) This approval applies only for plans which provide for compensation-related benefits.

(2) This approval does not apply if the actuarial value of assets is less than the present value of benefits for inactive participants and beneficiaries, or if the amount in paragraph (3)(b)(i) is less than zero.

(3) Under this method, the normal cost is the sum of the individual normal costs for each active participant.

(a) The normal cost for an active participant is

(i) the present value of future benefits for the participant, less allocated adjusted assets, divided by

(ii) the ratio of (A) the present value of the compensation expected to be paid to the participant for each year of the participant’s anticipated future service, determined as of the participant’s attained age, to (B) the participant’s current compensation.

(b) For this purpose, allocated adjusted assets are calculated as follows:

(i) First, the adjusted value of the assets is equal to:

(A) the actuarial value of the assets, plus

(B) the sum of the outstanding balances of the amortization bases established on account of funding waivers under § 412(b)(2)(C), switchback to the regular funding standard under § 412 (b)(2)(D), use of the shortfall method under § 1.412(c)(1)–2, and the transition under § 1.412(c)(3)–2(d), minus

(C) the credit balance (or plus the funding deficiency), if any, in the funding standard account, minus

(D) any liabilities retained by the plan for any inactive participant or benefi

ciary.

(C) the credit balance (or plus the fund

(ii) In the first year the method is used, the allocated adjusted value of the assets for an active participant is calculated by allocating the adjusted value of the assets in proportion to the present value of accrued benefits, or in proportion to the accrued liability determined under one of the immediate gain funding methods described in subsection .01 or .08.

(iii) For years subsequent to the first year in which the method is used, the adjusted value of the assets is allocated to an active participant in the proportion that

(A) the sum of the allocated adjusted assets and calculated normal cost as of the valuation date for the prior year for that active participant bears to

(B) the total of the amounts in (A) for all active participants.

.05 Approval 5. Approval is granted for a change in funding method to the level dollar individual aggregate funding method described below.

(1) This approval does not apply if the actuarial value of assets is less than the present value of benefits of inactive participants and beneficiaries, or if the amount in paragraph (2)(b)(i) is less than zero.

(2) Under this method, the normal cost is the sum of the individual normal costs for each active participant.

(a) The normal cost for an active participant is

(i) the present value of future benefits for the participant less allocated adjusted assets, divided by

(ii) the present value of an annuity of $1 per year for every year of the participant’s anticipated future service, determined as of the participant’s attained age.

(b) For this purpose, allocated adjusted assets are calculated as follows:

(i) First, the adjusted value of the assets is equal to:

(A) the actuarial value of the assets, plus (B) the sum of the outstanding balances of the amortization bases established on account of funding waivers under § 412(b)(2)(C), switchback to the regular funding standard under § 412(b)(2)(D), use of the shortfall method under § 1.412(c)(1)-2, and the transition under

§ 1.412(c)(3)-2(d), minus

2000–42 I.R.B. 361 October 16, 2000

ing deficiency), if any, in the funding standard account, minus

(D) any liabilities retained by the plan for any inactive participant or beneficiary.

(ii) In the first year the method is used, allocated adjusted assets for an active participant is calculated by allocating the adjusted value of the assets in proportion to the present value of accrued benefits, or in proportion to the accrued liability determined under one of the immediate gain funding methods described in subsection .01 or .09.

(iii) For years subsequent to the first year in which the method is used, the adjusted value of the assets is allocated to an active participant in the proportion that

(A) the sum of the allocated adjusted assets and calculated normal cost as of the valuation date for the prior year for that active participant bears to

(B) the total of the amounts in (A) for all active participants.

.06 Approval 6. Approval is granted for a change in funding method to the level percent of compensation frozen initial liability funding method described below.

(1) This approval applies only for plans which provide for compensation-related benefits.

(2) Under this method, the normal cost is calculated in the aggregate, for every year the method is used including the first, as the normal cost accrual rate multiplied by the total compensation of all active participants.

(a) The normal cost accrual rate is (i) the total present value of future benefits of all participants and beneficiaries less the sum of the actuarial value of assets and the unfunded liability, divided by

(ii) the total, for all active participants, of the present value of the compensation expected to be paid to each participant for each year of the participant’s anticipated future service, determined as of the participant’s attained age.

(b) As of the date of change, the unfunded liability is set equal to the unfunded accrued liability determined under the level percentage of compensation individual entry age normal funding method described in subsection .08.

(c) For years subsequent to the plan year of the change in method, the unfunded liability equals

(i) the unfunded liability for the prior

plan year, plus the normal cost for the prior plan year (the result adjusted with appropriate interest to the valuation date), minus the actual contribution(s) for the prior plan year (adjusted with appropriate interest to the valuation date), and

(ii) the unfunded liability is further increased (or decreased) by the amount of any base established on the valuation date which results from a plan amendment or a change in assumptions. Such bases are amortized over the period(s) described in § 412(b)(2)(B) or § 412(b)(3)(B), as applicable.

.07 Approval 7. Approval is granted for a change in funding method to the level dollar frozen initial liability funding method described below.

(1) Under this method, the normal cost is calculated in the aggregate, for every year the method is used including the first, as the normal cost per active participant multiplied by the number of active participants.

(a) The normal cost per active participant is

(i) the total present value of future benefits of all participants and beneficiaries less the sum of the actuarial value of assets and the unfunded liability, divided by

(ii) the total, for all active participants, of the present value of an annuity of $1 per year for every year of a participant’s anticipated future service, determined as of the participant’s attained age.

(b) As of the date of change, the unfunded liability is set equal to the unfunded accrued liability determined under the level dollar individual entry age normal funding method described in subsection .09.

(c) For years subsequent to the plan year of the change in method, the unfunded liability equals

(i) the unfunded liability for the prior plan year, plus the normal cost for the prior plan year (the result adjusted with appropriate interest to the valuation date), minus the actual contribution(s) for the prior plan year (adjusted with appropriate interest to the valuation date), and

(ii) the unfunded liability is further increased (or decreased) by the amount of any base established on the valuation date which results from a plan amendment or a change in assumptions. Such bases are amortized over the period(s) described in § 412(b)(2)(B) or § 412(b)(3)(B), as applicable.

.08 Approval 8. Approval is granted for a change in funding method to the level percent of compensation individual entry age normal funding method described below.

(1) This approval does not apply if the alternative minimum funding standard account is used at any time within the 5-year period commencing with the first day of the plan year for which the change is made.

(2) This approval applies only for plans which provide for compensation-related benefits.

(3) Under this method, the normal cost is the sum of the individual normal costs for all active participants. For an active participant, the normal cost is the participant’s normal cost accrual rate, multiplied by the participant’s current compensation.

(a) The normal cost accrual rate equals (i) the present value of future benefits for the participant, determined as of the participant’s entry age, divided by

(ii) the present value of the compensation expected to be paid to the participant for each year of the participant’s anticipated future service, determined as of the participant’s entry age.

(b) In calculating the present value of future compensation, the salary scale must be applied both retrospectively and prospectively to estimate compensation in years prior to and subsequent to the valuation year based on the compensation used for the valuation.

(c) The accrued liability is the sum of the individual accrued liabilities for all participants and beneficiaries. A participant’s accrued liability equals the present value, at the participant’s attained age, of future benefits less, the present value at the participant’s attained age of the individual normal costs payable in the future. A beneficiary’s accrued liability equals the present value, at the beneficiary’s attained age, of future benefits. The unfunded accrued liability equals the total accrued liability less the actuarial value of assets.

(d) Under this method, the entry age used for each active participant is the participant’s age at the time he or she would have commenced participation if the plan had always been in existence under current terms, or the age as of which he or she first earns service credits for purposes of benefit accrual under the current terms

October 16, 2000 362 2000–42 I.R.B.

of the plan. Alternatively, the entry age may be determined as the age at the valuation date next following the time described in the preceding sentence.

.09 Approval 9. Approval is granted for a change in funding method to the level dollar individual entry age normal funding method described below.

(1) This approval does not apply if the alternative minimum funding standard account is used at any time within the 5-year period commencing with the first day of the plan year for which the change is made.

(2) Under this method, the normal cost is the sum of the individual normal costs for all active participants.

(a) For an active participant, the individual normal cost equals

(i) the present value of future benefits for the participant, determined as of the participant’s entry age, divided by

(ii) the present value of an annuity of $1 per year for every year of the participant’s anticipated future service, determined as of the participant’s entry age.

(b) The accrued liability is the sum of the individual accrued liabilities for all participants and beneficiaries. A participant’s accrued liability equals the present value, at the participant’s attained age, of future benefits, less the present value at the participant’s attained age of the individual normal costs payable in the future. A beneficiary’s accrued liability equals the present value, at the beneficiary’s attained age, of future benefits. The unfunded accrued liability equals the total accrued liability less the actuarial value of the plan assets.

(c) Under this method, entry age used for each active participant is the participant’s age at the time he or she would have commenced participation if the plan had always been in existence under current terms, or the age as of which he or she first earns service credits for purposes of benefit accrual under the current terms of the plan. Alternatively, the entry age may be determined as the age at the valuation date next following the time described in the preceding sentence.

if the prior method for valuing ancillary benefits had been the one-year term method. For this purpose, ancillary benefits are defined in § 1.412(c)(3)–1(f)(2) and include pre-retirement death and disability benefits.

.15 Approval 15. Approval is granted for a change in asset valuation method to the smoothed market value (without phase-in) described below, or to any alternative formulation that is algebraically equivalent to this smoothed value. The asset value determined under the method will be adjusted to be no greater than 120% and no less than 80% of the fair market value defined in § 1.412(c(2)–1(c).

Under this method, the actuarial value of assets is equal to the market value of assets less a decreasing fraction (i.e., (n-1)/n, (n-2)/n, etc., where n equals the number of years in the smoothing period) of the gain or loss for each of the preceding n-1 years. The stated smoothing period may not exceed five (5) plan years.

Under this method, a gain or loss for a year is determined by calculating the difference between the expected value of the assets for the year and the market value of the assets at the valuation date. The expected value of the assets for the year is the market value of the assets at the valuation date for the prior year brought forward with interest at the valuation interest rate to the valuation date for the current year plus contributions minus disbursements (i.e., benefits and expenses), all adjusted with interest at the valuation rate to the valuation date for the current year. If the expected value is less than the market value, the difference is a gain. Conversely, if the expected value is greater than the market value, the difference is a loss.

For example, if the smoothing period is five years, the actuarial value of the assets will be the market value of the plan’s assets, with gains subtracted or losses added at the rates described as follows: (i) 4/5 of the prior year’s gain or loss (ii) 3/5 of the second preceding year’s gain or loss (iii) 2/5 of the third preceding year’s gain or loss (iv) 1/5 of the fourth preceding year’s gain or loss

.16 Approval 16. Approval is granted for a change in asset valuation method to

.10 Approval 10. Approval is granted for a change in asset valuation method to fair market value as defined in § 1.412(c)(2)–1(c).

the average value as defined in § 1.412(c)(2)–1(b)(7) (which does not have a phase-in), or to any alternative formulation that is algebraically equivalent to this average value. The asset value determined under the method will be adjusted to be no greater than 120% and no less than 80% of the fair market value defined in § 1.412(c)(2)–1(c).

For example, under § 1.412(c)(2)–1(b)(7), if the averaging period is five years, the average value is based on the fair market value of assets in the current year and the adjusted values of assets for the prior four years as provided in § 1.412(c)(2)–1(b)(8). An alternative formulation which is algebraically equivalent to this method is one in which the average value of assets is equal to the fair market value on the valuation date, minus decreasing fractions (4/5, 3/5, 2/5 and 1/5, in this example) of the appreciation and depreciation of the assets in each of the four preceding years. The stated averaging period may not exceed five (5) plan years.

.12 Approval 12. Approval is granted for a change in asset valuation method to the average value (as defined in § 1.412(c)(2)–1(b)(7)), modified to use the phase-in described below, or to any alternative formulation that is algebraically equivalent to this average value. The asset value determined under the method will be adjusted to be no greater than 120% and no less than 80% of the fair market value defined in § 1.412(c)(2)–1(c).

In the first year this method is used, the average value is calculated as in Approval 11, except that the adjusted values for all but the most recent prior year are replaced by the adjusted value for the most recent prior year. In the second year, the average is calculated as in Approval 11, except that the values for all but the most recent two prior years are replaced by the adjusted value for the second most recent prior year. This process is continued until values for all prior years in the averaging period are phased in. The stated averaging period may not exceed five (5) plan years.

.13 Approval 13. Approval is granted for a change in the valuation date to the day that is the first day of the plan year.

.14 Approval 14. Approval is granted to change the funding method used for valuing ancillary benefits to the funding method used to value retirement benefits,

.11 Approval 11. Approval is granted for a change in asset valuation method to

2000–42 I.R.B. 363 October 16, 2000

the smoothed market value (with phasein) described below, or to any alternative formulation that is algebraically equivalent to this smoothed value. The asset value determined under the method will be adjusted to be no greater than 120% and no less than 80% of the fair market value defined in § 1.412(c)(2)–1(c).

In the first year this method is used the actuarial value of assets is equal to the market value as of the valuation date. In each subsequent year, the smoothed value is calculated in the same manner as in Approval 15, except that the only gains or losses recognized are those occurring in the year of the change and in later years. The stated smoothing period may not exceed five (5) plan years.

.17 Approval 17. Approval is granted for a change in asset valuation method to the average value (as defined in § 1.412(c)(2)–1(b)(7)), modified to use the alternative phase-in as described below, or to any alternative formulation that is algebraically equivalent to this average. The asset value determined under the method will be adjusted to be no greater than 120% and no less than 80% of the fair market value defined in § 1.412(c)(2)–1(c).

In the first year this method is used, the actuarial value of assets is equal to the market value. In the second year, the average value is calculated in the same manner as in Approval 11, except that the averaging period is two years. In the third year, the average value is calculated in the same manner as in Approval 11, except that the averaging period is three years. This process continues until the stated averaging period (not to exceed five years) is reached.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Internal Revenue Bulletin 2000-42

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.