SECTION 13. ADMINISTRATIVE
Internal Revenue Bulletin 1997-23 · 2026-10-03 edition · updated 2026-10-04 · United States
REVIEW PROCESS FOR DENIAL OF PARTICIPATION IN THE 1040NR PROGRAM
.01 An applicant that has been denied participation in the 1040NR Program has the right to an administrative review. During the administrative review process, the denial of participation remains in effect.
.02 In response to the submission of a Form MAR–8980, the Service will either (1) accept an applicant into the 1040NR Program, or (2) issue a proposed letter of denial that explains to the applicant why the Service proposes to reject the application to participate in the 1040NR Program.
.03 An applicant that receives a proposed letter of denial may mail or deliver, within 30 calendar days of the date of the proposed letter of denial, a written response to the Project Office. The applicant’s response must address the Project Office’s explanation for proposing the denial to participate.
.04 Upon receipt of an applicant’s written response, the Project Office will reconsider its proposed letter of denial. The Project Office may (1) withdraw its
proposed letter of denial and admit the applicant into the 1040NR Program, or (2) finalize its proposed letter of denial and issue it to the applicant.
.05 If an applicant receives a final letter from the Project Office that denies the applicant participation in the 1040NR Program, the applicant is entitled to an appeal, in writing, to the Director of Practice.
.06 The appeal must be mailed or delivered to the Project Office within 30 calendar days of the date of the denial letter. An applicant’s written appeal must contain a detailed explanation, with supporting documentation, of why the denial should be reversed. In addition, the applicant must include a copy of the applicant’s Form MAR–8980 and a copy of the denial letter.
.07 The Project Office, upon receipt of a written appeal to the Director of Practice, will forward to the Director of Practice its file on the applicant and the materials described in section 13.06 that the applicant has submitted to the Project Office. The Project Office will forward these materials to the Director of Practice within 15 calendar days of receipt of the applicant’s written appeal.
.08 Failure to respond within the 30-day periods described in sections 13.03 and 13.06 of this revenue procedure irrevocably terminates an applicant’s right to an administrative review or appeal.