§ 58.75 Permissible bases for objections.
24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-performed and responsible-entity NEPA procedures) · 2026 edition · updated 2026-07-29 · United States
HUD (or the State), will consider objections claiming a responsible entity's noncompliance with this part based only on any of the following grounds:
(a) The certification was not in fact executed by the responsible entity's Certifying Officer.
(b) The responsible entity has failed to make one of the two findings pursuant to § 58.40 or to make the written determination required by § 58.35, § 58.47 or § 58.53 for the project, as applicable.
(c) The responsible entity has omitted one or more of the steps set forth at subpart E of this part for the preparation, publication and completion of an EA.
(d) The responsible entity has omitted one or more of the steps set forth at subparts F and G of this part for the conduct, preparation, publication and completion of an EIS.
(e) The recipient or other participants in the development process have committed funds, incurred costs or undertaken activities not authorized by this part before release of funds and approval of the environmental certification by HUD (or the state).
(f) Another Federal agency acting pursuant to 40 CFR part 1504 has submitted a written finding that the project is unsatisfactory from the standpoint of environmental quality.
[61 FR 19122, Apr. 30, 1996, as amended at 68 FR 56130, Sept. 29, 2003]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — 24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-performed and responsible-entity NEPA procedures)
- 24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-perfor…
- PART 50—PROTECTION AND ENHANCEMENT OF ENVIRONMENTAL QUALITY
-
▸ PART 58—ENVIRONMENTAL REVIEW PROCEDURES FOR ENTITIES ASSUMING …
Overview- Subpart A—Purpose, Legal Authority, Federal Laws and Authorities
- Subpart B—General Policy: Responsibilities of Responsible Enti…
- Subpart C—General Policy: Environmental Review Procedures
- Subpart D—Environmental Review Process: Documentation, Range o…
- Subpart E—Environmental Review Process: Environmental Assessme…
- Subpart F—Environmental Review Process: Environmental Impact S…
- Subpart G—Environmental Review Process: Procedures for Draft, …
-
▸ Subpart H—Release of Funds for Particular Projects
Overview- § 58.70 Notice of intent to request release of funds.
- § 58.71 Request for release of funds and certification.
- § 58.72 HUD or State actions on RROFs and certifications.
- § 58.73 Objections to release of funds.
- § 58.74 Time for objecting.
- § 58.75 Permissible bases for objections.
- § 58.76 Procedure for objections.
- § 58.77 Effect of approval of certification.