§ 58.46 Time delays for exceptional circumstances.

24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-performed and responsible-entity NEPA procedures) · 2026 edition · updated 2026-07-29 · United States

The responsible entity must make the FONSI available for public comments for 30 days before the recipient files the RROF when:

(a) There is a considerable interest or controversy concerning the project;

(b) The proposed project is similar to other projects that normally require the preparation of an EIS; or

(c) The project is unique and without precedent.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — 24 C.F.R. Parts 50 & 58 — HUD Environmental Review (HUD-performed and responsible-entity NEPA procedures)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.