Chapter 2›Article 27 — EXTENSIONS OF TIME
Article 27 — EXTENSIONS OF TIME
Torrance Zoning Code · 2026-06 edition · updated 2026-09-23 · Torrance
92.27.1 EXTENSIONS; GRANTING WITHOUT HEARING.¶
a) Whenever a waiver, conditional use permit, variance or other planning permit, exclusive of subdivisions or lot splits, is granted the Planning Director may extend such period of time for commencing the use one (1) or more times subject to the following criteria:
The extension of time will not affect the rights of adjacent property owners or tenants or otherwise would constitute an adverse impact on them.
The extension of time will not result in a material change in the concept or execution of the project as approved by Council, a Commission or other body or official.
There is a hardship to the applicant if the extension of time is not granted.
The extension of time will not be contrary to any established planning or zoning policies of the Council, a Commission, body or official for the particular project under consideration as determined by a review of the minutes or other records of the original approval.
b) Whenever any such planning permit is granted without stating a specific period of time, such permit shall expire and become null and void if not exercised within one (1) year after the date the permit was originally granted unless a time extension is granted by the Planning Director.
c) A request for such extension of time may be granted before expiration of the period for which the relief was granted and no request for an extension of time pursuant to this Section shall be granted if the request is made after the expiration date of the original planning permit or term for performance of the condition or extension thereof.
d) These same time limits and procedures for extensions shall apply to compliance with conditions of approval of the above described permits.
e) Each week the Planning Director shall prepare or cause to be prepared a list of each such extension of time upon which he has made a determination, and he shall distribute a copy of said list to each Council member, the City Manager and to the Planning Commission. The lists shall be published in the minutes of the Planning Commission and a copy shall be posted on not less than two (2) bulletin boards within the City Hall which are easily accessible to the public.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — Torrance Zoning Code
- Chapter 1
▸Chapter 2
Overview- Article 1 — CONTROLLED ZONING
- Article 2 — USES GENERALLY Revised 4/25 Revised 10/25
- Article 3 — HEIGHT OF BUILDINGS
- Article 4 — MINIMUM LOT AND BUILDING SITE AREAS
- Article 5 — YARDS
- Article 6 — EXPOSED EXTERIOR WALLS
- Article 7 — SPECIAL SETBACK LINE.
- Article 8 — ACCESSORY BUILDINGS
- Article 9 — ZONING APPLIED TO ANNEXED AREAS
- Article 10 — SPLITTING LOTS
- Article 11 — ACCESSIBILITY TO BUILDING SITE AND LIVING QUARTERS
- Article 12 — SIGNS
- Article 13 — FENCES, WALLS, RETAINING WALLS AND HEDGES
- Article 14 — AUTOMATIC REZONING OF SUBDIVIDED LAND
- Article 15 — GARAGE DOORS
- Article 16 — GARAGES FACING PUBLIC STREETS
- Article 17 — MOBILEHOMES AND MOBILEHOME PARKS
- Article 18 — HOME OCCUPATIONS
- Article 19 — UNAUTHORIZED SALE OF VEHICLES ON VACANT LOTS
- Article 20 — LIVING AREAS
- Article 21 — BUILDING DESIGN COMPATIBILITY
- Article 22 — NONCONFORMING USES, BUILDINGS OR STRUCTURES
- Article 23 — ENFORCEMENT
- Article 24 — REAPPLICATION AFTER DENIAL OR WITHDRAWAL
- Article 26 — RECORDING CONDITIONS ON USE OF LAND
▸Article 27 — EXTENSIONS OF TIME
- Article 28 — MODIFICATION OF CONDITIONS
- Article 29 — SUBDIVISION CONTROL
- Article 30 — DEVELOPMENT STANDARDS
- Article 32 — PROPERTY MAINTENANCE
- Article 33 — SPACING OF BLIGHT INDUCING ENTERPRISES
- Article 34 — AMENDMENT TO GENERAL PLAN
- Article 35 — NUISANCE ABATEMENT
- Article 36 — DEVELOPMENT PERMITS
- Article 37 — LARGE FAMILY DAY CARE PERMITS
- Article 38 — VACANT BUILDING AND LOT MAINTENANCE AND REGISTRAT…
- Article 39 — WIRELESS TELECOMMUNICATION FACILITIES
- Article 40 — UNATTENDED COLLECTION BOXES
- Article 41 — VIEW EQUITY
- Article 42 — GARAGE SALES
- Article 43 — SHORT TERM RENTALS
- Article 44 — SHARED MOBILITY DEVICES
- Chapter 3 — OFF STREET PARKING
- Chapter 4 — VARIANCES - WAIVERS
- Chapter 5 — CONDITIONAL USE PERMITS
- Chapter 6 — REZONING - PRECISE PLAN.
- Chapter 7 — OIL.
- Chapter 8 — HELICOPTERS
- Chapter 9 — SCHEDULE OF FEES
- Chapter 10 — TRIP REDUCTION AND TRAFFIC MANAGEMENT
- Chapter 11 — SIGNS Revised 4/25