Article II — Construction Inspection
Santa Cruz County Planning Code · 2026-07 edition · updated 2026-07-25 · Santa Cruz County
14.01.507. Superintendence. ¶
The contractor shall designate in writing, before starting work, an authorized representative who shall have complete authority to represent and act for the contractor. Said authorized representative or his agent shall be present at the site of the work at all times while the work is actually in progress. During periods when work is suspended, arrangements acceptable to the Director of Public Works shall be made for any emergency work which may be required. (Ord. 2093, 1975)
14.01.508. Access for inspection. ¶
The Director of Public Works shall at all times have access to the work site during construction and shall be furnished with every reasonable facility for ascertaining that the materials and workmanship are in accordance with the requirements and intentions of the approved improvement plans and work done and all materials furnished shall be subject to his inspection and approval. The inspection of the work or materials shall not relieve the contractor of any of his obligations to fulfill the work as prescribed. Work and materials not meeting such requirements may be rejected, notwithstanding that such work or materials have been previously inspected by the Director of Public Works. Any superintendent, foreman, laborer, or other person employed on the work by the contractor, who performs his work in an unsatisfactory manner, or who is disorderly, intemperate, or incompetent, shall, upon request of the Director of Public Works, be removed from the site immediately, and such person shall not again be employed on the job. (Ord. 2093, 1975)
14.01.509. Notification—Required inspections. ¶
The Director of Public Works shall make such inspections as he deems necessary and shall be notified 24 hours in advance of any required inspection. Minimum inspection requirements follow:
(A) The inspection of clearing and grubbing work before grading operations are started in any cut or fill area.
(B) The inspection and compaction testing of subgrade before the placing of sub-base, base, and surfacing.
(C) The inspection of storm drain and sewer pipe installation and backfill, including compaction testing.
(D) The inspection and compaction testing of sub-base and base prior to paving.
(E) The inspection of all penetration treatment, seal coat, and paving while the work is in progress.
(F) The inspection of concrete forms.
(G) The inspection of concrete while being placed.
(H) Final inspection.
Downloaded from https://ecode360.com/SA4770 on 2026-07-06
County of Santa Cruz, CA
SUBDIVISION REGULATIONS
14.01.509
14.01.511
- (I) Installation of residential street lighting. (Ord. 2093, 1975; Ord. 4126 § 2, 1991)
14.01.510. Agreement. ¶
The subdivider shall, concurrent with the acceptance of the final map, or parcel map where applicable, or prior to the start of construction, whichever is earlier, enter into an agreement with the County, agreeing to have the specified or required improvements completed within a specified time. In the case of a subdivision for which a final map is required, the agreement shall be executed by the subdivider and the Board. In the case of a subdivision for which a parcel map is required, the agreement shall be executed by the subdivider and the Director of Public Works for the Board. Standard agreement forms are available upon request from the County Surveyor.
If formal time extensions are considered to complete the improvements, such extensions will not be granted until all construction, inspection and materials testing charges, which have been accumulated as of that date, have been paid.
(Ord. 2093, 1975; Ord. 2196, 1975; Ord. 2213, 1975; Ord. 3242 § 2, 1982)
14.01.511. Security—Bonds—Deposits. ¶
(A) Except as provided in subsection (B) of this section, security shall be provided to ensure satisfactory completion of the required improvements and other associated costs and fees. Securities shall only be accepted in the form of one of the following:
(1) Bond or bonds by duly authorized corporate sureties acceptable to the County; or
(2) A deposit, either with the County or a responsible escrow agent or trust company, at the County's option, of money or negotiable bonds of kind approved for securing deposits of public monies; provided, that:
(a) Any such escrow is noncancelable and nonmodifiable without the County's prior written consent; or
(b) Any such deposit is specifically made for the benefit of the County with the County as named beneficiary; or
(3) An instrument of credit from an agency of the State, Federal, or local government when any agency of the State, Federal, or local government provides at least 20 percent of the financing for the portion of the act or agreement requiring security; or
(4) A letter of credit issued by a financial institution subject to regulation by the State or Federal government; or
(5) Any combination of the above, at the discretion of the Director of the Department of Public Works.
(B) To assure satisfactory completion of the improvements for a development by a California nonprofit corporation with public financing to develop new low and moderate income housing, securities shall only be accepted in the form permitted by Government Code Section 66499.
(C) The securities to be furnished are as follows:
Downloaded from https://ecode360.com/SA4770 on 2026-07-06
County of Santa Cruz, CA
SANTA CRUZ COUNTY CODE
14.01.511
14.01.513
(1) For "faithful performance," the amount of 100 percent of the cost of the improvements as determined by the subdivision engineer and accepted by the Director of Public Works, to guarantee faithful completion of the work; and
(2) For "materials and labor," the amount of 50 percent of the cost of improvements as determined by the subdivision engineer and accepted by the Director of Public Works, to guarantee payment to material men and laborers furnishing materials, equipment, or labor in connection with the subdivision improvements; and
(3) For "guarantee, warranty, and maintenance of work," the amount of 15 percent of the cost of improvements as determined by the subdivision engineer and accepted by the Director of Public Works, to guarantee and warrant the work for a minimum period of 12 months following the completion and acceptance thereof by the Board of Supervisors against any defective work or labor done, or defective materials furnished and to maintain such work to the satisfaction of the County for said period. In the event the subdivider fails to maintain, repair, replace or reconstruct the work to the satisfaction of the County, the security shall be obligated for the payment of all necessary costs and expenses that may be incurred or expended by the County of Santa Cruz in causing any or all repair, replacement, reconstruction, or maintenance of said work, which is discovered or may become necessary during said 12-month period.
(4) Such other securities as may be needed pursuant to SCCC § 14.01.208(B) (monumentation), 14.01.437(A) (taxes), and 14.01.506 (plan check and inspection fees).
(5) For subdivisions for which parcel maps are required, the securities to be supplied may be limited to subsections (A) and (B) of this section plus the security noted in SCCC § 14.01.506.
(Ord. 2196, 1975; Ord. 2213, 1975; Ord. 4073 § 1, 1990; Ord. 5034 § 1, 2009; Ord. 5069 § 1, 2010; Ord. 5394 § 1, 2022)
14.01.512. Grading improvements not permitted prior to recording the final map—Waiver. ¶
(A) No grading or improvement shall be permitted prior to recording of the final map unless, by a specific condition of the tentative map, this restriction is waived by the County. If the subdivider is thus permitted to grade or install improvements, he shall submit and obtain approval of grading and improvement plans and enter into an agreement with the County to guarantee completion of the work. Said agreement shall be backed by securities in accordance with SCCC § 14.01.511.
(B) Doing such work contrary to this section shall void the tentative map and constitute a violation of the Santa Cruz County Code.
(C) It shall be unlawful for any person whether as owner, principal, agent, or employee or otherwise to perform an action or allow a situation to continue that violates the provisions of this chapter or violates any permit conditions required pursuant to this chapter. All violations shall be punishable in accordance with the provisions of Chapter 19.01 SCCC except as otherwise specified in this chapter.
(Ord. 3436 § 2, 1983; Ord. 4496-C § 76, 1998)
Downloaded from https://ecode360.com/SA4770 on 2026-07-06
County of Santa Cruz, CA
SUBDIVISION REGULATIONS
14.01.513
14.01.513
14.01.513. Acquisition of property interests for off-site improvements. ¶
In the event a subdivider is required to construct or install off-site improvements on land in which neither the subdivider nor the County has sufficient title or interest, including an easement or license, at the time the tentative map is approved or the final or parcel map is filed with the County to permit the improvements to be made, the subdivider shall enter into an agreement with the County prior to the filing of the final map or parcel map to pay for the County's costs, including personnel salaries and benefits, legal fees and costs, and compensation to the landowner for acquiring an interest in the land which will permit the improvements to be made. The subdivider shall also post an appropriate cash security deposit with the County prior to filing of the final map or parcel map to be applied towards the County's costs for acquiring the off-site property interest.
Pursuant to Section 66462.5 of the Government Code, if the County fails to commence condemnation proceedings to acquire the off-site property interest within 120 days of the filing of the final map or parcel map, then the condition for construction of any off-site improvement which is dependent on the property acquisition shall be deemed to be waived. (Ord. 3648 § 1, 1985)
Downloaded from https://ecode360.com/SA4770 on 2026-07-06
County of Santa Cruz, CA
SUBDIVISION REGULATIONS
14.01.601
14.01.610
Get a plain-English answer with a citation back to this text.
Ask AI about this code