Earlier editions: 2026-09
Title C — CONSTRUCTION, DEVELOPMENT AND LAND USE›Chapter II — SINGLE BUILDING SITES›Article 3 — REQUIREMENTS
Santa Clara County Municipal Code Part 2 Improvements
Santa Clara County Municipal Code · 2026-10 edition · updated 2026-10-04 · Santa Clara County
Cite as: Santa Clara County Municipal Code Part 2 · Text as of 2026-10-04
Sec. C12-324. - Improvement requirements.¶
Improvement requirements shall be limited to those improvements which are directly related to the proposed development and consistent with similar improvements in the immediate area. When improvements are required, the provisions of Chapter 1 of the County of Santa Clara Subdivision Ordinance shall apply, and in no event shall improvement requirements exceed those provisions. In situations where a grading permit is required, the improvements may be incorporated in the grading plan and permit, at the discretion of the County Surveyor. The County Surveyor may defer street and drainage improvements or require stage improvements commensurate with the development pattern of the neighborhood and with traffic needs for safe and adequate access. The stage improvement design shall take into consideration the number of existing and potential building sites making allowance for future divisions of land. When the County Surveyor determines that the installation of the improvement should be deferred, he may require the property owner to enter into a agreement with the Board of Supervisors pertaining to such deferred improvements.
(Ord. No. NS-1203.35, § 5, 3-13-78)
Sec. C12-325. - Underground utilities.¶
The provisions of Chapter I, pertaining to underground utilities, shall apply to single building sites. Undergrounding generally shall be limited to on-site work, unless the off-site work can be coordinated with undergrounding to serve other properties in the immediate area.
(Ord. No. NS-1203.35, § 5, 3-13-78)
Sec. C12-326. - Legal access.¶
The applicant shall demonstrate that the property has legal access sufficient to meet County access and improvement requirements.
(Ord. No. NS-1203.35, § 5, 3-13-78)
Sec. C12-327. - Surveying and map requirements.¶
Field surveying may be required by the County Surveyor as necessary to determine topographic conditions and to locate easements and property lines. If a survey is performed which establishes points or lines of ownership, a record of survey conforming to the requirements of the Land Surveyor's Act, or a parcel map conforming to the requirements of Chapter I, shall be prepared and submitted for approval and recording.
(Ord. No. NS-1203.35, § 5, 3-13-78)