Skip to content

Earlier editions: 2026-09

Title C — CONSTRUCTION, DEVELOPMENT AND LAND USE›Chapter I — SUBDIVISIONS›Article 4 — REQUIREMENTS

Santa Clara County Municipal Code Part 9 Solar Access for Subdivision Development

Santa Clara County Municipal Code · 2026-10 edition · updated 2026-10-04 · Santa Clara County

Cite as: Santa Clara County Municipal Code Part 9 · Text as of 2026-10-04

Sec. C12-173. - Intent.

It is the intent of this part to implement and enforce the requirements of the California Solar Rights Act, that the design of all subdivisions for which a tentative map is required shall demonstrate the use of natural heating and cooling opportunities to the maximum extent feasible and that the dedication of solar easements may be required as a condition of tentative map approval for new parcels in order to protect solar access. It is intended that the provisions of this part shall prevail over any other provisions of this Ordinance Code which may conflict with any of the requirements herein. No tentative subdivision map shall be approved after the effective date of this part unless the provisions of this part are met.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-173.1. - Definitions.

The following definitions shall apply to this part:

(a) Solar energy system:

(1) Any solar collector or other solar energy device whose primary purpose is to provide for the collection, storage and distribution of solar energy for space heating, cooling or hot water heating; or

(2) Any structural design feature of the building whose primary purpose is to provide for the collection, storage and distribution of solar energy for space heating, cooling or hot water heating.

(b) Solar access: For purposes of this part, "solar access" shall mean any of the following:

(1) The provision of direct sunlight to a south wall and/or south roof of a principal structure from 9:00 a.m. to 3:00 p.m. Pacific Standard Time on December 21 sufficient for the effective use of a solar energy system.

(2) The provision of direct sunlight to a solar energy system from 9:00 a.m. to 3:00 p.m. Pacific Standard Time on December 21.

(3) The provision of direct sunlight to the southernmost end of the buildable portion of a lot from 9:00 a.m. to 3:00 p.m. Pacific Standard Time on December 21.

(c) Solar easement: The right of receiving direct sunlight across the real property of another to protect solar access.

(d) Burdened property: Property for which development restrictions are placed, or proposed, in order to protect solar access to benefited property.

(e) Benefited property: Property for which solar access protection is granted or proposed.

(f) South wall: A southern wall area of a principal structure facing within 45 degrees of due south. In the event wall areas are located 45 degrees from south, the south wall shall be defined as the wall area facing southwest.

(g) South roof: A southernmost roof area of a principal structure facing within 45 degrees of due south. In the event roof areas are located 45 degrees from south, the south roof shall be defined as the roof area facing southwest.

(h) Due south: The direction of the south terrestrial pole.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-173.2. - Energy conservation plans.

(a) Subsequent to October 1, 1980, the design of all minor and major land subdivisions as defined by Section C12-5.20 of Santa Clara County Land Development Regulations shall provide, to the maximum extent feasible, for future passive or natural heating and cooling opportunities in the subdivision. An energy conservation plan shall be submitted with the tentative subdivision map. Such plans shall meet the design objectives of Paragraphs (b) and (c) of this section. The development shall be designed to optimize the number of future buildings receiving sunlight sufficient for using solar energy systems. All proposed structures and vegetation shall be sited to provide solar access to a south wall of the greatest possible number of buildings. To the extent the provision of south wall solar access is not feasible on one or more lots, these lots shall be designed to provide solar access to a south roof.

(b) Specific passive or natural heating opportunities to be contained in an energy conservation plan shall include, but are not limited to, design of streets, lot size and configuration to permit a maximum number of buildings to be oriented so that south wall and roof areas may face within 25 degrees of due south. To the extent solar access is not impaired, existing vegetation should be used to moderate prevailing winter winds on the site.

(c) Specific passive or natural cooling opportunities to be contained in an energy conservation plan, to the extent solar access to future buildings is not impaired, include design of lot size and configuration to permit buildings to receive cooling benefits from both prevailing summer breezes and existing shading vegetation.

(d) For the purposes of this part, "feasible" means capable of being accomplished in a successful manner within a reasonable period of time, taking into account economic, environmental, social and technological factors. Such factors include, but are not limited to, contour, orientation, grading, slope stability, tree preservation and access to existing streets. It is the intent of this section that the provision of natural heating and cooling opportunities in subdivision design be included with all other design considerations and be pursued whenever the benefits in terms of energy conservation and the potential for solar energy development are greater than the associated negative impacts. It is not intended that the requirements of this section result in reducing densities, reducing the percentage of a buildable lot area that may be occupied by a structure thereby precluding construction under the applicable zoning in force at the time the tentative map is filed, or cause the unnecessary destruction of existing trees.

(e) In cases where a proposed building configuration has been developed at the tentative map stage, energy conservation plans shall include a sketch of the approximate shading pattern cast by all remaining and proposed vegetation exceeding, or capable of exceeding, ten feet in height and all structures on December 21 from 9:00 a.m. to 3:00 p.m. Pacific Standard Time. This requirement shall apply to structures and proposed or existing vegetation located within 150 feet and within 45 degrees of due south from any proposed south wall or south roof area. In addition, in order to determine the potential for natural heating and cooling opportunities on the site, energy conservation plans shall indicate the approximate location and type of all trees, or groups of trees, exceeding, or capable of exceeding, ten feet in height that are located within 100 feet of a proposed structure.

(f) In cases where a building configuration has not been developed at the tentative map stage, the energy conservation plan shall indicate the extent to which future construction could receive solar access by indicating the approximate location and type of all trees, or groups of trees, exceeding, or capable of exceeding, ten feet in height that are located within the buildable portions of proposed lots or are within 150 feet and within 45 degrees of due south from the southernmost end of the buildable portion of proposed lots. Prior to the effective date of this part, the planning staff shall develop and the Planning Commission shall adopt specific guidelines for preparing energy conservation plans and determining shading patterns.

(g) Exemptions may be granted by the advisory agency from the design objectives of Paragraph (a), (b) or (c) of this section upon a finding that either:

(1) Compliance will result in reducing densities below what would normally be allowed by the advisory agency at the time the tentative map is filed without the provisions of this section.

(2) Compliance is not feasible as defined in Paragraph (d) of this section.

(h) All applicants requesting an exemption pursuant to this section shall submit a written statement and sufficient supporting documentation with the energy conservation plan describing the basis for the claim. In submitting sufficient supporting documentation pursuant to this section, it is not the intent to require the initial submission of an alternative tentative subdivision map. Subsequent requests for alternative maps may be made as part of the approval process.

(i) The planning staff shall review any requested exemption and include recommendations as part of the staff report transmitted to the approving agency.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-173.3. - Solar access easements—General requirement.

(a) In proposed subdivisions where a building configuration has been developed at the tentative map stage, solar access easements created pursuant to this part shall be designed, to the extent feasible, to protect solar access to proposed south roof and south wall areas and any proposed site for a solar energy system. In proposed subdivisions where a building configuration has not been developed at the tentative map stage, solar access easements shall be designed, to the extent feasible, to protect solar access to the southernmost boundary of the buildable portion of a lot. In establishing the dimensions of a solar access easement, consideration shall be given to contour, configuration of the parcel to be divided, existing vegetation and the use of adjacent parcels.

(b) In cases where a building configuration is specified on the tentative map and upon finding that neither lot size, lot configuration or applicable zoning is sufficient to reasonably protect solar access to a proposed south wall, south roof or any proposed location for a solar energy system, the advisory agency may require the preparation and dedication of solar access easements as a condition of tentative subdivision map approval for any subdivision application containing one or more proposed lots under one acre.

(c) In cases where a building configuration is not specified at the tentative map state and upon finding that neither lot size, lot configuration or applicable zoning is sufficient to reasonably protect solar access to the southernmost boundary of the buildable portion of the lot, the advisory agency may require the preparation and dedication of solar access easements as a condition of tentative subdivision map approval for any subdivision application containing one or more proposed lots under one acre.

(d) Solar access easements shall not be required in cases where the lot that would be benefited is equal to or greater than one acre or where solar access is not available due to either existing vegetation, topography or surrounding development, or where other deed restrictions are sufficient to protect solar access. The establishment of a solar access easement is not intended to result in reducing development densities or reducing the percentage of a lot which may be occupied by a structure, or cause the unnecessary destruction of existing trees. The requirements of this section are not applicable to condominium projects which consist of the subdivision of airspace in an existing building where no new structures are proposed.

(e) Prior to the effective date of this part, the planning staff shall develop and the advisory agency shall adopt guidelines for preparing solar access easements, including a model solar easement form for general use.

(f) Solar access easements required pursuant to this part shall be recorded with the final subdivision map with the County Recorder.

(g) The provisions of this section shall be effective on October 1, 1980.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-173.31. - Same—Contents.

All solar access easements required pursuant to this part shall provide for the following:

(a) A description of the solar access easement in terms of specific area(s) on benefited property to which solar access is to be protected and a statement specifying that no structure, vegetation or land use shall cast a shadow so as to impede the passage of direct sunlight to more than ten percent of a protected area on a benefited property between 9:00 a.m. and 3:00 p.m. on December 21 or on any other date approved by the advisory agency. For purposes of this section, the easement shall protect and it shall be sufficient to describe only those specific areas on benefited property that would limit the height of structures and vegetation to under 50 feet on the burdened property in order to protect solar access.

(b) The burdens and benefits of the solar access easement as being transferable and running with the land to subsequent grantees.

(c) The solar access easement may be revised or terminated pursuant to Paragraph (e) of this section or by a modification in writing that is signed by all benefited and burdened property owners and recorded with the County Recorder. Said right of modification in writing shall not apply to the initial grantor of the easement.

(d) A diagram of the burdened property indicating in a manner easily understood by nontechnical persons the approximate height restrictions up to and including 50 feet on the property necessary to protect solar access to specific areas on benefited property.

(e) (1)

Because a solar access easement is not intended to unnecessarily burden properties, a statement shall be included specifying that subsequent to the development of a benefited property, restrictions on structures, vegetation and land uses due to a recorded solar access easement on a burdened property not required to protect solar access to a south wall or south roof or the site of a solar energy system shall be void and unenforceable provided a revised solar access easement signed by all affected benefited and burdened parties and a revised diagram pursuant to this section have been recorded with the County Recorder. The easement shall also contain a statement that upon refusal of an affected party to sign the modified solar access easement any other affected party may bring an action in court to determine what modification if any should be made to the easement and that costs of suit may be awarded to the prevailing party. This provision (e)(1) is not intended to and shall not increase the area burdened by any solar access easement on any property.

(2) In cases where applicable, zoning in force at the time the solar access easement is recorded would allow the construction of only one principal structure on the benefited property, the provisions of (e)(1) shall apply subsequent to final approval of the building permit for the principal structure or any detached solar energy system constructed on the benefited property at the same time as the principal structure.

(3) In cases where applicable zoning in force at the time the solar access easement is recorded would allow the construction of more than one principal structure on the benefited property, the provisions of (e)(1) shall apply subsequent to approval of a complete development plan for the benefited property that indicates the future location of all principal structures and the site of any detached solar energy system.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-173.4. - Appeal procedure.

Any person dissatisfied with a decision of the advisory agency pursuant to this part may appeal to the Board of Supervisors within 15 days of said decision.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-173.5. - Severability.

If any portion of this part is for any reason held to be invalid or unconstitutional by a decision of any court of competent jurisdiction, such decision shall not affect the validity of the remaining portions of this part.

(Ord. No. NS-1203.50, § 2, 4-21-80)

Exceptions & meaning →

Sec. C12-174. - Reserved.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Santa Clara County Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.