Sanger Municipal Code § 62-381 Vesting on approval

Sanger Municipal Code · 2026-10 edition · updated 2026-10-04 · Sanger

Cite as: Sanger Municipal Code § 62-381 · Text as of 2026-10-04

Sec. 62-381. - Vesting on approval.

(a) The approval or conditional approval of a vesting tentative map shall confer a vested right to proceed with development in substantial compliance with the ordinances, policies and standards described in Government Code § 66474.2. However, if Government Code § 66474.2 is repealed, the approval or conditional approval of a vesting tentative map shall confer a vested right to proceed with development in substantial compliance with the ordinances, policies, and standards in effect at the time the vesting tentative map is approved or conditionally approved.

(b) Notwithstanding subsection (a) of this section, a permit, approval, extension, or entitlement may be made conditional or denied if any of the following are determined:

(1) A failure to do so would place the residents of the subdivision or the immediate community, or both, in a condition dangerous to their health or safety, or both.

(2) The condition or denial is required, in order to comply with state or federal law.

(c) The rights referred to in this section shall expire if a final map is not approved prior to the expiration of the vesting tentative map as provided in section 62-368. If the final map is approved, these rights shall last for the following periods of time:

(1) An initial time period of two years. Where several final maps are recorded on various phases of a project covered by a single vesting tentative map, this initial time period shall begin for each phase when the final map for that phase is recorded.

(2) The initial time period set forth in subsection (c)(1) of this section shall be automatically extended by any time used for processing a complete application for a grading permit or for design or architectural review, if such processing exceeds 30 days from the date a complete application is filed.

(3) A subdivider may apply for a one-year extension at any time before the initial time period set forth in subsection (c)(1) of this section expires. If the extension is denied, the subdivider may appeal that denial to the legislative body within 15 days.

(4) If the subdivider submits a complete application for a building permit during the periods of time specified in subsections (c)(1) through (c)(3) of this section, the rights referred to in this section shall continue until the expiration of that permit or any extension of that permit.

(Code 1960, § 19.320)

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Sanger Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.