Earlier editions: 2026-09
Title 27 — PROCUREMENT OF PUBLIC WORKS›Chapter 27.30 — CHANGES
San Jose Municipal Code Part 1 Definitions
San Jose Municipal Code · 2026-10 edition · updated 2026-10-04 · San Jose
Cite as: San Jose Municipal Code Part 1 · Text as of 2026-10-04
27.30.010 - Application of chapter.¶
This Chapter sets forth the requirements for using Change Orders, Directed Change Orders, and Emergency Change Orders.
(Ord. 30308.)
27.30.020 - Definitions.¶
The definitions in this Part 1 govern the application and interpretation of this Chapter.
(Ord. 30308.)
27.30.030 - Change order.¶
"Change Order" means a written amendment to the Public Works Contract or work order, executed by both the City and Contractor, that does any of the following:
A. Changes the scope of work in the contract;
B. Adjusts the time for completing all or a portion of the scope of work in the contract;
C. Adjusts the Contractor's compensation to reflect any change in the scope of work or any time adjustment; or
D. Makes any other changes arising from a change to the scope of work, a time adjustment or an adjustment to the Contractor's compensation.
(Ord. 30308.)
27.30.040 - Directed change order.¶
"Directed Change Order" means a written amendment to the Public Works Contract or work order that meets the requirements of a Change Order except that it is unilaterally issued by the City.
(Ord. 30308.)
27.30.050 - Emergency change order.¶
"Emergency Change Order" means a Change Order or a Directed Change Order that provides for the Contractor to perform work necessary for the immediate preservation and safety of persons and/or property at or around the construction site.
(Ord. 30308.)
Get a plain-English answer with a citation back to this text.
Ask AI about this code