Chapter 27.18
San Jose Zoning Code · 2026-06 edition · ingested 2026-07-07 · San Jose
ENVIRONMENTAL MITIGATION MONITORING AND REPORTING
Sections:
27.18.010 Application of chapter. ¶
27.18.020 Incorporating mitigations.
27.18.030 Confirming completion.
27.18.040 Procurement documents.
T27:22.1
2026-Supplement 4
PROCUREMENT OF PUBLIC WORKS
§ 27.20.040
27.18.010 Application of chapter. ¶
This Chapter addresses the inclusion of environmental mitigation measures in a Public Works Contract.
(Ord. 30308.)
27.18.020 Incorporating mitigations. ¶
Every Public Works Contract will include appropriate requirements for the Contractor to complete the applicable environmental mitigation measures adopted by the City or other lead agency as a condition of approving the underlying project. (Ord. 30308.)
27.18.030 Confirming completion. ¶
The Director, in coordination with the Director of Planning, will document completion of the environmental mitigation measures required by the Public Works Contract before finally accepting the work performed under the contract. (Ord. 30308.)
27.18.040 Procurement documents. ¶
The procurement documents for any Public Works Contract must include appropriate provisions implementing this Chapter 27.18. (Ord. 30308.)