Part 1 — Purpose Part 2 Definitions
San Jose Zoning Code · 2026-06 edition · ingested 2026-07-07 · San Jose
Sections in this part
Part 3 Requirements for Electric Vehicle Charging Stations
Part 4 Expedited Building Permit Process for Electric Vehicle Charging Stations
Part 1
17.86.420 Permit review and inspection requirements. ¶
- A. The building official shall issue a building permit, the issuance of which is nondiscretionary, on the same day for complete in person appli-
PURPOSE
Sections:
17.88.010 Purpose. ¶
T17:316
BUILDINGS AND CONSTRUCTION
§ 17.88.300
17.88.010 Purpose. ¶
The purpose of the chapter is to provide an expedited, streamlined building permit process that complies with state law in order to achieve timely and cost-effective installations of electric vehicle charging stations.
(Ord. 29740.)
Part 2
DEFINITIONS
Sections:
17.88.200 Definitions. ¶
17.88.210 Building official. ¶
17.88.220 Electric vehicle charging stations. ¶
17.88.230 Electronic submittal. ¶
- 17.88.240 Feasible method to satisfactorily mitigate or avoid the specific adverse impact.
17.88.250 Specific adverse impact. ¶
17.88.200 Definitions. ¶
The definitions set forth in this part shall govern the application and interpretation of this chapter.
(Ord. 29740.)
17.88.230 Electronic submittal. ¶
"Electronic submittal" means the utilization of electronic e-mail or submittal via the internet. (Ord. 29740.)
17.88.240 Feasible method to satisfactorily mitigate or avoid the specific adverse impact. ¶
A "feasible method to satisfactorily mitigate or avoid the specific, adverse impact" includes but is not limited to, any cost effective method, condition or mitigation imposed on another similarly situated application in a prior successful application for a permit.
(Ord. 29740.)
17.88.250 Specific adverse impact. ¶
"Specific adverse impact" means a significant, quantifiable, direct, and unavoidable impact, based on objective, identified, and written public health or safety standards, policies or conditions as they existed on the date the application was deemed complete.
(Ord. 29740.)
Part 3
REQUIREMENTS FOR ELECTRIC VEHICLE CHARGING STATIONS
Sections:
17.88.210 Building official. ¶
"Building official" means the chief building official, or a regularly authorized deputy. (Ord. 29740.)
17.88.220 Electric vehicle charging stations. ¶
"Electric vehicle charging station" means any level of electric vehicle supply equipment station that is designed and built in compliance with Article 625 of the California Electric Code, as it reads on the effective date of this section, and delivers electricity from outside an electric vehicle into a plug-in electric vehicle. (Ord. 29740.)
17.88.300 Electric vehicle charging station requirements. ¶
17.88.300 Electric vehicle charging station requirements. ¶
A. All electric vehicle charging stations shall meet applicable health and safety standards and requirements imposed by the state and the city.
B. Electric vehicle charging stations shall meet all applicable safety and performance standards established by the California Electrical Code, the Society of Automotive Engineers, the National Electrical Manufacturers Association,
T17:317
SAN JOSÉ CODE
§ 17.88.300
and accredited testing laboratories such as Underwriters Laboratories and, where applicable, rules of the public utilities commission regarding safety and reliability.
- (Ord. 29740.)
Part 4
EXPEDITED BUILDING PERMIT PROCESS FOR ELECTRIC VEHICLE CHARGING STATIONS
Sections:
17.88.400 Applicability. ¶
17.88.410 Applications and documents. ¶
17.88.420 Permit review requirements. ¶
17.88.400 Applicability. ¶
A. This part applies to the issuance of building permits for electric vehicle charging stations in the city. All requirements of building permit applications in Title 24 for electric vehicle charging stations that are not addressed in this part shall remain in effect.
B. Electric vehicle charging stations legally established or permitted prior to the effective date of the ordinance codified in this chapter are not subject to the requirements of this chapter unless physical modifications or alterations are undertaken that materially change the size, type, or components of an electronic vehicle charging station. Routine operation and maintenance or like-kind replacements for electric vehicle charging stations shall not require a permit.
(Ord. 29740.)
17.88.410 Applications and documents. ¶
A. All documents required for the submission of an expedited electric vehicle charging station building permit application shall be made available on the city website.
B. Electronic submittal of the required building permit application and documents by email,
or the internet when in operation shall be made available to all electric vehicle charging station permit applicants.
C. The building official shall adopt a checklist of all requirements with which electric vehicle charging stations shall comply to be eligible for expedited review.
D. The electric vehicle charging stations permit process and checklist shall substantially conform to recommendations for expedited permitting, including the checklist contained in the most current version of the Plug-In Electric Vehicle Infrastructure Permitting Checklist of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" adopted by the governor's office of planning and research.
(Ord. 29740.)
17.88.420 Permit review requirements. ¶
A. The building official shall issue a building permit, the issuance of which is nondiscretionary, for complete applications that meet the requirements of the approved checklist and Part 3 of this chapter.
B. If an application is deemed incomplete, the building official shall issue a written correction notice to the applicant detailing all deficiencies in the application and any additional information or documentation or payment of fees required to be eligible for expedited permit issuance shall be sent to the applicant for resubmission.
C. The chief building official may require an applicant to apply for a special use permit if the official finds, based on substantial evidence, that the electric vehicle charging station could have a specific, adverse impact upon the public health and safety. Such decisions may be appealed to the city planning commission.
D. If a use permit is required, the city may deny such application if it makes written findings based upon substantive evidence in the record that the proposed installation would have a specific, adverse impact upon public health or
T17:318
BUILDINGS AND CONSTRUCTION
§ 17.845.020
safety and there is no feasible method to satisfactorily mitigate or avoid the adverse impact. Such findings shall include the basis for the rejection of the potential feasible alternative for preventing the adverse impact. Such decisions may be appealed to the city planning commission.
E. Any condition imposed on an application shall be designed to mitigate the specific, adverse impact upon health and safety at the lowest possible cost.
(Ord. 29740.)