Title 18 — ZONING›Chapter 18.48 — RIVER/CREEK CORRIDOR DEVELOPMENT
§ 18.51
Redding Zoning Code · 2026-06 edition · updated 2026-07-25 · Redding
18.51.010 - Purpose. ¶
A.
The Federal Emergency Management Agency (FEMA) requires that flood-hazard regulations be adopted by all agencies participating in the National Flood Insurance Program which was established by Congress for the purpose of minimizing flood losses by providing federally subsidized flood insurance for existing structures and reduced premiums for new structures. To participate in the program, the city must adopt and enforce floodplain-management measures to reduce the risk of flood losses. It is the purpose of the "FP" combining district to implement this federal mandate, to carry out the city's general plan policies regarding development in floodplain areas, and to provide land-use regulations in areas with properties situated within the designated floodplains of rivers, creeks, streams and water courses in order to:
1.
Protect human life and health, safety and welfare;
2.
Minimize public and private losses as a product of floods or construction in flood-hazard areas;
3.
Require that uses vulnerable to floods be protected against flood damage by incorporating floodproof construction standards in their design or be developed outside flood-prone areas at the time of their initial construction;
4.
Protect riparian corridors along waterways by reducing alterations to the natural floodplain and stream channels;
5.
Prohibit filling, grading, dredging or development which may individually or cumulatively cause flood damage or danger to life or property;
6.
Prevent stream erosion which may adversely affect the fisheries of streams and the river or cause loss of property;
7.
Prevent the construction of flood barriers which may unnaturally direct floodwaters or raise flood levels thereby increasing flood hazards in other areas;
8.
Protect areas of pleasing appearance to the community and visitors, enhance the natural environment through the provision of open-space, break up the monotony of continuous urban development and increase community pride;
9.
Make every effort to preserve and improve public access to and along the Sacramento River and creeks for riding, hiking, fishing and nature observation;
10.
Encourage development to occur outside of flood-prone areas. Discourage development within the onehundred-year floodplain;
11.
Reduce public liability and the need for expensive public works projects in flood-prone areas. Minimize damage to public facilities and utilities located in areas of special flood hazard;
12.
Preserve wildlife and wildlife habitat along the Sacramento River and area creeks from erosion, loss of vegetation, degradation of water quality and loss of thermal cooling;
13.
Ensure that adequate capacity for future urban runoff is reserved;
14.
Recognize the Sacramento River as an economic resource for tourism, commercial recreation, private recreation and public enjoyment;
Ensure that as a product of any encroachment into the floodplain, flood levels are not significantly raised on other properties;
16.
Ensure that stream velocities are not significantly increased, which could cause erosion above, below or across from an area of encroachment or realignment;
17.
Ensure that proposals to encroach into floodplains fully address the following issues:
a.
Size of stream, major or minor,
b.
Existing and future volume of water,
c.
Existing and future changes in the velocity of water,
d.
Impact on adjoining properties,
e.
Potential for increased erosion upstream or downstream,
f.
Potential for riprap and type of riprap,
g.
Riparian habitat,
h.
Fisheries and wildlife,
i.
Urban trails and fishing access,
j.
Water temperature,
k.
Aesthetics,
l.
General plan consistency,
m.
Liability, both public and private,
n.
Depth of floodplain and fill needed,
o.
Amount of existing usable area on parcel and additional area to be created,
p.
Maintenance responsibility and costs,
q.
Short-term gains versus long-term costs,
r.
Future increases in runoff.
18.
Protect individuals from buying land by identifying such land which is unsuited for intended purposes because of flood hazards;
19.
Minimize prolonged business interruptions;
20.
Minimize the need for rescue and relief efforts associated with flooding and generally undertaken at the expense of the general public.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.020 - Basis for establishing areas of special flood hazard. ¶
The areas of special flood hazard identified by the Federal Emergency Management Agency (FEMA) in the Flood Insurance Study (FIS) for Shasta County, California and Incorporated Areas dated December 16,
2021, and accompanying Flood Insurance Rate Maps (FIRMS) and all subsequent amendments and/or revisions, are hereby adopted by reference and declared to be a part of this chapter. The FIS and attendant mapping are the minimum area of applicability of this chapter and are supplemented by the Citywide Storm Drain Master Plan by Montgomery-Watson Engineers dated October 1993. These studies may be further supplemented by the Floodplain Administrator based upon the best available information, which may include any base flood elevation and floodway data available from a federal or state agency, other flooding studies, measured high-water elevations from historic flooding events, local topography, or other available information accepted by the City Engineer. The FIS, FIRMs, Montgomery-Watson drainage study and any other special studies are on file at the Development Services Department, 777 Cypress Avenue, Redding, California 96049-6071.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2438, § 6, 10-26-2009; Ord. No. 2668, § 1, 4-18-2024)
18.51.030 - General provisions.
A.
Applicability. The regulations of this chapter provide seven levels of protection within and along waterways of the "FP" Floodplain Overlay District by (1) generally prohibiting development within the floodway, (2) allowing only limited use and development in the flood fringe, (3) regulating uses and development on properties contiguous to the flood fringe and outside of the floodplain, which do not meet the minimum protection standards, (4) reviewing proposed development located in designated scenic corridors, (5) reviewing all development permits to determine that the permit requirements of this chapter have been satisfied, (6) reviewing all permits to determine that the site is reasonably safe from flooding, and (7) reviewing all development permits to determine if the proposed development adversely affects the floodcarrying capacity of the area of special flood hazard.
Accordingly, the regulatory scope of this chapter is as follows:
1.
These regulations and standards shall be applied uniformly to all lots which, after considering evidence from flood experience and engineering studies, are deemed subject to inundation by a 100-year flood or are within the "FP" District of the City limits. These regulations and standards are recommended for all lots meeting the same criteria within the City's sphere of influence.
2.
These regulations and standards shall apply to land outside the FEMA floodplain but within the "FP" District if the Planning Commission determines that the proposed development or use of the property bears relationship to the floodplain, has an unprotected lowest floor level of less than two feet above the 100-year flood elevation, may adversely affect a designated scenic corridor, or is in an area where a potential of bank undermining exists.
Property that is determined to be contiguous to, within, or partially within the floodplain subsequent to the adoption of this chapter is automatically subject to the regulations of the "FP" District without further consideration by the Planning Commission and City Council and shall be considered as if already zoned "FP" District.
4.
Ensure that floodplain development does not unnecessarily adversely affect a scenic corridor or riparian habitat.
B.
Interpretation.
1.
Except as provided for in this chapter, all development and uses in the base floodplain, including grading and fill, are prohibited without approval as specified herein.
2.
Any development within the floodplain, as determined by FEMA or higher floodplain elevation adopted by the Citywide Storm Drain Master Plan, shall comply with the standards of Section 60.3(a, b, c, and d) and Section 60.6(a) of the Rules and Regulations of the National Flood Insurance Program (44 CFR 59), incorporated herein by reference; the development standards of this chapter; and any conditions of approval applied to the development.
3.
Where there appears to be a conflict between a mapped boundary and actual field conditions and the conflict cannot be attributed to fill material being deposited to alter the elevations, the Floodplain Administrator and City Engineer may make interpretations, where needed, as to the exact location of the boundary of the floodway and 100-year floodplain consistent with the purpose of this chapter. Any person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation to the Planning Commission. Such appeals shall be reviewed consistent with the variance and exception procedures of Title 44, Section 60.6 of the Rules and Regulations of the National Flood Insurance Program (44 CFR 59, etc.). All costs for information necessary to make an interpretation shall be borne by the property owner and shall follow the procedures listed in Section 18.51.100.
4.
Backwater areas along streams, which rise or fall with the level of water in the adjacent stream, are considered to be within the base floodplain of the adjacent creek or stream unless proven by a registered hydrologist/ engineer that these water levels are not the same level as the base flood of the adjacent stream and may have a base floodplain of their own.
5.
When base flood elevation data has not been provided by federal, state, or local agencies, the owner shall be responsible for obtaining the information in accordance with Section 18.51.100.
6.
The Transportation and Engineering Department and Development Services Department will review proposed development to ensure that all necessary permits have been received from those governmental agencies from which approval is required by federal or state law, including Section 404 of the Federal Water Pollution Control Act Amendments of 1972 and CDFG's 1601 or 1603 Agreements.
C.
Department Records.
1.
In addition to the requirements of the building code and these regulations, and regardless of any limitation on the period required for retention of public records, the Floodplain Administrator shall maintain and permanently keep and make available for public inspection all records that are necessary for the administration of these regulations.
(Ord. 2381 § 15, 2007; Ord. 2374 § 26, 2006: Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2438, § 6, 10-26-2009; Ord. No. 2668, § 1, 4-16-2024)
18.51.040 - Uses prohibited in a flood-fringe area.
Structures or insurable improvements other than those listed in Sections 18.51.060 and 18.51.070 of this chapter shall not be located within the floodway.
The following uses in a floodway and flood-fringe area are prohibited unless the area is raised to a height of flood protection elevation (one foot above the base floodplain elevation) based upon an approved application for encroachment:
A.
The storage or processing of materials that, in time of flooding, are buoyant or explosive; that could be injurious to human, animal or plant life; or that may affect the capacity of the floodway or increase flood heights.
B.
The storage or parking of recreational vehicles as defined in Section 18.51.020 of this chapter within the floodway or floodplain of local streams.
C.
Underground storage of toxic or flammable substances that could be injurious to human, animal or plant life.
D.
Fences or walls unless the wall is along a street arterial. Street arterial walls must provide proper openings to allow passage of floodwaters.
E.
Swimming pool equipment.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.050 - Permitted uses within the floodway and flood fringe (not requiring a use permit).
The following uses are allowed within the floodway and flood fringe, provided they are allowed in the district combined with the "FP" District, meet the FEMA development standards, and are approved by all agencies with jurisdiction:
A.
Emergency actions approved by the city manager taken to protect existing property or facilities, not including concrete or asphalt riprap or narrowing the existing channel.
B.
Removal of water-deposited debris that could result in channel alteration subject to obtaining a grading permit and any permits from the State Department of Fish and Wildlife.
C.
Maintenance and repair to existing structures and yards pursuant to Chapter 18.48, Nonconforming Uses, Structures, Sites, Parcels and Signs, of this code and normal maintenance of existing channels, ditches or levees.
D.
Bridges with a design capacity to pass a one hundred-year flood without impedance of base floodwaters (bridges without piers or abutments in the floodway), taking into consideration full urbanization of the tributary area.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2590, § 24, 8-21-2018)
18.51.060 - Uses requiring a use permit within the floodway and flood fringe.
The following uses may be permitted by use permit in the "FP" District for the area of floodway and flood fringe, provided such uses meet the standards of Section 18.51.080 and Section 18.51.100 and are approved by all agencies with jurisdiction:
A.
In the Floodway or Flood Fringe.
1.
Dams or diversions for water supply, flood control, hydroelectric production, irrigation or fisheries enhancement. Levees and pumping stations.
2.
Actions approved by the State Department of Fish and Wildlife to enhance riparian or wildlife habitat. Streambank stabilization structures.
3.
Gravel- and sand-extraction operations along such waterways as Stillwater Creek, Clear Creek and the Sacramento River when a riparian and fishery reclamation plan has been approved by the planning commission and necessary permits have been obtained from the State Department of Fish and Wildlife and the Army Corps of Engineers, provided such operations will not broaden the floodplain nor direct flood flows out of the natural floodplain.
4.
Bridges with piers or abutments in the floodway or flood fringe.
5.
Water-related recreational uses not exceeding thirty consecutive days in any one year, excluding recreational uses that create permanent improvements or would result in destruction of banks.
B.
In the Flood Fringe Only.
1.
Public parks, picnic areas, playgrounds, boat launch, equestrian, pedestrian and bicycle trails, and golf courses which involve only the open use of land without permanent structures and which do not impede flood flows.
2.
Underground utilities including sewer, water, electric, telephone and cable lines properly floodproofed. Overhead electric lines greater than twelve kilovolts.
3.
Agriculture and hobby farming, including field crops, orchards, vineyards and grazing.
4.
New residential or substantially improved residential structures, agricultural, commercial, and industrial structures permitted by the underlying district regulations involved, provided floodproofing and/or floodprotective measures have been installed in a manner meeting with the approval of the floodplain administrator, city engineer, building official and fire marshal.
5.
Mobile homes or manufactured homes.
6.
The storage or parking of recreational vehicles within the floodplain of the Sacramento River.
7.
Unless otherwise noted, any use allowed by the district with which the "FP" District is combined may be permitted subject to obtaining a use permit and meeting the standards of Sections 18.51.090 and 18.51.100, provided the following are in evidence:
a.
The use meets the provisions of this chapter.
b.
The use is consistent with the Redding general plan.
c.
The use is consistent with the zoning of the parcel.
d.
Adequate floodproofing and/or flood-protection measures have been installed meeting with the approval of the floodplain administrator, city engineer, building official, fire marshal, and planning commission.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2590, § 25, 8-21-2018)
18.51.070 - Permitted uses within the city's "FP" district, outside the floodway and the flood fringe.
The following uses are permitted without a use permit in the "FP" district for the area outside the flood fringe:
A.
Any permitted use in the district combined with the "FP" district, provided there is not any encroachment into the base floodplain. The minimum setback from the base floodplain lines shall be thirty feet when adjacent to the Sacramento River where there is moving water. The minimum setback from the base floodplain line shall be fifteen feet, when adjacent to any creek. The lowest floor elevation of any habitable
structure shall be one foot above the base floodplain elevation, as identified by FEMA or the city's master storm drain study, whichever is highest, and the structure shall have year-round access not subject to inundation by a base flood of a depth of more than one foot.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.080 - Construction standards. ¶
Any structures or construction activities within the flood fringe or floodway shall be subject to the following:
A.
Construction, General.
1.
No construction or grading is to limit the capacity of the floodway or increase the base flood elevation unless the following requirements are met:
a.
Revision to the Flood Insurance Rate Map is prepared by the applicant's engineer and is adopted by FEMA in accordance with 44 CFR 65 to incorporate the increase in the base flood elevation.
b.
Appropriate legal documents are prepared in which all property owners affected by the increased base flood elevations consent to the impacts on their property.
B.
Anchoring.
1.
All new construction and substantial improvements subject to a 100-year flood shall be anchored to prevent flotation, collapse, or lateral movement of the structure.
C.
Construction Materials and Methods.
1.
All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage and flood-resistant materials, as specified in FEMA Technical Bulletin 2-93 entitled, Flood-Resistant Materials Requirement, when subject to a 100-year flood.
2.
All new construction and substantial improvements shall use methods and practices that minimize flood damage.
3.
All nonstructural elements that function as a part of the structure, such as furnace, hot-water/heater, air conditioner, electrical equipment, plumbing fixtures, and other service facilities shall be elevated to one foot above the base flood elevation or to the depth number specified on the Flood Insurance Rate Map (FIRM) or the Citywide Storm Drain Master Plan (whichever is more restrictive), plus one foot.
D.
Elevation and Flood-Proofing.
1.
Residential construction, and accessory structures thereto, including new or substantial improvement in flood zones A, AE, AO, or A1-30, shall have the lowest floor, including basement and machinery and equipment servicing the building, elevated a minimum of one foot above the base flood elevation, as determined by the FIRM maps, by the method in Section 18.51.100, or by the Citywide Master Storm Drain Study by Montgomery-Watson Engineers, whichever is more restrictive. The elevation of the lowest floor, including the basement, shall be certified by a registered professional engineer or licensed land surveyor per Section 18.51.080(D)(4) and (5). Said certification shall be submitted to the development services department for approval and to verify that certification requirements have been met.
2.
Nonresidential construction, including new or substantial improvement, shall either be elevated consistent with subsection (D)(1) of this section or together with attendant utility and sanitary facilities shall be required to do the following:
a.
Be floodproofed below the elevation required under Section 18.51.080(D)(1) of this section so that the structure is watertight with walls substantially impermeable to the passage of water.
b.
Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy.
c.
Be certified by a registered professional engineer, licensed land surveyor, or architect that the standards of this subsection and the standards required in FEMA Technical Bulletin 3-93, entitled Nonresidential Flood Proofing Requirements and Certification are satisfied. Such certifications shall be provided to the City's Development Services Department.
All new construction and substantial improvement with fully enclosed areas below the lowest floor (excluding basements) that are usable solely for parking of vehicles, building access, or storage and which are subject to flooding shall be designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for the entry and exit of floodwaters. Designs for meeting this requirement must meet the specifications in the FEMA Technical Bulletins 1-93 and 7-93, entitled Openings in Foundation Walls and Wet Flood proofing Requirements, respectively, and/or exceed the following minimum criteria:
a.
Be certified by a registered professional engineer or architect.
b.
Have a minimum of two openings on different sides of the structure, having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding. The bottom of all openings shall be no higher than one foot above grade. Openings may be equipped with screens, louvers, valves, or other coverings or devices, provided that they permit the automatic entry and exit of floodwaters.
4.
An Elevation Certificate for residential construction (FEMA Form FF-206-FY-22-152) of the lowest adjacent grade and lowest floor, based on construction drawings, shall be required prior to issuance of a building permit. Prior to pouring a foundation, the engineer shall provide written verification that the foundation form elevations are consistent with elevations shown on approved construction drawings. A second certification of the elevation of the lowest floor and utilities is required at the time of finished construction prior to final building permit approval (prior to occupancy). The Elevation Certificates must be prepared by a licensed land surveyor, registered professional engineer, or architect who is authorized by state or local law to certify elevation and shall be approved by the Development Services Department. Failure to submit elevation certification shall be cause to issue a stop-work order for a project.
5.
An Elevation Certificate (FEMA Form FF-206-FY-22-152) or a nonresidential Flood Proofing Certificate (FEMA FF-206-FY-22) for nonresidential construction is required prior to issuance of a building permit. Prior to pouring a foundation, the engineer shall provide written verification that the foundation form elevations are consistent with elevations shown on approved construction drawings. A second Elevation Certificate is required at the time of finished construction, prior to the final building permit.
E.
Substantial improvement and substantial damage determinations. For applications for building permits to improve buildings and structures, including alterations, movement, repair, additions, rehabilitations, renovations, substantial improvements, repairs of substantial damage, and any other improvement of or work on such buildings and structures, the Floodplain Administrator, in coordination with the Building Official, shall:
Estimate the market value, or require the applicant to obtain a professional appraisal prepared by a qualified independent appraiser, of the market value of the building or structure before the start of construction of the proposed work; in the case of repair, the market value of the building or structure shall be the market value before the damage occurred and before any repairs are made.
2.
Compare the cost to perform the improvement, the cost to repair the damaged building to its pre-damaged condition, or the combined costs of improvements and repairs, where applicable, to the market value of the building or structure.
3.
Determine and document whether the proposed work constitutes substantial improvement or repair of substantial damage.
4.
Notify the applicant when it is determined that the work constitutes substantial improvement or repair of substantial damage and that compliance with the flood resistant construction requirements of the building code is required and notify the applicant when it is determined that work does not constitute substantial improvement or repair of substantial damage.
F.
Standards for Utilities.
1.
All new and replacement water-supply and sanitary-sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the system and discharge from systems into floodwaters.
2.
On-site, waste-disposal systems shall be located to avoid impairment to them or contamination from them during flooding.
G.
Standards for Levees.
1.
Design criteria for levees shall incorporate adequate design, operation, and maintenance systems to provide protection from the base flood. The following requirements must be met:
a.
Freeboard. Riverine levees must provide a minimum freeboard of three feet above the water-surface level of the base flood. An additional one foot above the minimum is required within one-hundred feet of either side
of structures (such as bridges) riverward of the levee or wherever the flow is constricted. An additional onehalf foot above the minimum at the upstream end of the levee, tapering to not less than the minimum at the downstream end of the levee, is also required.
H.
Standards for Manufactured Homes.
1.
All manufactured homes that are placed or substantially improved within Zones A, AO, A1-30, AE, or AH on the Flood Insurance Rate Map or in the 100-year floodplain as identified on the Citywide Storm Drain Master Plan shall be elevated on a permanent foundation such that the lowest floor of the manufactured home, including machinery or equipment servicing the building, is elevated at least one foot above the base floodplain elevation and be securely fastened to an adequately anchored foundation system to resist flotation collapse and lateral movement.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2438, § 6, 10-26-2009; Ord. No. 2570, § 8, 4-4-2017; Ord. No. 2668, § 1, 4-16-2024)
18.51.090 - Existing parcels.
Existing parcels which, at the time of the effective date of this chapter, fall wholly within a floodplain or which have a residual area outside the floodplain which, by itself, does not meet the minimum lot size for the zoning district in which it is located or is less than five thousand square feet, whichever is less, may seek relief as follows:
A.
Petition to encroach into the flood fringe pursuant to Section 18.51.100 of this chapter;
B.
Seek a use permit to reduce any required setback by fifty percent, provided the floodplain area is placed in an open-space easement or dedicated to the city;
C.
Offer to dedicate the flood-fringe area to the city council in exchange for a dwelling-unit credit at a ratio of one unit per ten acres dedicated. Floodplain areas claimed by the state of California (reclamation board's designated floodway) are not eligible for a dwelling-unit credit. If the city council approves the exchange, the dwelling-unit credit could then be added to the density of any unsubdivided residential property of five acres or more in the city subject to the following:
1.
Any dwelling-unit credit must be used within five years of the date approved by the city council,
The density of the recipient property is not increased by more than twenty percent above what the Redding general plan otherwise would allow,
3.
The dw8elling-unit credit would not change the intended use shown by the general plan. For example, single-family would not become multiple-family,
4.
The development of the recipient property meets all other standards of the city pertaining to the property,
5.
The dwelling-unit credit is not in addition to any other bonus-density provisions sought for the property,
6.
Any dwelling-unit credit shall be in the form of a recorded agreement,
7.
The fringe area shall be calculated as follows:
a.
The base floodplain elevation and the edge of floodway shall be plotted on a one- to four-foot interval contour map of the property. The area then bounded by the edge of floodway, edge of base floodplain, and property lines shall then be planimetered to calculate the flood fringe. That number shall then be divided by ten and reduced to the nearest whole number. In the event the flood-fringe area is less than ten acres, one dwelling unit credit can be given.
8.
Any offer to dedicate flood fringe shall also include any adjacent floodway under the same ownership.
9.
Areas that are surrounded by floodway are not considered eligible for density credit.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.100 - Application for encroachment into the flood fringe. ¶
Property owners requesting permission to encroach into the flood fringe shall submit to the planning commission a hydraulic assessment of the base flood event prepared by a hydrologist who is a registered civil engineer. The cost of evaluating the analysis by the city or its consultant will be the responsibility of the applicant. The assessment shall meet the requirements for surveying, hydraulic analysis, and flood-flow frequency analysis, as outlined in the Guidelines and Specifications for Study Contractors prepared by FEMA, dated January 1995, or as subsequently amended. The city shall specify the hydraulic method and model to be used. Acceptable models for water-surface profiles include the latest version of the HEC-2,
HEC-RAS, HEC-HMS, HSPF, or other identical models. The city shall also require that calculations include the runoff from projected upstream urbanization of the tributary area, which may be obtained from the HEC-1 (HEC-HMS) hydrograph model.
Except along the Sacramento River, the assessment shall include a flood-flow frequency analysis obtained from HECWRC Program Model (CPD 13); and when there is insufficient gauged flood history, then the frequency analysis and associated levels of confidence shall be developed through sensitivity analysis of rainfall and runoff parameters impacts using HEC-1 (HEC-HMS). The results of the estimated frequency curve of the base flood event and resulting surface-water analysis shall be compared with a frequency chart using a ninety percent confidence limit and curves of standard deviations from the mean versus the frequency exceedance range, showing bands of confidence ranging from five hundredths to ninety-five hundredths.
Except along the Sacramento River, the assessment shall also include calculations and cross sections with a minimum interval of one hundred feet or less based on one-foot contour intervals and shall be submitted in a format for review by the city relative to FEMA flood insurance study guidelines. Additional information may also be required by the city as necessary to make a final determination.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.110 - Equal encroachment.
All requests for encroachments into a floodplain shall, to the greatest extent possible, assume equal encroachment on both sides of a stream, unless it can clearly be determined that the opposite bank above the base floodplain elevation which would be affected is unusable and not subject to erosion or undercutting from increased water velocity or raised flood levels or has been placed in a permanent openspace status to the extent that there would be no impact from an increase in the level of the base flood.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.120 - Environmental review.
Any application for encroachment into a flood-fringe area shall be subject to environmental clearance under the California Environmental Quality Act (CEQA). Any encroachment which significantly raises the projected flood levels on adjacent property or has the potential to increase erosion or diverts the natural flow of water shall be subject to an environmental impact report. The environmental impact report shall evaluate the area needed to make a determination, taking into consideration the cumulative and long-term impact of the proposed encroachment, the relationship of the project to the purpose of this chapter and alternatives to the proposed project.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.130 - Whenever a floodway or floodplain is to be altered or relocated.
The city will notify adjacent communities and the California Department of Water Resources prior to such alteration or relocation of a floodway or floodplain, submit evidence of such notification to the Federal Emergency Management Agency (FEMA) in a request for a conditional letter of map revision (CLOMR), and ensure that the flood-carrying capacity of the altered or relocated portion of said watercourse is
maintained. Whenever base flood-elevation changes are due to physical alterations, the city shall submit technical or scientific data to FEMA for a letter of map revision (LOMR) within six months of information becoming available or project completion, whichever comes first. Preparation of the conditional LOMR application by the applicant's engineer and approval of the conditional LOMR by FEMA will be required prior to issuance of a grading permit or building permit. Approval of the final LOMR is typically required prior to final building permit approval (certificate of occupancy).
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2438, § 6, 10-26-2009)
18.51.140 - Warning and disclaimer of liability. ¶
The degree of flood protection required by this chapter is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. It is probable that larger floods can and will occur, that the base flood may occur more often than the one percent frequency, and that flash floods may cause equal or greater damage. Flood heights inside the city limits may also be increased by manmade or natural causes in unincorporated areas. This chapter does not imply that land outside the areas of special flood hazards or uses permitted within such areas will be free from flooding or flood damage. This chapter
shall not create liability on the part of the city or any officer or employee thereof, the state of California, or the Federal Insurance Administration of the Federal Emergency Management Agency for any flood damages that result from reliance on this chapter or any administrative decision lawfully made thereunder.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.150 - Nonconforming uses in the floodway or floodplain.
A.
Floodway. If any nonconforming use or structure within the floodway is destroyed by any means, including floods to an extent of fifty percent or more of its market value as defined in Section 18.51.020, it shall not be reconstructed.
B.
Flood Fringe. Within the flood fringe, a structure may be reconstructed pursuant to the Nonconforming Uses, Structures Section of the City's Zoning Code, provided that upon reconstruction, the structure is adequately and safely flood proofed, elevated, or otherwise protected in conformity with the requirements of this chapter.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2668, § 1, 4-16-2024)
18.51.160 - Prohibitions. ¶
No building permit, license, certificate or other approval or entitlement shall be issued or given by the city or any department or employee thereof with respect to any improvement until the design of the improvement has been approved, as provided in this chapter, and the one-hundred-year flood elevation has
been determined. No certificate of use and occupancy or similar approval shall be issued or given for any improvement subject to use permit by this chapter, unless and until a representative of the development services department has certified that the improvement has been completed in accordance with the use permit approved pursuant to this chapter.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.170 - Nuisance. ¶
A.
Any improvement constructed, located, repaired, altered or maintained contrary to the provisions hereof, after the effective date of this chapter, is hereby declared to be unlawful and a public nuisance. If any permit is issued based on plans or other submittals by the applicant or his or her representative which are contrary to this chapter or planning commission approval, the applicant shall be responsible for correcting any work done under such permit in order to bring it into conformance with the approved design.
B.
Any grading or filling within the floodplain contrary to the provisions of this chapter is hereby declared unlawful and a public nuisance.
C.
When the city engineer has been made aware of the unlawful deposit of filling or grading within the floodplain, he or she shall advise the property owner by registered mail that such material shall be removed within thirty working days and that a riparian reclamation plan must be submitted for approval by the planning commission within the same period of time. Thereafter, the property owner will have nine months to implement the approved plan. The city-approved reclamation plan shall be recorded and shall remain in the title report until the city is satisfied that compliance has been achieved. Within thirty days of planning commission approval, the property owner shall deposit improvement security based on the value of reclamation improvements to ensure that the plan is implemented. Until such time as the property is restored to its natural conditions, no building, grading or use permit shall be issued for improvement of the property.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.180 - Standards for subdivisions. ¶
A.
Unless encroachment into the flood fringe has been approved by the planning commission or the city council, as the case may be, no subdivision shall be approved which creates lots that extend into any flood fringe or floodway area and no lots shall use areas subject to flooding by a base flood in order to meet minimum area requirements. The surface area of all lots in a subdivision that are not subject to flooding by a base flood shall be a minimum of one foot above the base flood elevation; or all lowest floor elevations, including basements, shall be at least one foot above the base floodplain elevation. Both the tentative and final maps for a subdivision shall show the boundary of the base flood. The boundary shall be certified by
the engineer preparing the map. All final maps shall also have a warning note on the map similar to Section 18.51.140 of this chapter.
B.
All final subdivision plans will provide the elevation of proposed structures, pads, and adjacent grade. If the site is filled above the base floodplain, the final pad elevation shall be certified by a registered professional engineer or surveyor and provided to the city engineer and shown on the final map. Approval of a conditional letter of map revision (CLOMR) by FEMA shall be required prior to grading.
C.
All subdivision proposals shall be consistent with the need to minimize flood damage.
D.
All subdivision proposals shall have public utilities and facilities, such as sewer, gas, electrical, and water systems located and constructed to minimize flood damage.
E.
All subdivision proposals shall have adequate drainage, provided to reduce exposure to flood damage. Certification of compliance shall be required of the developer.
F.
Subdivisions will be required to have the base floodplain elevation established with consideration of the tentative map.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
18.51.190 - Variances. ¶
A.
The Planning Commission shall hear requests for variances from the requirements of this chapter.
B.
Those aggrieved by the decision of the Planning Commission may appeal such decision to the City Council.
C.
In considering a variance application, the Planning Commission shall consider all technical evaluations, all relevant factors, standards, etc., specified in other sections of this chapter, and:
1.
The danger that materials may be swept onto other lands to the injury of others.
The danger to life and property due to flooding or erosion damage.
3.
The susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner.
4.
The importance of the services provided by the proposed facility to the community.
5.
The necessity to the facility of a waterfront location, where applicable.
6.
The availability of alternative locations for the proposed uses that are not subject to flooding or erosion damage.
7.
The compatibility of the proposed use with existing and anticipated development.
8.
The relationship of the proposed use to the comprehensive plan and floodplain-management/program for that area.
9.
The safety of access to the property in times of flood for ordinary and emergency vehicles.
10.
The expected heights, velocity, duration, rate of rise, and sediment transport of the floodwaters and the effects of wave action, if applicable, expected at the site.
11.
The costs of providing governmental services during and after flood conditions, including maintenance and repair of public utilities and facilities, such as sewer, gas, electrical, water system, and streets and bridges.
D.
Upon consideration of the factors of Section 18.51.190(C) and the purpose of this chapter, the Planning Commission may attach such conditions to the granting of variances as it deems necessary to further the purpose of this chapter.
E.
The Floodplain Administrator shall maintain the records of all appeal actions and report any variances to the Federal Insurance Administration of the Federal Emergency Management Agency in the biennial report.
F.
Conditions for Variances:
1.
Variances may be issued for the repair, rehabilitation, or restoration of structures listed on the National Register of Historic Places or the State Inventory of Historic Places, provided that the proposed repair, rehabilitation, or restoration will not preclude the structure's continued designation as an historic structure and the variance is the minimum necessary to preserve the historic character and design of the structure.
2.
Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result.
3.
Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
4.
Variances shall only be issued upon:
a.
A showing of good and sufficient cause, such as renovation, rehabilitation, or reconstruction. Variances issued for economic considerations, aesthetics, or because variances have been used in the past, are not good and sufficient cause.
b.
A determination that failure to grant the variance would result in exceptional hardship to the applicant.
c.
A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, or extraordinary public expense; create nuisances; cause fraud on or victimization to the public; or conflict with existing local laws or ordinances.
5.
Any applicant to whom a variance is granted shall be given written notice that the structure will be permitted to be built with a lowest floor elevation below the base flood elevation and that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation. It
is recommended that a copy of the notice be recorded by the Floodplain Administrator in the Office of the Shasta County Recorder and be recorded in a manner so that it appears in the chain of title of the affected parcel of land.
(Ord. 2343 § 2 (part), 2005: Ord. 2310 § 3 (part), 2003; Ord. 2301 § 3 (Att. A (part)), 2002)
(Ord. No. 2668, § 1, 4-16-2024)
Chapter 18.52 - "MR" MINERAL RESOURCES OVERLAY DISTRICT